Title: Case Study IR Viewing of the LH Antenna Project (IRLH) Scheduling and Costing
1Case StudyIR Viewing of the LH Antenna
Project(IRLH)Scheduling and Costing
Malcolm Kear
2Case StudyIRLH Project
Contents of Presentation
- Development of Work Breakdown Structure (WBS)
- Identification of Work Package tasks
- Development of Gantt Chart (Schedule)
- Development of Costs
- Finalising the Work Package information
3IRLH Project Top-level WBS - Levels 1-2
4IRLH Project Development of Gantt Chart
- Step 1 - Create Top-Level Strands
- Do NOT insert durations - these will
automatically be created
5IRLH Project Top-level WBS - Levels 1-3
6IRLH Project Development of Gantt Chart
- Step 2 - Create Second-Level items
- Do NOT insert durations - these will
automatically be created
7IRLH Project Second-level WBS - Levels 2-4 -
Engineering Design Manufacture
Work Packages
8IRLH Project Development of Gantt Chart
- Step 3 - Create Work Packages
- Do NOT insert durations - these will
automatically be created
9IRLH Project Work Package Description Summary
Sheets - WP 1.2.1.1
Do NOT enter Start and End Dates at this stage
Enter name of WP Manager
Define Inputs required - these may be Outputs
from other WPs
Define the tasks that comprise this Work Package
Define Outputs from Work Package
Do NOT enter Management Info. At this stage
10IRLH Project Development of Gantt Chart
- Step 4 - Create Work Package Tasks
- Now insert task durations and interdependencies
Note Work Package Tasks can be copied from the
Work Package Description Summary Sheets Durations
are the TOTAL length of time it will take to do
the task and can be fixed or variable. Example
Preparing a meal. Time taken to cook in the oven
is fixed, whereas the time taken to prepare the
meat and veg, set the table, etc is dependent of
the number of people available
11IRLH Project Compiling Costs
- Costs are compiled bottom-up using the Work
Package as the smallest entity - 3 Cost elements are defined (Manpower, Article 7
and Purchases) BUT there can be any number and
any definition - Spreadsheet automatically rolls-up costs
through WBS - The number of Man-days is the time the man will
spend on the task
12IRLH Project Compiling Costs
13IRLH Project Compiling Costs
14IRLH Project Compiling Costs
15IRLH Project Finalise WPD Summary Sheets - WP
1.2.1.1
Enter Start and End Dates for WP from Plan
Enter Management Info. From Cost Spreadsheet and
SAP
16IRLH Project Cumulative Time-phase Costs