2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India

Description:

Commissioning Gas. Start-up Power. Evacuation System. Responsible agency. ONGC. TSECL. NETCL / POWERGRID / NER STATES. Latest required to meet commissioning schedule – PowerPoint PPT presentation

Number of Views:197
Avg rating:3.0/5.0
Slides: 29
Provided by: mdonerGo
Category:

less

Transcript and Presenter's Notes

Title: 2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India


1
2 X 363.3 Combined Cycle Gas Power Project
Palatana, Tripura PresentationatMinistry of
Development ofNorth Eastern Region,Government
of India
December 16, 2010
www.otpcindia.inNew Delhi
2
Contents
  • Background
  • Project Highlight
  • Power Allocation
  • Project Location
  • Gas Supply Network of ONGC
  • Project Status Clearances Permits
  • Project Status Supply and Construction
  • Logistics
  • Status of Inputs
  • Areas of Concern
  • Assistance Required

3

LAYING OF FOUNDATION STONE
October 29, 2005
4


Source of Inspiration
5
Site Activity Photographs
10-Dec-10
SITE VIEW FROM (MAIN GATE ROOF)
6
Site activity photographs
10-Dec-10
GTG STG BUILDING UNIT-1
7
Site Activity Photographs
10-Dec-10
10-Dec-10
COOLING TOWER UNIT-1
8
Site activity photographs
10-Dec-10
CW PUMP HOUSE UNIT-1
9
Site Activity Photographs
10-Dec-10
10-Dec-10
132 kV SWITCHYARD
10
Background
  • Unutilized gas reserves in Tripura
  • Transportation of gas to mainland not
    economically viable
  • Possible Option Gas head generation
    transmission of electricity
  • Government of Tripura, ONGC and ILFS join hands
    to set-up Power Plant to provide good quality
    energy in NER stimulating economic growth
  • Honble Prime Minister laid the foundation stone
    in October, 2005

11
Project Highlight
  • Capacity 2 x 363.3 MW
  • Type Gas Based Combined Cycle
  • Location Palatana, Tripura
  • Project Cost Rs 3,429 Crore
  • Source of Fuel ONGCs Gas Field in Tripura
  • Type of Fuel Natural Gas
  • Quantity of Fuel 2.65 MMSCMD
  • Source of Water River Gumti
  • Quantity of Water 125 MLD
  • Promoters ONGC (50), ILFS (26), GOT (0.5).

12
Project Highlight Contd
  • EPC Contractor Bharat Heavy Electricals Limited
    (BHEL)
  • Award of Contract 23-Jun-08
  • Commissioning Unit-1 22-Dec-11,
  • Unit-2 22-Mar-12
  • Evacuation 650 KM 400 KV D/C Palatana
    Bongaigaon Line

13
Power Allocation
  • Power Allocation by MoP

Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW
Tripura 196
Assam 240
Arunachal Pradesh 22
Nagaland 27
Mizoram 22
Manipur 42
Meghalaya 79
Power allocated to OTPC 98
14
Project Location
Ajara S/S
Byrnihat S/S
Silchar S/S
650 kms 400 kV D/C line
15
Gas Supply from ONGC Tripura Asset
16
Project Status Clearances and Agreements
  • Clearance received from MOEF, TSPCB, AAI, MOD
  • State Support Agreement Signed
  • 206 Acres of Land Acquired for the project
  • Shareholders Agreement, Gas Sale Purchase
    Agreement and Power Purchase Agreement signed.
  • Long Term Service Agreement signed with OEM (GE)
    for Gas Turbine

17
Project Status Supply Construction
  • SUPPLIES
  • Dispatch of ODCs to be transported through
    Bangladesh started in May-10 and last dispatch
    from BHEL works for Unit-1 Unit-2 is expected
    by end Feb-11.
  • Supplies of non-ODCs to be transported via
    Gauhati started in Mar-10 and last dispatch from
    BHEL works for Unit-1 is expected by Apr-11 and
    for Unit-2 by Aug-11.
  • CIVIL CONSTRUCTION
  • Piling and foundation of major buildings for
    Unit-1 completed and main plant equipment
    erection shall start in Jan-11.
  • Major structures for Unit-2 are likely to be
    ready for erection by Apr-11.
  • Work for Cooling Tower and Water Treatment System
    has commenced. CT-1 is likely to be commissioned
    in Sep-11 and Water Treatment System is likely to
    be commissioned in Jul-11
  • Construction of River Water Intake Pump house and
    pipeline has commenced and likely to be
    commissioned by Jul-11.

18
Project Status Erection
  • ERECTION
  • Erection contract has been awarded and erection
    of Main Plant equipment shall start in Jan-11
  • Milestone Target Date
  • Mechanical Completion Aug-11
  • Hydro test Completion Oct-11
  • Readiness for commissioning Dec-11

19
Routes Kolkata Ashuganj Palatana
Kolkata Karimgunj - Palatana
20
Logistic MOU Signing with Govt of Bangladesh
21
Logistic MOU Signing with Govt of Bangladesh
22
Logistic Movement of ODC by Barge
23
Logistic Movement of ODC through Road Diversion
24
Logistics Overview
  • Routes for transportation of ODCs from Kolkata
    There are two routes available for transportation
    of ODCs to Palatana site
  • Via Karimganj 1318 KM (river) 320 KM (road -
    India)
  • Via Ashuganj (Bangladesh) 856 KM (river) 115
    KM (road India Bdsh)
  • Ashuganj route has been selected because river
    route is navigable through out the year and road
    route passes through generally plain land leading
    to less risk in transportation.
  • Honble Prime Minister of Bangladesh during her
    visit to India in Jan-10 agreed to allow movement
    of ODC through Ashuganj in Bangladesh. Since
    then, Ashuganj has been included in Indo-Bangla
    Water Transport Proto-call and MOU has been
    signed with GOB formally allowing movement of
    ODCs through Bangladesh territory.
  • 96 ODCs shall be transported through Bangladesh
    for which construction of RO-RO jetty at Ashuganj
    and bypasses between Ashuganj and Palatana has
    started.
  • Movement of ODC from Kolkata to Ashuganj shall
    start from jan-11 and from Ashuganj to Palatana
    site shall start in Feb-11.

25
PROJECT STATUS OF INPUTS
Commissioning Gas Start-up Power Evacuation System
Responsible agency ONGC TSECL NETCL / POWERGRID / NER STATES
Latest required to meet commissioning schedule August 11 May11 November11
Current Status Construction has started Line construction contract yet to be awarded Construction started but moving at tardy pace.
OTPC assessment No delay Delay of 3 Months Delay of 3 months (up to Silchar) Delay of 6-9 months (up to Bongaigaon)
Impact on unit1 No impact Delay of 3 months Likely delay of 3 months
Impact on Unit2 No impact No impact Likely delay of 6/9 months
26
AREAS OF CONCERN
  • PALATANA SILCHAR TRANSMISSION LINE
  • Delay in Forest Clearance in Assam (4 KM)
  • SILCHAR BONGAIGAON TRANSMISSION LINE
  • Delay in Forest Clearance in Meghalaya (25 KM)
    and Assam (22 KM)
  • EVACUATION CONSTRAINT PALATANA BONGAIGAON
  • Delay in construction of Azara and Byrnihat
    sub-station
  • DOWNSTREAM NETWORK BY BENEFICIARY STATES
  • Work yet to commence by States i.e. Assam,
    Tripura, Mizoram etc for absorption of power.
    Unit-1 commissioning may be delayed on this
    account.

27
ASSISTANCE REQUIRED
  • Immediate Forest Clearance in Assam (26 KM) and
    Meghalaya (25 KM) required.
  • State governments to expedite development of
    Azara and Byrnihat sub-station and downstream
    network to match Unit-1 commissioning in Dec-11
  • States to advise POWERGRID to install
    series-compensation facility at Bongaigaon
    sub-station.
  • Government of Tripura to expedite construction of
    132 KV line and provide startup power by May-11

28

Thank You
December 16, 2010New Delhi