Title: Optimal revision of uncertain estimates in project portfolio selection
1Optimal revision of uncertain estimates in
project portfolio selection
- Eeva Vilkkumaa, Juuso Liesiö, Ahti Salo
- Department of Mathematics and Systems Analysis,
- Aalto University School of Science and Technology
2Contents
- Project portfolio selection
- Optimizers curse
- Revised estimates
- Discussion
3Project portfolio selection
- Select a subset of projects within a budget,
e.g., k out of n projects with the aim of
maximizing the sum of the projects values µi,
i1,...,n - The values µi are generally unknown, whereby
decisions about which projects to select are made
based on estimates Vi about µi.
Estimates
Portfolio selection
Values
t
4Optimizers curse in portfolio selection
- Assume that the estimates are unbiased
- Portfolio maximization selects, on average,
overestimated projects ? the value of the
portfolio is less than expected based on the
estimation information (optimizers curse cf.
Smith and Winkler, 2006) -
- where is the index set of the selected
projects.
5Optimizers curse in portfolio selection
- Choosing 10 projects out of 100
- Values i.i.d with
- Unbiased estimates
- The larger the estimation error variance, the
harder it is to identify the best projects, and
the larger the difference between the estimated
and realized portfolio value
µi N(0,12)
Portfolio value
Vi µi ei, ei N(0,s2)
Standard deviation of estimation error
6Optimal revision of the estimates
- Estimates do not account for the uncertainties
- Use Bayesian revised estimates instead as a
basis for project selection - For instance, with µi N(mi,si2), Vi
N(µi,ti2) - The estimate V and the prior information m are
weighted according to their uncertainty.
where
7Optimal revision of the estimates
- With revised estimates the optimizers curse is
eliminated, that is - where is the index set of the projects
selected using revised estimates - Previous example
- Choosing 10 projects out of 100
- True values i.i.d. with
-
- Unbiased estimates
Portfolio value
µi N(0,12)
Standard deviation of estimation error
Vi µi ei, ei N(0,s2)
8Revised estimates and portfolio composition
- In the previous example, the projects values
were identically distributed, and the estimation
errors had equal variances - Then, prioritization among the projects remains
unchanged when the estimates are revised, because - In general, using revised estimates may result in
a different project prioritization than estimates
9Revised estimates and portfolio composition
Same error variances
Different error variances
- Choosing 3 projects out of 8
- True values i.i.d. With µi N(0,12)
- On the left, estimates with equal error variance
for all projects - On the right, four projects (dashed) more
difficult to estimate
Project value
Project value
Vi µi ei, ei N(0,0.52)
Vi µi ei, ei N(0,12)
Estimate
Revised estimate
Estimate
Revised estimate
10Revised estimates and portfolio composition
Same error variances
Different error variances
- On the left, equal error variances ? estimates
are shifted towards the common prior mean (zero)
in the same proportion - On the right the revised estimates of the
dashed projects are more drawn towards zero,
because the estimation information is less
reliable - Selection of 3 projects leads to different
portfolios depending on whether the estimates are
revised or not
Project value
Project value
Estimate
Revised estimate
Estimate
Revised estimate
11Revised estimates and portfolio value
- The use of revised estimates yields at least as
high overall portfolio value as the use of
initial estimates, i.e. - Example
- Selection of 10 out of 100 projects with values
µi N(3,12) - Population contains two types of projects
-
- Revised estimates yield higher portfolio value
for any non-trivial division between projects
with small and large estimation error variances
Optimal
Portfolio value
Revised estimates
Estimates
1) ei N(0,0.12) - small error variance 2)
ei N(0,12) - large error variance
Share of projects with large error variance
12Revised estimates and correct choices
- The share of correctly selected projects
increases with revised estimates in the normally
distributed case, i.e., -
- where K is the index set of the projects in the
optimal portfolio - In the previous example, the difference between
the two portfolios is statistically significant
(a0.05), when the share of projects with large
error variance is between 25-55
Share of correct choices
Share of projects with large error variance
13Discussion
- Selection based on project prioritization
resulting from estimates - The value of the portfolio will, on average, be
lower than expected - If there are differences in the projects
estimation error variances, too many projects
with large error variance will be selected - Suggestions for improving the selection process
- Accounting for the uncertainties by using revised
estimates - Sorting the projects in terms of estimation error
variances by, e.g., budget division