Title: Rapid Assessment Process Project Strategic Plan City of Alamo Municipal Water and Wastewater Project Hidalgo County, Texas Presented to: Project Sponsor and BECC Staff Transition Meeting December 19, 2002
1Rapid Assessment ProcessProject Strategic
PlanCity of AlamoMunicipal Water and
Wastewater Project Hidalgo County,
TexasPresented toProject Sponsor and BECC
StaffTransition MeetingDecember 19, 2002
2Agenda
- General Aspects
- Environmental and Human Health Indicators
- Technical Approach, Objectives and Funding Plan
- Public Participation
- Sustainable Development
- Record of Project Coordination
3General Aspects
- Project Location
- City of Alamo is located in Hidalgo County, Texas
between McAllen and Harlingen. The community is
10 miles north of the U.S./Mexican Border.
4General Aspects
- State of Existing WTP and Distribution System
- Originally constructed in the 1920s and last
upgraded in 2002. - Systems include a 5.0 MGD WTP, storage reservoir,
clarifiers and filters. - The water storage capacity includes two elevated
storage tanks (150,000 and 300,000 gallons
respectively) and two ground storage tanks (1
million gallons each). - The water distribution system includes
approximately 370,000 linear feet of distribution
water lines and 3,750 retail water connections. - Concerns No back-up generator for emergencies.
Deteriorating elevated water storage tanks.
Exceedance of contaminant levels for total
trihalomethanes (TTHM) in the public water
system. Additional water rights. Water breaks due
to current pressure from new WTP. - Proposed Water Treatment System Improvement
Project - Upgrade and refurbish an elevated water storage
tank. - Improvements to the WTP systems to address TTHM
levels and pressure problems. - Addition of back-up power supply to the WTP.
- Improvements to eliminate water loss at HCID2
diversion point. - Additional Water Rights
5General Aspects
- State of Existing WWTP and Collection System
- The system includes a WWTP with a capacity of 2.0
MGD and consists of 8 lagoons located on 45
acres. - Sludge left in the first lagoon and deteriorating
lagoon embankments and perimeter fence. - The wastewater collection system contains 19 lift
stations and over 286,000 linear feet of sewer
lines. Most of these sewer lines are located near
the center of town. Approximately 40 of the
original clay pipe lines have been replaced with
PVC lines. - Approximately 100 original brick lined manholes
with infiltration and inflow problems during rain
events need replacement. - Concerns Expansion of WWTP based on TCEQs
inspection findings on capacity. Overall
maintenance of WWTP site. Deteriorating lift
stations, brick lined manholes and clay pipes.
Facility inventory. - Proposed Wastewater Treatment System Improvement
Project - Improvements to lift stations, brick lined
manholes, clay pipes and the addition of an SCADA
system. - Sludge removal in the first lagoon, lagoon
embankment repair work and replacement of
perimeter fence.
6General Aspects
- Total Estimated Cost TBD
- (Based on STEP I Application)
7General Aspects
Project Sponsor Profile
Prior Agency Support and Existing Studies
- Population 14,760
- Growth rate (90-00) 79.8
- MHI 23,928.00
- Unemployment rate 8.7
- Legal utility provider
- 3,750 water accounts
- 3,560 sewer accounts
- 17 employees (7 certified operators)
- Billing efficiency 99
- USDA infrastructure funding for construction of
new 5.0 MGD WTP and rehabilitation of City
streets. The City issued a Certificate of
Obligation for 2.9 million for the same project. - CDBG funding provided for reconstruction of
streets, waterlines and stormwater drainage in
colonias. - EDA funding for expansion of WWTP in 1992.
- No prior BECC or NADB assistance.
- 1994 WTP study for WTP expansion.
8Environmental and Human Health Indicators
- Human Health Indicators
- Water distribution deficiencies show existing WTP
capacity is not adequate to meet peak demands or
fire protection demands. - TTHM levels have created deficiencies in water
quality and threat to the health and safety of
the Citys residents. - Although existing statistics are not specific to
the City of Alamo, the Texas DOH has indicated
that cases of Cryptosporidiosis and Amebiasis
have been reported in Hidalgo County. The number
of cases per 100,000 people are as follow
9Environmental and Human Health Indicators
- Environmental Indicators
- The improvements to the WTP and WWTP systems will
enhance and protect the general health of the
population and environment. - Improvements will eliminate deteriorating lift
stations, infiltration problems in clay pipes and
brick lined manholes, which increase risk for
potential groundwater contamination. - Wastewater service to colonias and subdivisions
around the City will help reduce and eliminate
the current discharge of wastewater into septic
and outdoor systems.
10Environmental and Human Health Indicators
- Compliance with Environmental Norms Regulations
Including Violations - To comply with TCEQs requirements, the City must
initiate planning for the expansion of the
existing wastewater treatment plant when the
influent flow reaches 75 of the permitted
average daily flow for three consecutive months. - Additional compliance with the regulations
requires the City to take proper measures to
reduce the exceeding maximum contaminant levels
for total trihalomethanes (TTHM) in the public
water system Community has taken action on this
item.
11Technical Approach,Objectives and Funding Plan
- Project Objectives
- Rehabilitation and expansion of the water
distribution and wastewater collection system. - Expansion of the wastewater treatment plant.
- Refurbishing of an elevated storage water tank
and improvements to the water treatment plant. - Technical Approach
- Technical Assistance needed to develop the
following documents - Facility Plan and EID for water and wastewater
systems. - Financial Analysis.
- Public Participation Program.
- Final Design.
- Rate Study.
12Technical Approach,Objectives and Funding Plan
- Identified Potential Funding Sources
- Texas Water Development Board (TWDB)
- Funds may be available through TWDB Dfund II,
EDAP and CWTAP - North American Development Bank (NADB)
- BEIF and IDP
- Border Environment Cooperation Commission (BECC)
- PDAP program
- US Army Corps of Engineers
13Technical Approach,Objectives and Funding Plan
- Project Sponsor Financial Potential
- Revenues and Expenditures Summary (millions)
- 1999 2000 2001
- Revenues 1.4 1.5 1.4
- Expenses 1.1 1.2 1.1
- Net Available
- from Operations 0.3 0.3 0.4
- Existing Debt 2.9 million Annual Debt Service
TBA - (Bond due in installments of 7,000 to 155,000
thru August 2040 at interest of 4.5 percent.) - Water WW
- Average Monthly Bill 13.50 7.00
14Technical Approach,Objectives and Funding Plan
- PDAP Eligibility Criteria
- 1) Financial strategy for the entire
project Yes - 2) Project sponsor awareness of technical aspects
of project Yes - 3) Project sponsor has provided demonstration of
documentation Yes - support for the project
- 4) BEIF financing eligible Yes
- 5) C.N.A. and/or state/local gov. support, for
projects in Mexico NA - 6) Funds allocated on a per task basis Yes
- 7) Project coordination with all government
agencies involved Yes - 8) Value engineering as required under BEIF
program Yes
15Technical Approach,Objectives and Funding Plan
- BEIF Eligibility Criteria
- 1) Project located within 100 km of the
border Yes - 2) Project addresses a human health and/or
ecological issue Yes - 3) Project provides U.S. side benefits Yes
- 4) Project scope entails community infrastructure
in W/WW Yes - 5) Project sponsor to pursue Certification of
Project Yes - 6) Drinking water projects quality of water
only, not raw water supply Yes - 7) Projects have a funding strategy with funding
sources identified Yes - 8) Projects that discharge into U.S. side waters
to target US norms Yes - 9) Payment and benefit to public entity only not
private sector Yes - 10) For final design must meet eligibility
requirements NA - 11) Colonias projects, after 06-01-01,
eligibility based on established Yes - enforceable ordinances preventing
exacerbation or new colonias
16Technical Approach,Objectives and Funding Plan
Task Name Duration Start Finish
Application Process 11 days 07/25/02 08/08/02
Rapid Assessment Process 89 days 08/19/02 12/19/02
Technical Assistance Process 29 days 12/03/02 01/24/03
Project Development Process (TA, Public Participation, NEPA) 522 days 12/16/02 12/28/04
Project Design Process 325 days 10/01/03 12/28/04
TWDB Funding 66 days 10/01/03 12/31/03
NADB Rate Study 67 days 05/13/04 08/13/04
BECC Certification Process 39 days 10/18/04 12/09/04
17Technical Approach,Objectives and Funding Plan
- Agency Perspectives
- NADB
- An initial analysis of the proposed project in
regards to BEIF eligibility criteria provides a
sense that the project will be eligible for this
program. - An affordability will be completed to determine
any participation with BEIF grants including
construction, hook-up and transition support. - Loan assistance can be available for construction
and potential support may be provided by the IDP
for completion of a rate study and other
institutional capacity building needs.
18Technical Approach,Objectives and Funding Plan
- Agency Perspectives
- TWDB
- Because the project will address recently annexed
colonias, this project may be eligible for EDAP
funding through TWDB. - Water Rights purchases may be an eligible
activity supported by EDAP if the need for the
additional supply is related to the new service
provided to the colonias. - Project will meet criteria for application to SRF
and Dfund II.
19Technical Approach,Objectives and Funding Plan
- Technical Assistance Tasks
- Task Amount
- Water and Wastewater Facility Plan 160,000
- Environmental Information Document 40,000
- Financial Analysis 20,000
- Public Participation Program 10,000
- Project Certification Document 20,000
- Final Design TBD
- TOTAL 250,000
20Technical Approach,Objectives and Funding Plan
- Institutional Capacity Building
- The project sponsor identified such needs as a
capital improvement plan, rate study and the
development of public participation programs. - The Frank M. Tejeda Center has conducted an
Institutional Capacity Needs Assessment with the
City of Alamo.
21Technical Approach,Objectives and Funding Plan
- Institutional Capacity Building
- In specific, observations were made pertaining
to - Current Operating Violations
- Other Infrastructure Projects Ongoing or Planned
- Planning
- Project Development and Funds Management
- Outsourcing
- Operational Capacity
- Management Capabilities
- Governance
- Other Issues
22Technical Approach,Objectives and Funding Plan
- Potential Obstacles
- The City of Alamo informed the BECC that some
potential obstacles for the implementation of
this project may include water rights
acquisition, public perception of water quality
issues given existing litigation related to
levels of total trihalomethanes (TTHM) and
wastewater treatment plant technology, or site
changes. - Although the City has a water CCN inter-local
agreement with the City of San Juan, no obstacles
are anticipated to meet the proposed project
objectives. - Improvements and planning should take into
consideration that the Citys population does not
reflect additional winter Texans (between 6,000
and 7,000) that come to the area for
approximately 5-months every year.
23Public Participation
- Identification of Main Stakeholders
- City of Alamo and its residents
- Texas Water Development Board
- Texas Commission on Environmental Quality
- North American Development Bank
- Frank M. Tejeda Center
- Border Environment Cooperation Commission
- United States Department of Agriculture
- Secretary of State
- US Army Corps of Engineers
24Public Participation
- Local Politics
- The Mayor has been in office for the past 10-14
years. - Mayor and four commissioners, with a four-year
election term, and one municipal judge with a
two-year, are all elected at large. - The relatively new commission recently approved
the bond issuance to support the WTP improvements
and also passed rate increases for the utility,
displaying their commitment to sustainable
operations.
25Sustainable Development
- Minimum Criteria Requirements
- The City of Alamo made a commitment to comply to
all applicable minimum requirements for the
project in compliance with the BECCs sustainable
development criteria during the meeting held on
August 22, 2002 at the local City Hall, with
BECC, SOS and the Frank M. Tejeda Center.
26Sustainable Development
- Service Indicators
- Water service indicators all available water
service indicators were recorded, identifying all
relevant factors for the proposed infrastructure
project in the City of Alamo. - Sewer service indicators all available sewer
service indicators were recorded in relevance to
the proposed project. - Wastewater service indicators all available
wastewater service indicators were recorded in
relevance to all factors of the proposed project.
27Immediate Action Items
- Financial Potential separate accounts, identify
reserves and policy. - Formation of Steering Committee.
- Not Available Water, Sewer and Wastewater Service
Indicators. - Population of Future Colonias that will Become
Part of the Citys System. - Consultant Proposal.