Title: 2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India
12 X 363.3 Combined Cycle Gas Power Project
Palatana, Tripura PresentationatMinistry of
Development ofNorth Eastern Region,Government
of India
December 16, 2010
www.otpcindia.inNew Delhi
2Contents
- Background
- Project Highlight
- Power Allocation
- Project Location
- Gas Supply Network of ONGC
- Project Status Clearances Permits
- Project Status Supply and Construction
- Logistics
- Status of Inputs
- Areas of Concern
- Assistance Required
3 LAYING OF FOUNDATION STONE
October 29, 2005
4 Source of Inspiration
5Site Activity Photographs
10-Dec-10
SITE VIEW FROM (MAIN GATE ROOF)
6Site activity photographs
10-Dec-10
GTG STG BUILDING UNIT-1
7Site Activity Photographs
10-Dec-10
10-Dec-10
COOLING TOWER UNIT-1
8Site activity photographs
10-Dec-10
CW PUMP HOUSE UNIT-1
9Site Activity Photographs
10-Dec-10
10-Dec-10
132 kV SWITCHYARD
10Background
- Unutilized gas reserves in Tripura
- Transportation of gas to mainland not
economically viable - Possible Option Gas head generation
transmission of electricity - Government of Tripura, ONGC and ILFS join hands
to set-up Power Plant to provide good quality
energy in NER stimulating economic growth - Honble Prime Minister laid the foundation stone
in October, 2005
11Project Highlight
- Capacity 2 x 363.3 MW
- Type Gas Based Combined Cycle
- Location Palatana, Tripura
- Project Cost Rs 3,429 Crore
- Source of Fuel ONGCs Gas Field in Tripura
- Type of Fuel Natural Gas
- Quantity of Fuel 2.65 MMSCMD
- Source of Water River Gumti
- Quantity of Water 125 MLD
- Promoters ONGC (50), ILFS (26), GOT (0.5).
12Project Highlight Contd
- EPC Contractor Bharat Heavy Electricals Limited
(BHEL) - Award of Contract 23-Jun-08
- Commissioning Unit-1 22-Dec-11,
- Unit-2 22-Mar-12
- Evacuation 650 KM 400 KV D/C Palatana
Bongaigaon Line
13Power Allocation
Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW
Tripura 196
Assam 240
Arunachal Pradesh 22
Nagaland 27
Mizoram 22
Manipur 42
Meghalaya 79
Power allocated to OTPC 98
14Project Location
Ajara S/S
Byrnihat S/S
Silchar S/S
650 kms 400 kV D/C line
15Gas Supply from ONGC Tripura Asset
16Project Status Clearances and Agreements
- Clearance received from MOEF, TSPCB, AAI, MOD
- State Support Agreement Signed
- 206 Acres of Land Acquired for the project
- Shareholders Agreement, Gas Sale Purchase
Agreement and Power Purchase Agreement signed. - Long Term Service Agreement signed with OEM (GE)
for Gas Turbine
17Project Status Supply Construction
- SUPPLIES
- Dispatch of ODCs to be transported through
Bangladesh started in May-10 and last dispatch
from BHEL works for Unit-1 Unit-2 is expected
by end Feb-11. - Supplies of non-ODCs to be transported via
Gauhati started in Mar-10 and last dispatch from
BHEL works for Unit-1 is expected by Apr-11 and
for Unit-2 by Aug-11. - CIVIL CONSTRUCTION
- Piling and foundation of major buildings for
Unit-1 completed and main plant equipment
erection shall start in Jan-11. - Major structures for Unit-2 are likely to be
ready for erection by Apr-11. - Work for Cooling Tower and Water Treatment System
has commenced. CT-1 is likely to be commissioned
in Sep-11 and Water Treatment System is likely to
be commissioned in Jul-11 - Construction of River Water Intake Pump house and
pipeline has commenced and likely to be
commissioned by Jul-11.
18Project Status Erection
- ERECTION
- Erection contract has been awarded and erection
of Main Plant equipment shall start in Jan-11 - Milestone Target Date
- Mechanical Completion Aug-11
- Hydro test Completion Oct-11
- Readiness for commissioning Dec-11
19Routes Kolkata Ashuganj Palatana
Kolkata Karimgunj - Palatana
20Logistic MOU Signing with Govt of Bangladesh
21Logistic MOU Signing with Govt of Bangladesh
22Logistic Movement of ODC by Barge
23Logistic Movement of ODC through Road Diversion
24Logistics Overview
- Routes for transportation of ODCs from Kolkata
There are two routes available for transportation
of ODCs to Palatana site - Via Karimganj 1318 KM (river) 320 KM (road -
India) - Via Ashuganj (Bangladesh) 856 KM (river) 115
KM (road India Bdsh) - Ashuganj route has been selected because river
route is navigable through out the year and road
route passes through generally plain land leading
to less risk in transportation. - Honble Prime Minister of Bangladesh during her
visit to India in Jan-10 agreed to allow movement
of ODC through Ashuganj in Bangladesh. Since
then, Ashuganj has been included in Indo-Bangla
Water Transport Proto-call and MOU has been
signed with GOB formally allowing movement of
ODCs through Bangladesh territory. - 96 ODCs shall be transported through Bangladesh
for which construction of RO-RO jetty at Ashuganj
and bypasses between Ashuganj and Palatana has
started. - Movement of ODC from Kolkata to Ashuganj shall
start from jan-11 and from Ashuganj to Palatana
site shall start in Feb-11.
25PROJECT STATUS OF INPUTS
Commissioning Gas Start-up Power Evacuation System
Responsible agency ONGC TSECL NETCL / POWERGRID / NER STATES
Latest required to meet commissioning schedule August 11 May11 November11
Current Status Construction has started Line construction contract yet to be awarded Construction started but moving at tardy pace.
OTPC assessment No delay Delay of 3 Months Delay of 3 months (up to Silchar) Delay of 6-9 months (up to Bongaigaon)
Impact on unit1 No impact Delay of 3 months Likely delay of 3 months
Impact on Unit2 No impact No impact Likely delay of 6/9 months
26AREAS OF CONCERN
- PALATANA SILCHAR TRANSMISSION LINE
- Delay in Forest Clearance in Assam (4 KM)
- SILCHAR BONGAIGAON TRANSMISSION LINE
- Delay in Forest Clearance in Meghalaya (25 KM)
and Assam (22 KM) - EVACUATION CONSTRAINT PALATANA BONGAIGAON
- Delay in construction of Azara and Byrnihat
sub-station - DOWNSTREAM NETWORK BY BENEFICIARY STATES
- Work yet to commence by States i.e. Assam,
Tripura, Mizoram etc for absorption of power.
Unit-1 commissioning may be delayed on this
account.
27ASSISTANCE REQUIRED
- Immediate Forest Clearance in Assam (26 KM) and
Meghalaya (25 KM) required. - State governments to expedite development of
Azara and Byrnihat sub-station and downstream
network to match Unit-1 commissioning in Dec-11 - States to advise POWERGRID to install
series-compensation facility at Bongaigaon
sub-station. - Government of Tripura to expedite construction of
132 KV line and provide startup power by May-11
28Thank You
December 16, 2010New Delhi