Scheduling - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Scheduling

Description:

Contracts - SUNY Poly ... Scheduling – PowerPoint PPT presentation

Number of Views:176
Avg rating:3.0/5.0
Slides: 42
Provided by: sunyitEdu
Learn more at: http://people.sunyit.edu
Category:

less

Transcript and Presenter's Notes

Title: Scheduling


1
Scheduling
2
Scheduling
  • Putting the activities in chronological order
  • Chicken or the egg
  • Allows the PM to determine the time required to
    complete a project

3
Types of Schedules
  • Depend on Viewer
  • Simple bar chart (Gantt chart)
  • Tells owner progress
  • Activity on Node (AON)
  • Activity on Arrow (AOA)
  • Used by PM, supers, foremen
  • Short term schedules
  • Monthly , allows for close-up look at schedule

4
Developing Activity Sequence
  • Physical Relationship
  • An activity cannot start until a previous one is
    complete
  • Safety Relationship
  • Performing activities which cause a safety hazard
    to other activities
  • Resource Relationship
  • The amount of resources available at any time
  • Preferential Relationship
  • Contractors preference on activity order

5
Constructing Bar Chart
  • How should bar chart be laid out
  • Time on horizontal axis
  • Activity on vertical axis
  • Time of activity start based on position
  • Duration of activity based on length of line
  • Day start of day to start of day

6
Constructing Bar Chart
  • What time unit should be used
  • Work days
  • Hours
  • Weeks
  • What makes sense for your project
  • Bar chart size may dictate time units
  • Time unit dictates activity size

7
Constructing Bar Chart
  • Additional Info
  • Activity Value
  • Activity Cost
  • Activity Resource requirements

8
Constructing Bar Chart
  • Work days or Calendar days
  • Work days harder to follow
  • No weekends or holidays
  • Calendar days allow you to see concrete curing

9
Gantt Chart
  • Looks like a horizontal bar chart
  • Good for linear work
  • Good for providing an overview of the project
  • Not good for complex projects

10
Gantt Chart
11
Owners Chart
12
Activity Network Development
  • Network Models
  • Activity on Node
  • Precedence Diagram Method
  • Activity on Arrow
  • Network Characteristics
  • Discrete Activities
  • Deterministic Durations
  • Deterministic Logic
  • Activity Flow

13
Network Elements
  • Activities
  • Basic building block
  • Represent tasks
  • Must consume time and resources
  • Milestones
  • Notice to Proceed
  • Building Enclosed
  • Substantial Completion
  • Project Complete
  • Activity Relationships
  • Physical, Safety, Resource, Preferential

14
Precedence
  • Succeeding activities cannot start until
    preceding activities finished
  • Changes in duration of one activity affect all
    succeeding activities

15
Activity on Node
  • All activities occur at nodes
  • Arrows connect nodes and show relationships

16
Activity on Node
  • Basics
  • Unique Alphanumeric identifier
  • Unique description
  • Estimated Duration
  • Succeeding activity cannot start until preceding
    activity is finished
  • Need beginning and ending milestone to tie
    project together

17
Constructing an AON Network
  • Sequential logic
  • All activities preceding must be finished before
    next activity can start
  • Concurrent Logic
  • 2 or more activities can be worked at one time

18
Constructing an AON Network
  • Multiple Successor Logic
  • 2 or more activities can be worked at one time
    after common predecessor is finished
  • Multiple Predecessor Logic
  • 2 or more activities need to be finished before
    next activity starts

19
Constructing an AON Network
  • Combinational Logic
  • 2 or more activities can be worked at one time
    after multiple predecessor activities are finished

20
Logic Errors and Problems
  • Incorrect Logic
  • Activities MUST have a logical connection
  • Paint color does not control the roofing
    application
  • Redundant Logic
  • Not incorrect
  • Can cause errors

21
Logic Errors and Problems
  • Logic Loops

22
Activity Numbering
  • Numbering Activities can make it easier to use
    schedule
  • Group like activities under the same general
    numbers
  • Activity Category
  • WBS can make it easy to categorize resources used
    to each activity
  • Work Classification
  • Numbers refer to a class of activity

23
Activity Numbering
  • Location
  • Number activity based on location on project
  • Responsibility
  • Numbers refer to who is responsible for work

24
Activity Numbering
  • Numbering Conventions
  • Directional
  • Numbers increase from start to finish of project
  • Numbering gaps
  • Leave gaps between numbers to allow for additions
    to schedule
  • Even/Odd Numbering
  • Even part of base contract
  • Odd additional work

25
Constructing a AON
  • Determine the relationships between the
    activities
  • Forward Pass
  • Determine when each activity can start based on
    the finish of the predecessor activities
  • Backward Pass
  • Determine when each activity can start based on
    when the successor activities start

26
Constructing a AON
Activity Duration Predecessors
A 6
B 4 A
C 10 B
D 10 C
E 1 D,G,I
F 6 A
G 8 F
H 10 A
I 6 H
27
Constructing a AON
  • Critical Path
  • Path through schedule which provides the shortest
    time to complete project
  • Total Float
  • Amount of time that activity can float without
    impacting CP
  • Free Float
  • Amount of time an activity can be delayed without
    effecting the early start date of the successor
    activity

28
Reviewing the Schedule
  • Is Schedule complete
  • Are Activity Duration Reasonable
  • Are Activity Relationships Complete
  • Are Activity Relationships Valid
  • Is Project Calendar Correct
  • Is Schedule Duration within Contract Time
  • Are Contractual Milestones Met

29
Analyzing the Schedule
  • Is Critical Path Reasonable
  • Are there Multiple Critical paths
  • What Activities are Near Critical
  • How does Work Flow
  • Are there Conflicts Among Concurrent Activities
  • Is there an Excessive amount of Work at any Time

30
Value Engineering
  • Provides alternatives to the proposed design
  • Save Owner
  • Must be as good or better than original design
  • Must save enough so that contractor can
    recover his cost of doing VE
  • Usually comes from contractors or engineers
    previous experience

31
Value Engineering
  • Can save either due to savings in time or
    materials
  • Ex Composite Wall and roofs
  • Material cost per sf is higher than regular roof
  • Labor cost is lower
  • Requires a crane

32
Value Engineering
  • Ex
  • Replace infiltrators with Eljen In drains
  • System size is reduced to 50
  • Also reduces amount of sand, clay, topsoil
  • Reduces dozer time and installation time
  • In-drain costs about 2x infiltrator

33
Updating Schedule
  • Frequency
  • Depends on
  • Complexity
  • More complex -gt more updates
  • Unexpected events
  • Update after event to determine new completion
    date
  • Helps team evaluate strategies to mitigate
    impacts
  • When specified
  • By contract documents

34
Updating Schedule
  • How
  • Gather Activity Status Info
  • Update Date when the info is gathered
  • Activity status
  • Actual start date meaningful work begins
  • complete
  • Work in place -gt work in place/planned work
    quantity
  • Time expended -gt time expended/ planned duration
    (only good for time dependent activities like
    concrete curing)
  • Cost Incurred - gtcost incurred/planned cost
    (depends on actual resource productivity being
    constant and resource costs not varying)
  • Resource used -gt Resource Used/Planned resource
    amount

35
Updating Schedule
  • How
  • Activity status
  • Remaining duration Remaining Work
    quantity/Anticipated Productivity
  • Actual finish date all completed activities
  • Provides data for future jobs
  • Gathering Data
  • Direct observation, Update meetings, field
    reports, turnaround reports, photos and videotape

36
Analyzing Schedule Status
  • What is the basis for evaluating schedule status?
  • Usually the original schedule is the baseline
  • What is planned completion date
  • Is updated schedule completion date same as
    baseline
  • If not why not (is there an error)

37
Analyzing Schedule Status
  • Has the critical path shifted?
  • If so why
  • Are CP activities really critical
  • Has the float changed on any activities?
  • Has weather become a factor for any activity
  • Are there trends worth watching
  • Any changes since last update?

38
Modify and Revise Schedule
  • Revise network logic
  • Change duration to meet contracted completion
  • Reflect changes in planned means and methods for
    completing activity
  • Shift activity to better time (summer for
    concrete)

39
Modify and Revise Schedule
  • Revise Activity Durations
  • Planned quantity of work has changed
  • Amount of resources has changed
  • Productivity is either higher or lower than
    planned
  • Add Delete Activities
  • Scope of work changed
  • Activities divided into smaller activities

40
Review and Analyze Schedule
  • Make sure new schedule does not contain errors
  • Implement updated schedule

41
Out of Sequence Work
  • Why?
  • Keep crews busy
  • Preparatory work starts early
  • Gives crew a chance to test means and methods
  • Preserve Schedule Logic
  • Shorten successor activity caused by out of
    sequence work
  • Keep all other logic intact
Write a Comment
User Comments (0)
About PowerShow.com