Title: Sn
1HUSKROUA/1001/028
Foresters towards life-long learning for the
better forest management
Administrative requirements and procedures
Lesya Loyko FORZA NGO head, Project Manager July
4, 2012 Velky Saris, Slovakia
2 Start of implementation
- Distinguish between
- When the contract takes effect date of last
signature MAY 30, 2012 - When the Action starts as specified in art. 2.2
of the special conditions JUNE 1, 2012 - Costs are eligible only after Action start date!
- Procedures to award sub-contracts for goods,
services or works may be initiated before but
sub-contracts may NOT be concluded by the
Beneficiary or its partners before Action start
date
3 Implementation period
- Distinguish between
- When the implementation period ends 24 months
after Action start date (art. 2.3 Special
conditions) - MAY 31, 2014
- - When the execution period of the
contract ends - When final payment is paid by JMA OR
- In any case at the latest 18 months after the end
of implementation period - Costs are eligible only during implementation
period - Except costs relating to final reports,
expenditure verification and evaluation of the
Action
4C O M M U N I C A T I O N
- Regular meetings (in person and via skype)
- Make minutes of those meetings and use them as
working documents! - efficient external communication and both of them
should be in line with each other - Ensures everyone speaks with one voice
- To JTS(VATI) only through FORZA
5V I S I B I L I T Y
- Visibility - art. 6 General conditions and 7.1.8
Special Conditions - Is a contractual obligation!
- Art. 6.1 the Beneficiary must take all necessary
steps to publicise the fact that the EU has
financed or co-financed the Action. Such measures
must comply with the Communication and Visibility
Manual for EU External Actions and with the
provisions of the Hungary-Slovakia-Romania-Ukraine
Cross-border Cooperation Programme 2007-2013 - Art. 6.2 In particular, the Beneficiary shall
mention the Action and the EUs contribution in
information given to the final recipients of the
Action, in its internal and annual reports, and
in any dealings with the media. It shall display
the EU logo wherever appropriate
6V I S I B I L I T Y
- All material purchased, project outputs
(materials produced) and results, including
investments, as well as information and
communication material (letters, publications)
must have clear reference to EU contribution and
to the Programme (logo, statements) regardless
of the source of financing. Projects must display
the EU Programme logo at all events. The use of
Programme slogan is voluntary. - Publications must include a disclaimer This
publication has been produced with the assistance
of the European Union. The contents of this
publication are the sole responsibility of ltname
of the author/contractor/implementing
partner/international organisationgt and can in no
way be taken to reflect the views of the European
Union.
7Guidelines for visibility
- Programme Communication Guidelines include logos
and templates in the 4 languages!
8Communication guidelines and manual
- http//www.huskroua-cbc.net/en/useful-information/
communication-guidelines-for-projects/154 - Download and use
- Programme communication guidelines
- EC communication and visibility manual
9C O N T R A C T
- Grant contract special conditions and general
conditions and Annexes should be well studied and
followed - The provisions of the Special Conditions take
precedence over ALL the Annexes check art. 7 for
additions/derogations! - Annex II (General Conditions applicable to
European Community-financed grant contracts for
external Actions) takes precedence over the other
annexes - Beneficiary statement on conditions
- Project modification requests
10 Modification of the Action
- General Conditions Art 9.1
- Any amendment to the contract, including the
annexes, must be set out in writing in an
addendum - Contract can be modified only during its
execution period - Beneficiary must submit a request to the JMA one
month before the date on which the amendment
should enter into force, unless there are special
circumstances duly substantiated by the
Beneficiary and accepted by JMA - The maximum grant amount referred to in article
3.2. of Special Conditions may not be increased
(nor amount nor !)
11 Limited amendments
- General Conditions Art. 9.2 Beneficiary may
amend the budget and inform JMA in writing
without delay - When financial transfer between items within the
same budget heading, including cancellation or
introduction of an item - When financial transfer between budget headings
involving a variation of 15 or less of the
original amount (or as modified by addendum) in
relation of each concerned headings - Amendment should not affect the basic purpose of
the Action - This method cannot be used to amend the headings
for administrative costs or the contingency
reserve
12Limited amendments - example
- Contact your JTS programme manager in case of
doubt and to keep him/her informed in any case!
13B U D G E T
- Total -373 682,08 EUR
- EU financing 336 313,86 EUR (90)
- UA- 198 501,05 EUR(co-financing 10)
- SK 171 181,03 EUR(co-financing 55)
- 1st installment (80 of 90) 147 986,50 EUR
- SK 69 620,22 EUR
- 70 threshold 48 734,15 EUR request for fin.
verification
14B U D G E T
- Co-financing UA -10, SK-5
- Suggested make the co-financing equally during
the whole period of project implementation - Keep the record of co-financing
- Use of HUSKROUA website as the source of
documents
15Types of eligible costs
- The types of costs considered as eligible,
defined in Article 14 of the General Conditions
are - Eligible direct costs
- Costs must comply with the provisions of Article
14.1 14.2 - Contingency reserve
- Not exceeding 5 of the direct eligible costs.
It may be used only with the prior authorisation
of the contracting authority. - Eligible indirect costs (overheads)
- Flat-rate funding set at not more than 7 of the
total eligible direct costs.
16Staff costs
- The cost of staff assigned to the Action, not
exceeding those normally borne by the
organisation in question, corresponding to gross
salaries and including social security costs and
other remuneration-related costs. - Supporting documents
- Salary slip and proof of payment
- Social charges
- Contract
- Timesheet
- Calculation of the hourly/daily/monthly cost
17Human resources
- Involvement of human resources use the procedure
in the organization - TORs!
- Project staff directory/contacts
- Time sheets all human resources, timely,
accurately (see example - involvement in other
projects)
18Staff costs
- Preparation of monthly timesheet
- The eligible cost is the cost of the time devoted
to the project therefore, the timesheet is the
key document to ensure the proof of the
necessity of the claimed expense and that the
right amount is included in the accounting. It is
also essential in case of control. - Only paid hours may be
- includes (no un-paid extra hours)
19Costs
- Cost incurred by staff or any other person taking
part in the project - Costs may not exceed those normally borne by the
Beneficiary or partner - Any flat-rate for the subsistence costs must not
exceed the rates (per diems) set out in the
scales published by the European Commission at
the time of signing the contract - KEEP ALL the receipts as confimation
20Subsistence costs
- Supporting documents
- Take care to have information and documentation
proving for each travel - Number of participants
- Number of nights
- Total cost of subsistence costs for the travel
- The supporting documents needed are
- Invoice of the travel agency for accommodation,
including proof of payment - Reimbursement sheet or salary slip
- Meeting or event related documents, as in the
case of travels
21Equipment and supplies
- According to article 14.2, the purchase or rental
of equipment and supplies (new or used) is
eligible if it is specifically for the purposes
of the project. - The cost of related services, such as
transportation or installation is also eligible.
The costs have to correspond to market rates.
22Equipment and supplies
- Supporting documents
- Documents related to the award procedure,
including a contract and a purchase order (see
presentation on procedure). They have to give
evidence of the market rates. - Proof of delivery
- Invoice from contractor and proof of payment
- Proof of origin for equipment and supplies of a
unit cost on purchase on more than 5.000 ,
according to section 2.2. of annex IV of grant
contract (procurement by grant beneficiaries)
23Other costs, services
- includes the subcontracting expenditure and other
costs deriving directly from the requirements of
the contract, as described in article 14.2 of the
General Conditions. - Supporting documents
- Documents related to the award procedure (see
presentation on procedure). - Invoices from contractors and proof of payment
- Proof of delivery of services
- Any materials published
- Proof of respect of the rules for visibility
http//ec.europa.eu/europeaid/work/visibility/inde
x_en.htm - In case of events, the related document, as in
case of travel
24Contingency reserve
- The contingency reserve can only be used in case
of unforeseeable circumstances and with prior
approval by JTS. - The request for its use has to indicate which
categories of expenditure (1 to 6) will need
extra resources. - The reallocation will be shown in the financial
report and no accounting entries will be found
under this category
25Administrative costs
- (category 10)
- These costs are claimed as indirect costs and
- They are calculated as a fixed rate of the total
amount of direct eligible costs (categories 1 to
6). - The flat rate does not need to be supported by
accounting documents - It is incompatible with the receipt of an
operating grant from EC by the beneficiary or
partners, that is, if the beneficiary or partner
is receiving a grant to finance its regular
operating costs, no additional administrative
costs can be accepted as eligible, as it would be
double funding
26Ineligible costs
- Debts and provisions for losses or debts
- Interest owed
- Items already financed in another framework
- Purchases of land or buildings, except where
necessary for the direct implementation of the
action - Currency exchange losses
- Taxes, including VAT, unless the beneficiary (or
the beneficiarys partners) cannot reclaim them
and the applicable regulations do not forbid
coverage of taxes - Loans to third parties.
27Controls
- Article 16.2 of the General Conditions indicate
that the Beneficiary and its partners shall allow
EC, European Anti-Fraud Office (OLAF), European
Court of Auditors and any external auditor sent
by JMA/JTS carrying out verifications, including - Examining documents
- On-the-spot checks
- Examining accounting
- These inspection may take place up to 7 years
after payment of the balance. - JMA/JTS will conduct a yearly audit plan for
projects on a sample of the ones having submitted
reports with payment claims.
282. Eligibility Nationality rule
Tenderers must state, in the tender, the country
of which they are nationals by presenting the
usual proof of nationality under their national
legislation. This rule does not apply to experts
proposed by service providers taking part in
tender procedures or service contracts financed
by the grant. All countries mentioned in
previous slide are acceptable, REGARDLESS OF THE
PROGRAMME ELIGIBLE AREA!
292. Eligibility Rule of origin
- ENPI Regulation 1638/2006 art. 21.6 ALL supplies
and materials purchased under contracts financed
shall originate in a EU Member State or ENPI,
IPA, EEA country (Cf list in previous slide) - Includes the materials to be used for the
construction - Does not apply to Contractors equipment to be
used during the construction - Contractors must present proof of origin no later
than when the first invoice is presented, for
equipment and vehicles of a unit cost on purchase
of more than 5 000. - The certificate of origin must be made out by the
competent authorities of the country of origin of
the supplies (Chamber of commerce) and must
comply with the rules laid down by the relevant
EC legislation (see next slide).
302. Eligibility Rule of origin, customs
- The term origin is the economic nationality
of goods in international trade and is defined in
the relevant EC legislation on rules of origin
for customs purposes (Customs Code, Council
Regulation 2913/1992) - Goods originating in a country shall be those
wholly obtained or produced in that country (art.
23) - Goods whose production involved more than one
country shall be deemed to originate in the
country where they underwent their last,
substantial, economically justified processing or
working in an undertaking equipped for that
purpose and resulting in the manufacture of a new
product or representing an important stage of
manufacture (art. 24) - http//ec.europa.eu/taxation_customs/customs/custo
ms_duties/rules_origin/index_en.htm
312. Nationality and origin, exceptions
- Exceptions may be justifyed by
- Unavailability of products and services in the
markets of the countries concerned - For reasons of extreme urgency
- If the eligibility rule were to make the
realisation of a project, a programme or an
action impossible or exceedingly difficult - NOT applicable just because a product of
ineligible origin is cheaper than the EU or local
product! - By derogation only (request to JTS/JMA) before
launching the tender!
323. Rules common to all tender procedures
- The tender documents must be drafted in
accordance with best international practice - If they do not have their own documents,
Beneficiary/partners may use the models published
on EC website relating to external actions (PraG
Chapters 2, 3, 4 and related annexes) - http//ec.europa.eu/europeaid/work/procedures/impl
ementation/practical_guide/index_en.htm - The time-limits for receipt of tenders and
requests to participate must be long enough to
allow interested parties a reasonable and
appropriate period to prepare and submit their
tenders. (eg PraG 60 days for Supplies and 90
days for Works in international tenders, 30 for
Supplies and 60 for Works in local tenders)
333. Rules common to all tender procedures
- All requests to participate and tenders declared
as satisfying the requirements must be evaluated
and ranked by an evaluation committee on the
basis of the exclusion, selection and award
criteria announced in advance. - This committee must have an odd number of
members, at least three, with all the technical
and administrative capacities necessary to give
an informed opinion on the tenders.
34Confirming docs of action
- Written materials Internal memos, meeting notes,
progress reports etc. - Prove of activities conducted invitations, list
of participants with signatures, meeting minutes,
photos - Filing (printed and electronic)
- Required to collect samples of all information
and communication materials as well as all media
materials produced about the project. A copy of
those materials should be sent to the JTS
together with Interim Reports. In addition, the
JTS should be notified about every event
organized in the frame of the project.
35 REPORTING
- Interim report (consisting of both narrative and
financial section) conforming to the model in
Annex VI must - Be submitted no later than 3 months after the end
of each six month (in the absence of request for
payment) - Covers June-November 2012
- To be submitted by end of February 2013
- Accompany every request for payment
- Final report shall be forwarded no later than 3
months after the implementation period - Report covers the Action as a whole