Title: Infrastructure Planning Commission Consenting procedures and the role of the Local Authority
1Infrastructure Planning CommissionConsenting
procedures and the role of the Local
Authority Mark Wilson Nikita
PerepelovIPC Case Team for The Isles
scheme 1 September 2011
2What we will be covering
- The IPC process whats different
- The special role of the Local Authorities
3The Planning Act 2008- Overview
1
2
3
4
5
6
Recommend / Decision
Post Decision
Pre-application
Acceptance
Pre-examination
Examination
Times in bold are statutory
4So whats different?
- Statutory engagement with the public and
consultees - Frontloading, including pre-application advice
- Applications not appeals
- Statutory deadlines
- Inquisitorial examination
- Stack of new, detailed rules and regulations
- Single consenting regime- associated
development and other regulatory and
environmental consents and licenses
5But whats been kept the same?
- Decisions on the relevant types of scheme are not
taken by the Local Planning Authority- as was the
case before the Planning Act 2008 regime was
established (e.g. before the 2008 Act, DECC were
the consenting authority for generating stations
with a capacity greater than 50 MW) - It is therefore a myth that the IPC has taken
control away from local decision makers
6Guidance and Advice
Advice Note 11Working with public bodies in the
infrastructure planning process (part 1)
IPC Guidance
IPC Advice
7Pre-application work
Getting the application right
- Consultation with the community (SoCC and s47)
- Consultation with prescribed bodies (s42)
- Environmental screening and scoping, PEI and ES
- Draft DCO and requirements
- IPC outreach and advice
8Pre-application the developer in the lead
Other organisations
General public
Developer
Potential interested parties
Land owners neighbours
Local authorities
Statutory consultees
Government Depts
9Post-application the Examining Authority takes
charge
Developers
Other organisations
General public
IPC Commissioners
Potential interested parties
Land owners neighbours
Statutory consultees
Government Depts
Local authorities
10Post-application work
- Acceptance s55 checklist and decision, Local
Authority views on adequacy of pre-application
consultation undertaken - Pre-examination registration, outreach, relevant
reps, principal issues, preliminary meeting - Examination timetable, written reps, hearings
(issue-specific, compulsory acquisition, open
floor), site visits, Local Impact Report - Recommendation report and (in future) SofS
decision - Throughout website updating, media management
11Changes to the regime- Localism Bill
- Present version of the Bill does not introduce
significant procedural changes (statutory
deadlines remain) - Flagship change is formal abolition of the IPC
and Ministerial decision-making in all cases - Case-by-case Ministerial direction on future
treatment of existing projects - Revised definition of relevant Local Authority
- Greater discretion at acceptance SoS can accept
application if she considers it satisfactory
12Local Authoritys Role- Summary
- Negotiating the terms of any s.106 agreement and
development consent obligations - Consulted by the developer on the content of the
SoCC - Statutory consultee, including on the drafting of
the DCO and requirements - Adequacy of consultation representation
- Representations key issues (pre-examination),
written and oral (examination) - Local Impact Report
- Enforcement, discharging requirements (?)
13Contact us
Infrastructure Planning Commission (IPC) Temple
Quay House Temple Quay Bristol BS1 6PN 0303 444
5000 ask for Mark Wilson or Nik
Perepelov mark.wilson_at_infrastructure.gsi.gov.uk ni
kita.perepelov_at_infrastructure.gsi.gov.uk www.indep
endent.gov.uk/infrastructure