H23G07: Environmental Geotechnology Presentation - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

H23G07: Environmental Geotechnology Presentation

Description:

H23G07: Environmental Geotechnology PRESENTATION MIXED TECHNOLOGY REMEDIATION OF A FORMER CHEMICAL WORKS, CADISHEAD, GREATER MANCHESTER By Ka Hang CHAN – PowerPoint PPT presentation

Number of Views:142
Avg rating:3.0/5.0
Slides: 13
Provided by: Informati652
Category:

less

Transcript and Presenter's Notes

Title: H23G07: Environmental Geotechnology Presentation


1
H23G07 Environmental GeotechnologyPresentation
  • Mixed Technology Remediation of a Former Chemical
    Works,
  • Cadishead, Greater Manchester

By Ka Hang CHAN Ting Ting LIM
2
Location
Cadishead Site
3
History
  • 1900-1965
  • Refining crude tar fractioning chemicals
  • 1965-2006
  • Storage facility for heavy fuel oils
  • 2006-current
  • Housing plan by Harrow Estates

4
Site Detail
  • Size of site
  • 6.5 hectare
  • 120,000m³ contaminated soil
  • 6,000m² of groundwater sources
  • Potential receptors
  • Local residents
  • Off-site groundwater receptors in sandstone
    aquifer
  • Adjacent sites
  • Future users of new homes

5
Contaminants
6
Remediation Methods
  • Alternatives
  • Traditional excavate dispose strategy
  • Ex-situ biological treatment followed by a
    groundwater treatment
  • Multi-technology Remediation
  • Ex-situ bioremediation for hydrocarbon
    contaminated soils (90,000m³)
  • Ex-situ chemical oxidation (500m³)
  • Multi-phase extraction (4000m²)
  • Air Sparging (1,000m² 1,000m²)

7
Air Sparging
  • Principles
  • Reducing concentration of volatile organic
    compounds(VOCs)
  • Air sparging lances driven into the aquifer using
    direct push technique
  • All vapours collected adsorbed by carbon

8
How Air Sparging works?
9
Air Sparging
Sparging Well
Air Blower
Installation of Sparging Lances
10
Air Sparging Pros Cons
Advantages Limitations
Simple implementation Cannot be used if free product exists
Easy equipments Potential for inducing migration of constituents
Cause minimal disturbance Produce a zone of reduced hydraulic conductivity
Short clean-up times
Low cost
11
Results
  • Over 6.5 tonnes of VOCs recovered
  • Project Costs - 6.3m
  • 85 - soil treatment
  • 15 - groundwater treatments
  • Unknown contamination sources
  • Odours VOC emissions
  • Grant planning permission
  • 392 dwellings on the 17 acre site
  • Best use of a combination of remediation
    techniques
  • Shortlisted in 2008 Brownfield Briefing Awards

12
  • Any Questions?
Write a Comment
User Comments (0)
About PowerShow.com