Title: Infrastructure Development in Romania
1Infrastructure Development in Romania
2Project Life Cycle
- by
- W J McCoubrey
- BSc CEng FICE FIEI FIHT FIAE
- Transport Infrastructure Consultant
- Email billy.mccoubrey_at_nireland.com
3Introduction
- Project Stages and responsibility
- Tendering and Contract Types
- Project Closure and Audit
4Cohesion Fund Financial Controls
EU Commission Audits carried out by EU
Commission Control Units
Certification of all expenditure
Certification of all expenditure
Certification of all expenditure
DoELG/MoT
ESB/MET
NRA/MoE
Certification of all expenditure
- Structure of financial controls to
- comply with Commission Regulations (EC) 1386/2002
- Article 9.1(a) and 9.1(b) and the Protocol on
- Internal Audit (IA) co-operation
RDO / Councils
5Project Stages
- 1 - Concept
- 2 - Preparation
- 3 - Application
- 4 - Evaluation - Funding Appraisal
- 5 - Decision - Approval for Cohesion Fund
- 6 - Selection and Award of Contract
- 7 - Contract Supervision
- 8 - Payments
- 9 - Modifications
- 10 - Project Closure and Audit
6Eligibility Issues
- General rules open to interpretation
- Commission Decision
- defines total CF assistance limit and period of
eligibility - Transparency
- Expenditure incurred in eligibility period
- Eligibility of expenditure
- Public Authority employees
- Land purchases
- limited to maximum 10 of project eligible
expenditure
7Eligibility Issues (2)
- Treatment of Financial other charges
- Operating costs
- Information publicity measures
- Car parks
- Computerised management monitoring systems
8Land Issues - Ireland
- Land purchases
- limited to maximum 10 of project eligible
expenditure - typically 25 -30 of overall project cost
- M50 SCRM major disagreement with auditors
- time period
- land not used for project
- robustness of systems for monitoring and audit
trail - initial decision was to exclude land from
eligibility claims - revised to now include land that has been
directly used - only within boundaries of project
- only payments made to landowners within
eligibility period - excludes interest payments from CF claim
9M50 SouthernCrossRouteMotorwayLand Use
10M1 Lissenhall-Balbriggan
- Commission Decision C (2000) 3518
- Period covered 07/07/2000 31/12/2004
- Decision covers expenditure during eligible
period to value of 41,485,702 with 85 funding
being 35,262,847 maximum - Expenditure covered construction costs of 9.8km
of main line, motorway including earthworks,
pavement, drainage and fencing. - Elements of structures, interchanges, side roads
and land acquisition not assisted
11M1 Lissenhall-Balbriggan
- Commission Decision C (2000) 3870
- 15 October 2003 Amended original decision
- Decision covers expenditure during eligible
period to value of 62,134,212 with 85 funding
being 52,814,080 maximum - Expenditure covered building and construction
costs of provision of elements of structures,
interchanges, side roads, earthworks, pavement,
drainage ,fencing and land acquisition of
mainline motorway
12Land Acquisition example
13The FIDIC Rainbow
- The Red bookConstruction
- The Yellow bookPlant and Design-Build
- The Silver bookEPC Turnkey Projects
- The Green bookShort Form of Contract
14Contract Selection
STRAIGHTFORWARD PROJECT
EMPLOYER DESIGN
CONTRACTOR DESIGN
fixed price lump sum little employer
involvement no major unforeseen risks
Plant and/or high unforeseen risks
DISCUSS IN DETAIL Employers requirements with
the Contractor and negotiate an appropriately
modified FIDIC contract
15Stage 8 Payments
- Financial Control
- IB assists FB with claims and payments
- Payment of Contract Claim
- FB responsibility, funds from IB
- Eligibility of Claim
- handled by IB FCU
- Drawdown of Cohesion Funding
- twice yearly by IB to Paying Authority
- all funds lodged in Treasury
- IB authorised to make payments direct to FB
16Cohesion Fund Finance Flows
ESB/MET
Contract Claim paid to Contractor
17Stage 9 Modifications
- Variations of Price
- on materials for gt 2 years contracts
- Modifications to quantities or scope
- to be avoided where possible
- gt 10 probably requires new Decision
18Stage 10 Project Closure and EU Audit
- Completion of the contract
- Project closure
- Archival of documentation
- Minimum of 3 years after Project closure
- Can be as much as 7 years for Audit
- EU Audit
- Regulation compliance
- Eligibility issues
- Financial corrections loss of funding
19EU Audit in Ireland
- Cohesion I
- N4 Collooney / Sligo, Stage II (CF No.
94.07.65.004) - Cohesion II
- No audit reports available
- Only 3 projects reported on
- all under review
- 11 million financial correction, claimed wrong
form of contract as price variation inappropriate - 750.000 still under discussion of which
100.000 issues relating to use of transport on 2
sites
20Infrastructure Development in Romania Workshop
Issues
- Maximising Grant Assistance
- Project selection
- Eligibility of expenditure
- Delivery - Earning Grant
- Contract selection
- Contract administration
- Ensuring Grant is Certified and Retained
- Audit trail
- Project closure
- Archiving documentation