Stage 3: Execution and Control - PowerPoint PPT Presentation

About This Presentation
Title:

Stage 3: Execution and Control

Description:

Stage 3: Execution and Control Earned Value Analysis MS Project and EVA More on Goldratt This is the third stage Of the . What were the first two stages? – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 47
Provided by: Jame3272
Learn more at: http://burns.ba.ttu.edu
Category:

less

Transcript and Presenter's Notes

Title: Stage 3: Execution and Control


1
Stage 3 Execution and Control
  • Earned Value Analysis
  • MS Project and EVA
  • More on Goldratt

2
This is the third stage
  • Of the.
  • What were the first two stages?

3
What were the deliverables of the first stage?
  • Project manager selected
  • Requirements document
  • Project charter
  • Project team selected
  • Signature signoffs by the stakeholders

4
What were the deliverables of the second stage?
  • Project plan
  • Project budget
  • The whole point of the plan and budget is to
    GUIDE EXECUTION
  • Signature signoffs by the stakeholders attached
    to the project plan and budget

5
Now what happens? THIRD STAGE BEGINS!!
  • Project ramps up (begins)
  • Project executes in conformance to plan and
    budget
  • Execution is tracked relative to plan

6
Goldratts rules regarding execution
  • The project manager must stay focused
  • On what?
  • What about safety?
  • How does Goldratt maintain a static critical
    path?
  • Communicate and Inform

7
Freeze Requirements???
  • What are the PROS?
  • What are the CONS?

8
Freeze those requirements!!
  • Late-project creeping requirements are the most
    common source of cost and schedule overruns
  • Late-project creeping requirements are a major
    factor in project cancellations

9
Rather than freezing, use some kind of change
control system
  • Allows for some changes to happen, depending upon
    contractual considerations
  • Allows for the system to reject some proposed
    changes
  • Use of a CCB is considered a modern BEST PRACTICE

10
Forces pushing for late-project requirements
change
  • Competition intros new version of competitive
    product with unanticipated KILLER features
  • New work is undiscovered late in the project
  • A Wouldnt It be Great if scenario happens
  • End-users want changes because they now know more
    about their requirements than they did 18 months
    ago
  • Developers want changes because they have a great
    emotional and intellectual investment in all of
    the systems details

11
Knowledge Areas and Processes used in Stage III
  • Integration management
  • Project plan execution integrated change control
  • Scope management
  • Scope change control
  • Time management
  • Schedule control
  • Cost management
  • Cost control
  • Quality management
  • Quality control

12
Processes utilized in Stage III, Continued
  • Communication management
  • Information distribution, Performance reporting
  • Risk management
  • Risk monitoring and control
  • Procurement management
  • Contract administration

13
Controlling Changes to the Project Schedule
  • Perform reality checks on schedules
  • Allow for contingencies
  • Dont plan for everyone to work at 100 capacity
    all the time
  • Hold progress meetings with stakeholders and be
    clear and honest in communicating schedule issues

14
Cost Control
  • Project cost control includes
  • monitoring cost performance
  • ensuring that only appropriate project changes
    are included in a revised cost baseline
  • informing project stakeholders of authorized
    changes to the project that will affect costs
  • Earned value analysis is an important tool for
    cost control

15
Earned Value analysis--EV
  • Budgeted Cost of Work Performed (BCWP)
  • Also uses Budgeted Cost of Work Scheduled (BCWS),
    and
  • Actual Cost of Work Performed (ACWP)
  • When you complete an activity, you earn the
    budgeted value of that activity

16
Why Earned Value Analysis??
  • You cant tell what your true cost variance is
    because you dont know where you are relative to
    schedule
  • Suppose you are behind schedule but also you have
    spent less than what the schedule has called for.
    Are you really under budget?

17
An Example
Budget
Overrun???
Actual
Budget
TIME
18
Budgeted Cost of Work Performed (BCWP) Earned
Value
  • Defined as the monetary value of the work
    actually accomplished within the control period.

ACTIVITY
BCWP
1 12,000
2 30,000 3 16,000
58,.000
CUMULATIVE
19
BCWP
  • Suppose 100,000 has been budgeted for a task and
    the task is 50 complete
  • Then its earned value is 50,000

20
Budgeted Cost of Work Scheduled (BCWS) Planned
Value
  • Defined as the value of the work scheduled to be
    accomplished in a given period of time

ACTIVITY BCWS
1 12,000 2 30,000 3 33,000
75,000
CUMULATIVE
21
BCWS
  • What is the BCWS of a 10,000 task whose start
    date is still in the future?
  • What is the BCWS of a 10,000 task whose stop
    date is in the past?
  • What is the BCWS of a 10,000 task whose duration
    is 10 days and five days have already passed?

22
BCWS, Contd
  • The BCWS of a 10,000 task whose start date is in
    the future is 0 (goose egg)

23
BCWS, Contd
  • The BCWS of a 10,000 task whose stop date is in
    the past is 10,000

24
BCWS, Contd
  • The BCWS of a 10,000 task whose duration is 10
    days and five days have already passed is 5,000.

25
Actual Cost of Work Performed (ACWP)
  • Defined as the cost actually incurred and
    recorded in accomplishing the work performed
    within the control period

ACTIVITY ACWP
1 15,000 2 30,000 3
29,000
74,000
CUMULATIVE
26
Schedule Variance (SV)
  • Defined as the difference between the budgeted
    cost of work performed and the budgeted cost of
    work scheduled
  • BCWP - BCWS
  • Indicates the deviation between the work content
    performed and the work content scheduled for the
    control period

27
Cost Variance (CV)
  • Defined as the difference between the budgeted
    cost of work performed and the actual cost of
    work performed
  • BCWP - ACWP
  • A positive CV indicates a lower actual cost than
    budgeted for the control period, while a negative
    CV indicates a cost overrun

28
Its your turn
  • For each of the activities in the examples above,
    calculate
  • SCHEDULE VARIANCE
  • COST VARIANCE
  • Calculate cumulative schedule and cost variance

29
Schedule Index (SI)
  • Defined as the ratio BCWP/BCWS
  • A value close to 1 indicates an activity that is
    on schedule
  • Values greater than 1 suggest the activity is
    ahead of schedule
  • Values less than 1 indicate a schedule overrun

30
Cost Index (CI)
  • Defined as the ratio BCWP/ACWP
  • A value close to 1 indicates an activity that is
    on budget
  • Values greater than 1 suggest the activity is
    below budget
  • Values less than 1 indicate a budget overrun

31
Answers to Schedule and Cost Variance
  • Cumulative schedule variance -17,000
  • Cumulative cost variance -16,000

32
Answers to Schedule and Cost Index
  • Cumulative schedule index .77
  • Cumulative cost index .78

33
Updating cost and schedule estimates
  • BAC Budget at completion total budget of the
    project activities based on the original project
    plan

34
Updating, Contd
  • WR Work Remaining budgeted cost of the work
    not yet accomplished by the end of the reporting
    period
  • WR BAC - BCWP
  • ETC updated estimate of the cost of work
    remaining COST(WR)
  • EAC updated estimate of the total project cost
    ACWP ETC

35
Using MS Project for Earned Value Analysis
  • Before entering any actual cost or schedule
    information
  • YOU MUST FIRST SAVE YOUR PROJECT PLAN AS A
    BASELINE
  • Then you enter your actual costs
  • Then you enter your percentages complete
  • Now MS Project will do earned value analysis

36
To Enter Your Actual Costs into MS Project
  •  1.      On the Tools menu, click Options, and
    then click the Calculation tab.2.      Clear the
    Actual costs are always calculated by Microsoft
    Project check box.3.      Click OK.4.      On
    the View Bar, click Task Usage.5.      On the
    View menu, point to Table, and then click
    tracking.

37
More on Entering Your Actual Costs into MS Project
  • 6.      Drag the divider bar to the right to view
    the Act. Cost field
  • 7.      In the Act. Cost field, type the actual
    cost for the assignment for which you want to
    update costs. 

38
Goldratts rules regarding execution
  • The project manager must stay focused
  • On what?
  • What about safety?
  • How does Goldratt maintain a static critical
    path?
  • Communicate and Inform

39
Safety
  • The extra time a project professional puts into
    his or her time estimate to do a particular task
  • It is customary to assign tasks to project
    personnel and then to ask them how long it will
    take them to do the task, knowing full well that
    they will then be required to finish their task
    within their estimated time

40
Solutions
  • Take the safety out of the individual tasks and
    put it at the end of the critical path in the
    time buffer, called a project buffer
  • This means making the tasks roughly 50-60 as
    long as they would otherwise be.

41
More solutions
  • At the point where each feeding path intersects
    with the critical path, place another time
    buffer, called a feeding buffer. The feeding
    buffer protects the critical path from delays
    occurring in the corresponding non-critical
    paths.
  • When resources are needed on the critical path,
    these resources are advised ahead of time exactly
    when they must make themselves available. When
    that time comes, they must drop everything else
    and do the required critical tasks.

42
Measurement solutions
  • Measure progress only on the critical path what
    percent of the critical path we have already
    completed, taken in relation to where we should
    be according to the plan. This is all we care
    about!!
  • Have project leader measure progress on non
    critical paths in terms of unused buffer days

43
Shrinking the task time Effects
  • There is less procrastination
  • There is much more focus
  • There is less multitasking

44
What are the ramifications of a delayed software
product, intended for commercial sale?
  • Less market share
  • Less profit maybe no profit
  • Lower analyst profit expectations
  • Declining share price
  • Out of business?
  • How many firms has Microsoft driven out of
    business?
  • Ask Mitch Kapor (founder of Borland) what the
    implications of getting a product late to the
    marketplace are

45
(No Transcript)
46
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com