LHC Systems - PowerPoint PPT Presentation

About This Presentation
Title:

LHC Systems

Description:

LHC Systems Cryogenics .as seen by Beam Handlers G. Arduini, S. Redaelli Many thanks to: A. Butterworth, S. Fartoukh, M. Giovannozzi, A. Rijllart, L. Serio, F ... – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 36
Provided by: god113
Category:

less

Transcript and Presenter's Notes

Title: LHC Systems


1
LHC Systems
  • Cryogenics.as seen by Beam Handlers
  • G. Arduini, S. Redaelli
  • Many thanks to
  • A. Butterworth, S. Fartoukh, M. Giovannozzi, A.
    Rijllart, L. Serio, F. Zimmermann

2
Outline
  • LHC Cryogenic system overview
  • Instrumentation and Signals
  • Cryo-Organization during Beam Commissioning
  • Application SW
  • Cryogenics powering
  • Cryogenics commissioning with beam
  • What could go wrong during beam commissioning?
  • Tools needed
  • Summary

3
LHC cryogenic system layout
L. Serio
4
LHC Cryogenic System layout
  • No redundancy for sector 2-3 in case of problems
    with the cryogenic unit in point 2 and no fast
    cool-down possible
  • Naming
  • Q Cryogenic System
  • S, U Surface, Undergorund
  • C, R, I Warm compressor, Refrigerator,
    Interconnection Box

5
LHC Cryogenic Components in Tunnel
6
Instrumentation and signals
  • Available instrumentation and signals in the
    tunnel
  • Pressure gauges (PT)
  • Temperature gauges (TT)
  • Level gauges (LT)
  • Valve opening (CV)
  • Virtual flow meters at the valves (based on
    pressure drop and temperature measurements,
    tables on He characteristics, valve opening,
    etc..) (FT)

7
Instrumentation and signals
L. Serio
8
Instrumentation and signals
9
Cryo-Organization during Beam Commissioning
  • On-line
  • Planned 1 8 h shift on-call operators and
    experts
  • Possible 2 8 h shift on-call experts (as for
    HW commissioning)
  • Ideal 3 8 h shift on-call experts
  • In the case of process faults (e.g. spurious
    faults, partial HW faults) the presence of a
    cryo-operator could limit the recovery time and
    even avoid beam-dumps and could be essential in
    case of teething problems
  • Off-line
  • Cryogenic Performance Panel (CPP Chair L.
    Serio)
  • Analyze off-line, manage all aspects of cryogenic
    performance,
  • Study, propose improvements of functional
    procedure and consolidations,
  • Record and track cryogenic sub-system performance
    in relation to their manufacturing and test data.
  • Design and set-up of the tools for the additional
    on-line monitoring of the cryogenics during beam
    commissioning
  • ? provide crucial feedback for the steering of
    the beam commissioning

10
Application SW
  • High level of detail in the application available
    in CCC.
  • Possible to navigate through the Cryogenic
    system.
  • Four access levels (the first three with
    password)
  • Administrator omnipotent
  • Expert login for experts only, direct control on
    each piece of equipment of the cryo system.
    Possibility to change interlock level.
  • Operator can operate the system, accessing the
    equipment but cannot change interlock levels.
  • Monitor Read access only ? this is the mode in
    which we should use the application
  • Under deployment nominative access with
    role-based rights

11
Sector 7-8 Navigation bar
12
Sector 7-8 (arc)
  • GreenOK
  • YellowWarning
  • RedNot Ok
  • BlueInvalid Data
  • PurpleNot Avail.

13
Sector 7-8 Navigation bar
14
Sector 7-8 Inner Triplet L8 DFBX
15
Temperature overview for each sector
16
Signal overviews for the Sectors
Cold Mass temperatures
Pressures
He levels
Line C temperatures
17
Sector 7-8 (arc)
18
Trends
  • Predefined sets or operator defined
  • Possibility to select the trend of one parameter
    from overview or synoptic plot

19
Cryogenics Post-Mortem - General information
  • PM analysis based on check functions defined by
    experts
  • LabView Logic specified by the Cryogenics
    Performance Panel in Excel tables, interpreted by
    a LabView program, this is part of the Magnet PM
    analysis software provided by CO/MA.
  • Four PM event triggers CRYO_START,
    CRYO_MAINTAIN, QUENCH, ALARM. They can be
    triggered on request ? PM can be used also as
    analysis tool!
  • For the moment, only expert logic is implemented
  • The tools seem flexible it should be possible to
    add a beam-oriented logic for the PM analysis.
  • PM application retrieves data from the logging
    data-base
  • Delay of a few minutes before data are available
    for analysis
  • Inconsistency between the logging and measurement
    DB have been observed
  • Filtering and smoothing of the data before
    transfer to the logging DB can false the trends
  • ? why not accessing the measurement data-base?

20
Cryogenics Post-Mortem application - snapshots
Buttons that simulated 4 PM events (CRYO_START,CRY
O_MAINTAIN,QUENCH,ALARM)
Display of selected signals
Main table with results of PM analysis (analysis
type and results given)
Signals for the plot
Faulty signals (did not pass the test)
Signals with no data (last acquisition reported)
21
Some additional features
Sorting results (signal name, analysis
type) Possibility to save and retrieve the
results of the analysis are available and
required in particular if access to the
measurement DB is implemented
Signals to graph
22
Cryogenics conditions for powering
  • There will be three logic states for each
    powering sub-sector
  • Conditions to authorize magnet powering
    (CRYO_STARTTRUE and CRYO_MAINTAINTRUE)
  • Conditions that do not authorize magnet powering
    but if there is already current in the magnets
    there is no request for discharge (the conditions
    of magnet powering were met at the time of the
    start of powering but have disappeared meanwhile)
    (CRYO_STARTFALSE and CRYO_MAINTAINTRUE)
  • Conditions that do not authorise magnet powering
    and request a slow current discharge
    (CRYO_STARTFALSE and CRYO_MAINTAINFALSE)
  • 32 Powering sub-sectors
  • 3 types per sector
  • ITD1 (in IR2 and 8)DFBX (8 in total)
  • Matching Section standalone magnets _at_ 4.5
    KDFBM,DFBL,DSL (12 in total)
  • ARC DFBA (8 in total)
  • 4 RF modules

23
CRYO_START / MAINTAIN
  • No direct connection of Cryo with BIC but only
    with PIC
  • Only insulation vacuum is directly interlocked to
    cryogenics (lt10-3 mbar, expect a steady state of
    10-6 mbar if no leaks).
  • No direct connection (no interlocking) between
    Beam Vacuum and Cryogenics Bad beam vacuum ?
    Higher heat load ? CRYO_START and CRYO_MAINTAIN
    might disappear

24
Cryogenics commissioning with beam
  • Assumptions
  • The Cryogenics system should be fully
    commissioned during the HW commissioning period ?
    in that case its behaviour as a function of the
    powering levels (energy dependence) should be
    understood
  • The main remaining unknown is the interplay of
    the beam with the cryogenics system
  • Heat load on the beam screen due to
  • resistive dissipation of image currents
  • synchrotron radiation
  • electron cloud
  • Heat load on the cold masses due to
  • Nuclear inelastic beam-gas scattering (depending
    on the vacuum level)
  • Other type of beam losses (e.g. beam halo losses
    and energy deposition from the induced showers)

25
Cryogenics commissioning with beam
per aperture
600
900
1300
2200
L. Tavian LTC 2/6/2004 F. Zimmermann LTC
6/4/2005
26
Cryogenics commissioning with beam
LHC Design report L. Tavian LTC 2/6/2004
  • A priori no need for dedicated time for
    cryogenics studies with beam but parasitic
    follow-up of the behaviour of the cryogenics in
    the presence of beam as a function of its
    parameters ? monitoring by Cryogenics Performance
    Panel. Its feedback will be crucial in steering
    the commissioning (in particular the increase in
    intensity)

27
Critical elements
  • Are there elements which are more critical than
    others?
  • Magnets
  • Q6 in IR1 and 5 (standalone magnet at 4.5 K) as
    evidenced by quench behaviour
  • MQTLs
  • In general SC magnets close to collimation areas
    and triplets in the interaction points
  • Q4 close to the beam dump area
  • Interaction with and feedback from MPP is vital
    to define critical elements
  • RF
  • Coupling with the rest of the sector might be an
    issue
  • Little margin for the pressure levels ? Beam dump
    at 1.5 bar
  • Cryo limit could be reached if we try to run with
    less cavities but higher field
  • Sector 2-3 no redundancy
  • Sector 3-4 and 4-5 are the most critical
  • From the point of view of the heat load (due to
    the additional load from the RF in IR4)
  • 4-5 is also critical from the point of view of
    the temperature due to the hydrostatic heads
    because of the slope on the LHC ring

28
What could go wrong during beam commissioning?
L. Serio AB/OP shut-down courses 7/3/2007
Cryo commissioning presently ongoing is the first
chance to test all the systems together and their
interactions. More might have to be learned when
we will start to inject beam.
29
What could go wrong during beam commissioning?
  • Quenches will be the routine
  • More than 14 cells or full sector ? recovery up
    to 48 hours
  • In case of fast discharge (even w/o quench) ? 2 h
    recovery (heating due to eddy currents).

L. Serio Training Day for the Commissioning of
the LHC Powering System 29/3/2007
30
What could go wrong during beam commissioning?
  • Strong correlation cryogenics vacuum
  • Vacuum transients might result from
  • excessive condensation of gases on the beam
    screen in the cells adjacent to a quenched one ?
    warming-up of the Beam Screen (to 40 K) might be
    required (few hours required) before injecting
  • Operation of the beam screen at temperatures
    close to 24 K (instead of 20 K) e.g. as a result
    of localized losses can result in emission of CO
    from the Beam Screen and reduced lifetime

V. Baglin Chamonix XIII
31
What could go wrong during beam commissioning?
  • Heat loads above specifications
  • In that case heat load measurements and
    comparison with expectations are essential before
    any increase in intensity
  • The resolution in heat load on the beam screen is
    0.5 W/cell to be compared with 280 W/cell as
    expected beam induced heat load at nominal
    intensity at 7 TeV. The expected margin in
    nominal conditions is 40 W/cell. Possible mean
    to see pressure bumps?
  • Local heating on cold masses can be measured with
    the resolution of a cell and localization within
    a cell might be possible by measurements of the
    temperature difference between magnets
  • EM-interference induced by the beam on the
    sensors
  • Past experience (SPS) has shown that sensors
    (e.g. temperature sensors) can be affected by the
    beam presence in particular for high intensity
  • Main difference sensors are not in direct view
    of the beam
  • Countermeasures redundancy and filtering
  • This should manifest itself as a
    non-deterministic behaviour of some of the
    control loops.
  • Could be a nightmare

32
Tools needed
  • Certainly we will need a summary of the Cryo
    Maintain/Start conditions for the different
    Sub-Sectors
  • Available soon

L. Serio
33
Tools needed
  • If the Cryogenics parameters start to drift on
    time scales of minutes probably there is not much
    that we (or the Cryogenics Expert) can do to
    re-establish stable conditions and save the
    beam
  • Follow-up of the trends when the mode of
    operation is changed (intensity or energy
    variation) is vital for planning the
    commissioning steps and minimizing down-time
  • We could specify analysis types relevant for LHC
    operation in the PM and trigger it via alarms (on
    trends) or external triggers.
  • Define virtual heat loads on beam screens and
    cold masses from temperature, flow, pressure
    measurements and heater setting (started by CPP)
  • Monitor heat load and temperatures on beam screen
    and cold mass, correlate with vacuum, beam
    intensity, beam losses and compare with
    expectations
  • Add temperature/flow trends to identify
    critical behaviour based on signal evolution
  • Later fixed-displays could take overonce the
    measurements and measurement devices are fully
    mastered and the needs and problems clarified

34
Summary
  • The behaviour of the cryogenics as a function of
    the powering levels (energy dependence) should be
    understood before beam commissioning ? a priori
    no dedicated time required during beam
    commissioning but the beam presence might
    introduce additional unexpected effects.
  • The presence of cryo-operators on 3 x 8 h shift
    during beam commissioning could help to sort-out
    potential teething problems of the cryo-system
    and to reduce beam down-time during the
    commissioning.
  • Interaction with CPP and MPP should be
    strengthened in order to focus on the critical
    elements and refine the analysis tools for beam
    commissioning.
  • Detailed SW tools exist to assist the expert in
    the control of the cryogenic system
  • For beam operation heat loads are probably the
    most meaningful parameters understanding of
    their trends could be very useful to identify and
    anticipate problems. The resolution (also
    spatial) should be sufficient.
  • Non-expert tools need to be enhanced ? The
    post-mortem analysis fishing in the measurement
    DB could be a powerful tool for the Beam
    Commissioning period although later fixed
    displays could be developed.

35
References
  • LHC Design Report Chapter 11 - Cryogenics
  • LHC-Q-ES-0004 (EDMS 710799) The circuit of the
    LHC cryogenic system
  • LHC-Q-ES-0003 (EDMS 710797) Functional analysis
    of the LHC cryogenic system process
  • L. Serio, Cryogenics and powering - Training Day
    for the Commissioning of the LHC Powering System
    29/3/2007
  • L. Serio, LHC Cryogenics AB/OP shut-down
    Courses 7/3/2007
  • L. Tavian, LTC 02/06/2004
  • F. Zimmermann, LTC 06/04/2005
  • V. Baglin, Vacuum Transients during LHC
    Operation, Chamonix XIII
Write a Comment
User Comments (0)
About PowerShow.com