Title: Organisational context of PM
1Organisational context of PM
- Project Management
- (seminar)
2Organisation within the organisation
3Organisational structures and projects
- Hierarchical functional structure
- Matrix structure
- Pure project structure
4Hierarchical functional structure(linear-function
al structure)
- Longest history
- Heads of specialist functions report directly to
the CEO - The CEO is responsible for co-ordinating the
functions - Strict hierarchical chain
5Advantages
- Tight control at the top
- Logically represents the functions maintains
their power and prestige - Reduces duplication of functional effort
- Concentrates functional skills
- Simple reporting relations
- High utilisation
6Disadvantages
- Over-specialisation
- Parochialism of key personnel
- Weak co-ordination between functions
- It stifles the development of generalist leaders
- Ineffecient in fast changing and diverse market
environment - It imposes an increasing burden on the chief
executive as the rate of change increases - It requires extremely detailed pre-production
plans (extremely high rate of formalised work)
7Problems arise when
- Jobs requires greater resources than a single
function has. - Jobs cut across functional boundaries.
- Chief executive is overburdened with
co-ordination problems between functions. - The solution project manager(s) project
team(s)PM Office
8Projects in a functional structure
- Place in the structure
- Staff (team)
- Project manager
- What if the project team is not enough?
- Professional skills
- Resources of one or more functions
- Responsibility of the staff
- Project team
- Functional staff involved in the project
9Matrix structure without projects(true matrix)
- Division of labor in a matrix structure
- 2 dimensions
- Responsibilities
- Dual reporting
- Biggest advantages
- Managing complexity
- Managing changing environment
- Greatest disadvantages
- High number of conflicts
- Low speed of decision making
10Matrix organisation with projects
- If there are (continuously) too many projects for
the functional structure - One dimension of the division labour is the
project structure - A project management function is created
- The project management function group
- Separation
- The staff members are organisationally disengaged
from their previous decisions - Physically (communication, atmosphere)
- Reporting
- Linear
- Functional
11Problems with the project-matrix structure
- Latent responsibility and loyalty
- It affects career
- Dual reporting
- Confusion and conflicts on two levels
- Problems arise at the CEOs level
- Temporary structure uncertainty
12A possible solution strong corporate culture
- Shared views (and values)
- Different project teams
- Functional managers
13Advantages of the project-matrix structure
- Rapid response to changes
- Better balance between time, cost and resources
- Independent policies and budgets for different
projects - Clear definition of responsibility and authority
(project managers)
14Disadvantages of the project-matrix structure
- Requires significant effort from the top
management to - Define policies, procedures, authorities for the
whole organisation - Monitoring and controlling the balance of power
between project and functional managers - Ensuring the shared view on company objectives
(project and functional managers)
15The true project structure
- The usual business activity is in form of
projects - Frequent only in some industries
- Functions disappeared skills are concentrated in
project teams - Reserve staff (central pool of extra resources)
- Project teams are not temporary
16Advantages
- Clear project responsibilities and authorities
- Clear and controlled project budgets
- Better communication between project managers and
the CEO - Generalists managers are developed who can manage
change - Strong team loyalty and understanding
- Management costs are identified
- ? subcultures
17Does the true project structure exist?