Title: Contract Management: A Public Sector Case Study Rivaj Parbhu
1Contract Management A Public Sector Case Study
Rivaj Parbhu
- The information contained in this presentation is
the property of Realyst and is to be treated as
private and confidential
2 Introduction
- Topics to be Covered
- What is Contract Management (5 Minutes)
- Why Contract Management (5 Minutes)
- Implementation of Contract Management Lessons
learnt in Government (20 Minutes) - The Problem
- The Solution
- Project Status
- Lessons Learnt
- Questions
3 what is contract management?
- What is Contract Management?
- A system for managing contracts through
documented processes and supported by software
that allows organisations to effectively manage
the various types of contracts they engage in,
including buy side, sell side, and non
monetary. (www.wikipedia.com, 2007) - Basic Functions of a Contract Management System
- Central Repository
- Alerting
- Contract Creation features
- Workflow and Process Control
- (IACCM Contract Management Report, 2007)
4Why is Contract Management relevant?
- Despite unprecedented spending on health,
education, law enforcement, housing etc we are
still lagging behind in Service Delivery.
Bid to deliver homes urgently has failed
Fin24June 22 2007 The government's bid to
deliver urgently homes and provide people with
shelter in the Western Cape had failed
Jo'burg Hospital down to 4 liftsThe Star
08/2008 Johannesburg - Only four lifts out of 21
are operational at Johannesburg Hospital, the
hospital's chief executive said on Thursday.
- In many cases Government contracts with the
Private Sector in order to deliver services to
South Africans. - The improved POST SIGNATURE management of
these contracts would ensure improved service
delivery.
5 Case Study The Problem
- In June 2006 Realyst Contract Management together
with PriceWaterhouseCoopers embarked on a project
to deliver a contract management solution to a
single directorate within a National Government
Department. - The primary reason for this department to
implement a contract management solution was an
external audit report highlighting deficiencies
in the contracting process with the potential
for financial mismanagement and gross
inefficiencies. - Five key findings were
- No contracts or SLAs in place for key,
multi-million Rand suppliers - No means or process to measure the performance
of suppliers - No regular reviews of the contract documents
- Inadequate controls in place for managing
payments - Inadequate contract policies and procedures
6 Case Study The Solution
- The Realyst automated contract management
solution was delivered to the department. The
initial implementation was scoped at taking 6-8
weeks with the deliverables being to address the
findings of the audit report. - Challenges experienced during roll-out
- Lost or non existent contracts and contract
documents - Confusing procurement process and contract
management process - No awareness of the need for contracts even at
an executive level - Non existent contract policies and procedures
- No checklist to be used to ensure all required
documentation is received - No contract templates available. Signing of
supplier agreements - Creating a sustainable solution
7 Case Study Project Status Lessons Learnt
- We now regard this implementation as being
successful. The department has cleared its audit
findings and has repeatedly enjoyed improved
service delivery from its suppliers. - Status of the Project
- We have just agreed and implemented a
checklist where all approvals, tender docs,
letter of appointment, etc, will be kept with
contract - Automated Contract approval process currently
being finalized - Last phase in the project is to agree
standard contract templates taking into account
both business drivers and legislation/guidelines.
- 5 Lessons Learnt
- Walk before we try to Run
- Dedicated centralized function with a Contracts
Administrator - Build operate and transfer model
- SLAs with suppliers, including penalties for non
performance are critical - Management support and buy-in is important to
ensure success of contract management office
8Rivaj Parbhu 011 463 5311 083 661
2669 rparbhu_at_Realyst.com