Project Management - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Project Management

Description:

Project Management Lecture Resource Analysis Plan Project planning Network analysis II Project planning Resource analysis Risk management Quality Budgets and cost ... – PowerPoint PPT presentation

Number of Views:62
Avg rating:3.0/5.0
Slides: 28
Provided by: Martin883
Category:

less

Transcript and Presenter's Notes

Title: Project Management


1
Project Management
  • LectureResource Analysis

2
Plan
  • Introduction
  • Project planning
  • Gantt chart and WBS
  • Project planning
  • Network analysis I
  • Project planning
  • Network analysis II
  • Project planning
  • Network analysis II
  • Project planning
  • Resource analysis
  • Risk management
  • Quality
  • Budgets and cost control
  • Project teams
  • Project planning
  • Resource analysis
  • Risk management
  • Quality
  • Budgets and cost control
  • Project teams

3
Why Network Diagrams?
  • Splits up the decision making process into
  • Method/logic - the order in which tasks have to
    be completed
  • Time estimates for the time to completion can
    be added to each task
  • Resources these can be added and then analysis
    carried out

4
Resources
  • Resources may be
  • Storable
  • Remains available if not used and is only
    depleted by usage
  • Examples?
  • Non-Storable
  • Availability has to be renewed for each time
    period
  • Examples?

5
Loading
  • The assignment of work to an operator, machine or
    department
  • When too much work is required of a resource it
    is overloaded
  • If too little work is assigned to a resource it
    is underloaded
  • What are the implications if a resource is
    underloaded?

6
Limits
  • Time limited projects Projects where time is
    the overriding factor
  • They must be completed by a certain date
  • Resource limited projects Limited resources are
    available to complete the project
  • Think about the relationship between time and
    resources in a project?

7
Units of resource
  • It is desirable when possible to state the work
    required in units of time. (i.e. person/machine
    hours)
  • Example
  • To dig a hole 4m x 4m x 6m 96m3 will take one
    person 12 hours.
  • So 96m3 12 person hours of digging
  • Or 1 person hour of digging 8m3
  • How long would it take 12 persons to dig the
    hole?

8
Units of resource
  • Most tasks will NOT have a linear relationship
    between the units of resource employed and the
    activity duration
  • IS Team working factors?
  • Communication overhead?
  • Increased likelihood of sickness?

9
Linear vs. non-linear relationship
10
Exercise 1 Resource Analysis
11
Exercise 1
Draw a Gantt chart using earliest Start/Finish
Times
12
Resource analysis
  • Earliest Start Time

13
Resource analysis
  • Earliest Start Time

Now add the resource usage histogram
14
Resource analysis
  • Earliest Start Time

15
Exercise 1
Draw a Gantt chart using latest Start/Finish Times
16
Resource analysis
  • Latest Start Time

Now add the resource usage histogram
17
Resource analysis
  • Latest Start Time

18
Resource analysis
  • Latest Start Time
  • Earliest Start Time

19
Different types of resource
  • It is likely that more than on type of resource
    is being consumed by a project
  • For three types of resource we need three
    histograms
  • (See example in Lockyer and Gordon)

20
Resource Analysis
  • The same approach can be used to calculate the
  • Cumulative Resource Requirements
  • Average Resource Requirements (using earliest
    start and latest start)

See (Lockyer and Gordon, 1996)
21
Levelling Resources
  • Resources can be levelled by
  • Moving activities with float
  • Splitting up activities
  • Only really effective for those with float
  • Mooving activities with no float
  • Trade-off between extending project duration and
    reducing resource costs
  • Sometimes there is no choice

22
Levelling Resources
  • After resource levelling the Activity Network
    must be reviewed
  • Some tasks will now have no usable float (due to
    resource constraints)
  • This can be indicated by using dummy activities
    such as Waiting for programmer availability
  • It is likely that more than on type of resource
    is being consumed by a task

23
Project Effort Estimation
  • Need to know
  • Usual efficiency of working
  • Sickness/absenteeism rate
  • Other existing commitments (e.g. other projects)
  • Additional tasks (e.g. routine maintenance)
  • Holidays
  • Constraints on Facilities (e.g. availability of
    labs)
  • Cost of and availability of overtime etc.

24
Software Effort Estimation
  • Needs Historical Data
  • KLOC is not a good measure on its own
  • Complexity of the software can effect time taken
    for development
  • E.g. more efficient algorithms will take longer
    to design

25
Laws of Estimation
  • Parkinsons Law
  • Work expands to fill the time available
  • Brookes Law
  • putting more people on a late job makes it
    later

26
Why Network Diagrams?
  • Splits up the decision making process into
  • Method/logic - the order in which tasks have to
    be completed
  • Time estimates for the time to completion can
    be added to each task
  • Resources these can be added and then analysis
    carried out

27
Plan
  • Introduction
  • Project planning
  • Gantt chart and WBS
  • Project planning
  • Network analysis I
  • Project planning
  • Network analysis II
  • Project planning
  • Resource analysis
  • Budgets and cost control
  • Quality
  • Risk management
  • Project teams
Write a Comment
User Comments (0)
About PowerShow.com