Title: 6th Review Meeting of the Convention on Nuclear Safety SLOVENIA
16th Review Meeting of theConvention on Nuclear
Safety SLOVENIA
- Country Group 3
- 24 March 2014, Vienna
2Outline
- Basic information on the national programme
- Changes in the legislation since the last Review
Meeting - Significant events since the last Review Meeting
- Action on challenges and planned measures from
the last Review Meeting - Current Challenges
- Questions Raised from Peer Review of National
Report - Updates to National Report to 6th Review Meeting
- Conclusions
3Basic information on the national programme
4Nuclear Slovenia
TRIGA
Mine
5Krško NPP
- Westinghouse PWR, 2 loop
- 700 MWe
- Commercial operation since 1983
- Ownership 5050 Slovenia-Croatia
- Without major problems
- Life time extension after 2023 is foreseen
- Intensive post Fukushima improvements
6Other facilities
- TRIGA research reactor
- Central Interim RW Storage
- Former Uranium Mine
- Looking for the LLIW Repository
- gt1000 sources of ionizing radiation
7Slovenia, the smallest nuclear country
- We have everything the big country has
- but we have to manage it with less resources!
8Dynamic period!
- Krško NPP operation was without major problems,
however ... - ... 11. March 2011 has drastically changed the
focus of nuclear safety related activities
9Post-Fukushima activities
- New mobile equipments
- Mobile DGs - various power (from 3 KW up to 2
MW) - Mobile Air Compressors
- Mobile FP pumps
- Stress tests and National Action Plan
- Long term improvements
- Comprehensive Safety Upgrade Programme
- Filtered Containment venting implemented
- Passive Autocatalitic Recombiners implemented
- Additional SI and FW pumps by 2018
- Additional heat sink by 2018
- External control room by 2018
- Dry spent fuel storage by 2018
10Fire Equipment
- Fire truck with a hydraulic fire-fighting arm
- Tanks 8500 l of water 1500 l of
fire-extinguishing foam
11First actions of the Krško NPP
30 m3/hr, 32 bar 2 discharge connections
Testing the spraying of the imaginary SFP
12First actions of the Krško NPP
- Fuel (diesel, gasoline) stored on-site
Mobile and portable diesel generators
13Other improvements
- 3rd safety related diesel generator
- Reduces risk primarily from the Station Blackout
Sequence and from seismic events - Upgrade of flood protection dikes.
- Protects against more demanding Probable Maximum
Flood - Reactor pressure vessel head replacement
- In response to industry events involving Alloy
600 penetrations and 82/182 weld material
14Safety Related Diesel Generator
15Other developments
- Aging management programme approved
- It makes operation after 2023 possible
- One more Periodic Safety Review have to be done
before first 10 year life extension - Second Periodic Safety Review is concluded, to be
approved by June 2014 - KI iodide tablets distributed in 10 km radius
around the Krško NPP.
16Improvements in the plant
- Replaced main generator rotor
- Upgraded of 400 kV buses and undervoltage
protection - Replaced main feedwater isolation valves
actuators - Upgraded fire protection detection system,
- Refurbished residual heat removal and essential
service water systems.
17Post Fukushima actions
- Operator immediately started with improvements
- The SNSA issued three decisions to the Krško NPP
- to perform an extraordinary PSR in line with
specifications for European Stress Tests - to reassess the severe accident management
strategy and implement safety improvements for
prevention of severe accidents and mitigation of
its consequences - to review bases for emergency planning and
response including emergency planning zones
18Stress tests analyses
- Evaluation of seismic and flooding margins,
- Additional station blackout analyses,
- Drain cycle of the 1E batteries,
- Water heatup and evaporation rate in the spent
fuel pool, - Evaluation of spent fuel pool criticality.
19Stress test conclusions
- Krško NPP was well designed and constructed,
- Potential external events were taken into account
during preparation of protective and mitigating
measures. - A single recommendation after Peer ReviewThe
regulator should consider requesting to update
the seismic design basis for future design
modifications and consequently the associated PSA
model.
20Post Fukushima Action plan
- Its core is the Krško NPPs Safety Upgrade
Program - Implementation of upgrades foreseen already in
2009 - Implementation of Short-Term Improvements
(accelerated B.5.b Requirements Actions) - Procurement of AC diesel generators, pumps and
compressors, implementation of quick connection
points for this equipment, additional fire
protection equipments, including high capability
fire truck - Amendments to the emergency operating procedures
and severe management accident guidelines
21Krško NPP Safety Upgrade Programme
- Safety upgrade of AC power,
- Additional FW pump,
- Additional heat sink (AHS),
- Additional SI pumps with a dedicated water
supply, - Containment filter vent system and passive
autocatalytic recombiners, - Emergency control room,
- Fixed spray system around the spent fuel pit,
22Krško NPP Safety Upgrade Programme (contd)
- Mobile heat exchanger with provisions to quick
connect, - Flood protection upgrade,
- New technical support center,
- Upgrade of existing operational support center.
23Changes in the legislation
24Changes in the legislation since the last Review
Meeting
- New Act on Liability for Nuclear Damage issued
- Amendments of the Act on Ionising Radiation
Protection and Nuclear Safety comprising - requirements of Nuclear Safety Directive,
- the restriction of the right to go on strike,
- provisions on physical protection,
- duplications in the area of radiation practices,
- availability of inspectors and professional
officers, etc. - Resolution on Nuclear Safety
25Significant events since the last Review Meeting
26Events in the Krško NPP
- Activation of false alarms in the seismic
monitoring system, - Inoperability of the service water system,
- Trip of auxiliary feedwater pump,
- Inoperability of Chilled Water System,
- Reactor vessel head cable bridge incident,
- Extensive fuel damage
27Reactor shutdowns
- Reactor trip and safety injection actuation
system due to the loss of external load - Main steam isolation valve stem failure
- Shutdown due to large amounts of debris in the
Sava river - Malfunctioning of primary temperature measurement
system
28Trip due to the loss of external load
- 23 March 2011 (during Fukushima!)
- Spurious activation of bus protection in the
NPPs 400 kV switchyard, - Rapid pressure decrease in the main steam line,
- Safety injection (SI) signal on low steam line
pressure, - Diesel generators started automatically,
- No other problems
29Trip due to steam isolation valve stem failure
- 25 February 2013
- Sudden closure of main steam isolation valve
(MSIV) valve stem break, - Increased steam flow in another line resulted in
pressure drop actuating the safety injection
system and the reactor trip, - Similar event occurred 1997,
- Replacement and redesign of MSIV.
30Trip due to steam isolation valve stem failure
31Shutdown due to debris in the river
- 28 October 2012
- The flow of the river Sava rose very rapidly
- High river washed down materials from river
banks, - The inlet of the condenser cooling system was
clogged, - Condenser cooling water flow was reduced,
- Temperature and pressure in the condenser
increased and vacuum in the condenser
deteriorated. - Operators carried out manual preventive shutdown
of the reactor.
32- Trip due to the malfunctioning of the primary
temperature measurement system - and
- Extensive fuel damage
- See last part of this presentation with updates
to the National Report
33Action on challenges and planned measures from
the last Review Meeting
34Problems of domestic TSOs Reliance on foreign
TSO
- Not all technical aspects could be covered by
domestic Technical Support Organizations (TSOs) - Operator is seeking expertise from anywhere
- Reducing number of domestic experts
- No systematic support to nuclear fission related
research, experts are growing older ... - Challenge remains!
35Financial and Human Resources for the SNSA
- SNSA is financed only by the state budget,
- Due to the crisis funds are decreasing,
- No new employments!
- SNSA had to abandon ISO9001 certification
- SNSA is fulfilling its mission, but ...
- ... has already publicly announced what risks are
increasing due to restrictions - Challenge remains and is growing bigger!
36IRRS in 2011
- Between 25 September 4 October 2011
- The SNSA Strengths
- Adequate legal framework
- SNSA has in place an effective process for
carrying out this responsibility, - Response to the accident at the TEPCO Fukushima
Daiichi power plant has been prompt and
effective. - Good practices
- SNSAs quality management system,
- An inter-ministerial committee chaired by SNSA
for coordination of emergency planning - Communications system used during emergency
situations
37IRRS in 2011
- A need to develop a national policy and strategy
for nuclear safety - done - Possible alternative methods of financing SNSA
decided not to go for independent agency! - SNSA needs competencies and resources see
previous challenge - Necessary steps to be taken for the Low and
Intermediate Level Waste Repository SNSA has
actively pushed for it, some progress - Transition between the emergency phase to long
term recovery operations and the post-accident
phase, - ... and some others.
38Reactor Head Replacement
39Upgrade of Flood Protection and Installation of
New Diesel Generator
- Done in 2011-12!
- Flood protection
- Upgrade by up to 1.8 meters of flood protection
dikes along the river Sava. - Seismic criteria the same as for the Krško NPP
- Safety margin of 0.75 m.
- Third Diesel Generator
- Class 1E 3.5 MW diesel generator
- Increases safety in case of a seismic event and
loss of offsite power.
40Upgrade of flood protection dikes
- Plant sitewould remain dry
Upgrade of dikes upstream of the plant to protect
the plant to the flood flows beyond the Probable
Maximum Flood
40
41Harmonization of Legislation with Good Practice
in EU
- WENRA Reference Levels are fully transposed into
Slovenian legislation, - Slovenian legislation is harmonized with the EU
Nuclear Safety Directive and EU Nuclear Waste
Directive
42The Krško QA System and Compliance with IAEA
GS-R-3
- The latest revision of Quality Assurance Plan in
2011. - In line with Slovenian Rules JV5 and IAEA GS-R-3
requirements - Covers Safety Culture, Self-Assessment, Human
Performance, Industrial Safety - The bases for the revision were
- Changes of the Slovenian regulatory requirements
and licensing documents, - SNSA inspection requirements,
- Changes of international standards,
- Conclusions of the first PSR,
43PSR 2 to be completed in 2013
- PSR2 was completed
- There were no major issues which would prevent
further safe operation - 15 safety factors were reviewed
- An action plan is being developed and will be
implemented in the next 5 years. - Some issues from the action plan
- Procedures periodic review
- Root cause analysis
- Temporary modification survey
- Generation of solid radioactive waste
- Potential tube wear from secondary side loose
parts - ...
44Cyber Security Threats and Airplane Crashes
- Krško NPP has prepared and implemented Cyber
Security programme - SNSA has trained its people
- Airplane Crashes
- No-flight zone in place around the NPP Krško
- NEI 06-12 B.5.b requirements was one of the
inputs to post Fukushima action plan and those
consider also airplane crash - Bunkerized structures for DG3 and future safety
equipment - Alternative Spent Fuel Pool cooling system,
- Fire fighting of airplane fuel fires capabilities
- Improved SAMGs.
45Future Planned Measures to Improve Safety
46Future Planned Measures to Improve Safety
- Most of those measures are within the Safety
Upgrade Programme (see post-Fukushima related
slides) - Upflow conversion in the reactor vessel
- Improvements in off-site emergency planning
together with Croatia - Inviting peer review missions
- WANO, IRRS-FU, OSART, EPREV
47Current and Future Challenges
48Challenges
- Individual actions of the Safety Upgrade Program
as well as other National post-Fukushima Action
Plan (NAcP), including Design Extension Codition
(DEC) implementation - Reassessment of alternative spent fuel strategy
(part of NAcP) - Preservation of knowledge and competencies
- Financial and Human Resources of SNSA
- Domestic TSOs
49Questions Raised from Peer Review of National
Report
50Questions from Peer Review
- The complete set of answers to the questions
raised by other CP is available at the SNSA site
http//www.ursjv.gov.si/fileadmin/ujv.gov.si/pageu
ploads/si/Porocila/NacionalnaPorocila/KJV_6th_answ
ers.pdf - Questions were evenly distributed among articles,
with the exception two - regulatory body the decreasing SNSA budget,
challenge to keep competency due to small nuclear
programme, ageing of the SNSA staff, sharing
information to the public of the SNSA activities - assessment and verification of safety PSA,
PSR, SAMG, response to Fukushima, performance
indicators,
51Questions from Peer Review
- The other questions referred to.
- Post-Fukushima upgrades (plan and status)
- Management system of the licensee
- Emergency preparedness in Slovenia and Croatia
and review of emergency plans in the light of
Fukushima - Incident reporting system by the operator
- Assessing safety culture
- Transparency and communication to the public by
the licensee
52Updates to National Report to the Review Meeting
53Fuel leakage and cladding failure
- Discovered during outage in October 2013,
- Six fuel assemblies were leaking,
- 50 cm long segment of the fuel rod found in the
fuel transfer channel
54Fuel leakage and cladding failure
- Open defects in 8 fuel rods of three fuel
assemblies, - Primary cause debris fretting, baffle jetting and
grid-to-rod fretting - Extensive inspection of fuel assemblies and the
core baffle plate - Corrective action armoring of fuel assemblies
with dummy stainless steel rods at exposed
positions - Prior to the start of operation an extended
Failed Fuel Action Plan was prepared
55RTD Spurious electrical signals caused reactor
trip
- Resistance Temperature Detectors Bypass was
eliminated during outage 2013 - After the outage signal spiking caused reactor
trip due to creation of OP?T (for a split second) - Corrective actions
- Installation of surge suppressors
- Some equipment was tagged out until the problem
was resolved - The vendor will analyze lead/lag filters used in
processing the signals and redesign appropriate
circuits
56CONCLUSIONS
- The only NPP operating safely
- Slovenia has Legislative System harmonized with
best practices - Regulatory Supervision is efficient and
effective, although the risks due to lack of
resources are increasing - Slovenia and its Nuclear Facilities fulfill
requirements of the Convention on Nuclear Safety