Title: Project: Rock Creek Cresta, North Fork Feather River, CA, 180 MW (two developments), filed in 1979
1(No Transcript)
2Workshop Agenda
- Welcome and Opening Remarks
- Purpose of the Workshop
- Overview and Pending Applications
- Project-Specific Discussions
- Closing Remarks
3(No Transcript)
4MAINE
5Burnham Project No. 11472Sebasticook River, ME,
1.05 MW, filed 1994 (Ridgewood Maine Hydro
Partners, LP), unlicensed operating project
- Activity Since November 2002 Workshop The Maine
legislature amended the state water quality
standards for dissolved oxygen (DO) standards in
riverine impoundments. - Remaining Actions Need WQC (due Feb. 2004).
6Gulf Island-Deer Rips Project No.
2283Androscoggin River, ME, 31.12 MW (three
developments), filed 1991 (FPL Energy Maine Hydro
LLC), relicense
- Activity Since November 2002 Workshop Maine
legislature amended the state water quality
standards for measuring DO in riverine
impoundments. Subsequently, Maine DEP initiated
a process to establish site-specific criteria for
measuring compliance with DO standards in Gulf
Island Pond. - Remaining Actions Need WQC (due Sept. 2004).
7Flagstaff Project No. 2612Dead River, ME, no
generating facilities, filed 1995 (FPL Energy
Maine Hydro, LLC), relicense
- Activity Since November 2002 Workshop The Maine
legislature passed resolution clarifying issues
related to storage reservoir drawdowns. Maine DEP
issued final WQC Nov. 14, 2003. - Remaining Actions Issue Order.
8Storage Project No. 2634Penobscot River, ME, no
generating facilities, filed 1998 (Great Lakes
Hydro America, LLC), relicense
- Project is new to the list FEA issued June
2002. ESA consultation completed Aug. 2002. WQC
request withdrawn and refiled Jan. 2003. Staff
issued letter Oct. 30, 2003, requesting status of
settlement negotiations. Response filed Nov. 28,
2003. - Remaining Actions Settlement agreement expected
in April 2004. Need WQC (expected following
settlement agreement).
9Howland Project No. 2721Piscataquis River, ME,
1.9 MW, filed 1998 (PPL Maine Energy Hydro, LLP),
surrender/relicense
- Project is new to the list REA notice issued
Aug. 8, 2003. Comments due Oct. 7, 2003.
Suspended until filing of comprehensive
settlement agreement. Non-decisional staff
assigned to facilitate settlement. - Remaining Actions File settlement, notice
settlement, initiate NEPA scoping, prepare
environmental document, PA, complete ESA
consultation, receive WQC, and issue order.
10NEW YORK
11Oswego River Project No. 2474Oswego River, NY,
18 MW (three developments), filed 1991 (Erie
Boulevard Hydropower, LP), relicense
- Activity Since November 2002 Workshop
Commission Dispute Resolution Service staff is
assisting stakeholders, as needed, in settlement
negotiations. Status of filing of settlement
expected Dec. 11. - Remaining Actions Need WQC (expected following
settlement agreement).
12School Street Project No. 2539Mohawk River, NY,
38 MW, filed 1993 (Erie Boulevard Hydro, LP),
relicense
- Activity Since November 2002 Workshop Settlement
talks continue. -
- Remaining Actions Need WQC (expected following
settlement agreement).
13VERMONT
14Carver Falls Project No. 11475Poultney River,
NY/VT, 1.85 MW, filed 1994 (Central Vermont
Public Service Corporation), unlicensed operating
project
- Activity Since November 2002 Workshop Licensee
met with VANR in January and February 2003 to
discuss aesthetic flows and flashboard design
which VANR says is needed before WQC can be
issued. - Remaining Actions Need WQC (due May 2004).
15Silver Lake Project No. 11478Sucker Brook, VT,
2.2 MW, filed 1994 (Central Vermont Public
Service Corporation), unlicensed operating
project
- Activity Since November 2002 Workshop Dec. 2002
benthic survey results indicate to VANR that a
drawdown plan needs to be developed by the
applicant before VANR can issue a WQC. -
- Remaining Actions Need WQC (due May 2004).
16Lamoille River Project No. 2205Lamoille River,
VT, 16.88 MW (four developments), filed 1987
(Central Vermont Public Service Corporation),
relicense
- Activity Since November 2002 Workshop Licensee
filed a settlement agreement in July 2003.
Public notice was issued Aug. 13, 2003,
requesting comments by Sept. 2, 2003. FWS
comments received Sept. 4, 2003. - Remaining Actions Need WQC (due March 2004).
17CALIFORNIA
18Escondido Project No. 176San Luis Rey River,
CA, 1.64 MW, filed 1971, amended 1975 (City of
Escondido), relicense
- Activity Since November 2002 Workshop Four
status reports filed. On October 10, 2003, the
parties to a 34-year-old water rights dispute
reached a water allocation agreement. - Remaining Actions Need comprehensive agreement,
pursuant to project-specific legislation.
19Lower Tule Project No. 372 Tule River, CA, 2.52
MW, filed 1998 (Southern California Edison
Company), Sequoia National Forest, relicense
- Project is new to the list DEA issued Jan.
2002, FEA issued June 2002, BO filed by FWS Nov.
2002. Feb 2003 report on water temp. and fish
distribution filed with SWRCB. WQC request
refiled March 2003. - Remaining Actions Need WQC (due March 2004).
20IDAHO
21Bliss Project No. 1975, Upper Salmon Falls
Project No. 2777, Lower Salmon Falls Project No.
2061, Shoshone Falls Project No. 2778, and C.J.
Strike Project No. 2055Snake River, ID, combined
252 MW, filed 1995, and 1998 (Idaho Power
Company), relicense, C.J. Strike occupies BLM
Lands.
- Activity Since November 2002 Workshop ESA
consultation and settlement negotiations between
FWS and Idaho Power. - Remaining Actions Need BO.
22OREGON
23Powerdale Project No. 2659Hood River, OR, 6 MW,
relicense filed 1998, surrender filed 2003
(PacifiCorp)
- Project is new to the list Relicense
application filed Feb. 25, 1998. Relicense FEA
issued Dec. 2001. Offer of Settlement for interim
operations and dam removal by 2012 filed on June
16, 2003, with request to hold relicense
application in abeyance. Noticed on June 26,
2003. Comments due July 28, 2003. Comments
received from American Rivers, Interior, State of
Oregon, and NOAA-Fisheries. EA issued Dec. 4,
2003. - Remaining Actions Need WQC (due June 2004),
initiate ESA consultation (upon issuance of EA).
24WASHINGTON
25Condit Project No. 2342White Salmon River, WA,
14.7 MW, relicense filed 1991, surrender filed
1999, (PacifiCorp)
- Activity Since November 2002 Workshop
Commission staff continues to discuss WQC and BO
issuance with Ecology and NOAA Fisheries,
respectively. - Remaining Actions Need BO from NOAA Fisheries
(expected Mar. 2004). Need WQC for surrender
application (due May 2004).
26Snoqualmie Falls Project No. 2493Snoqualmie
River, WA, 42 MW (49 MW proposed), filed 1991
(Puget Sound Energy), relicense
- Activity Since November 2002 Workshop NOAA
Fisheries concurred with staffs finding of not
likely to adversely affect in Mar. 2003. WQC
issued Sept. 2003. CZM compliance certified Nov.
13, 2003. Puget intends to file supplement to
application in Dec. 2003. - Remaining Actions Issue Order.
27ARIZONA
28Childs Irving Project No. 2069Fossil Creek, AZ,
7 MW (2 developments), relicense filed 1992,
surrender filed April 30, 2002 (Arizona Public
Service Company), Coconino and Tonto National
Forests
- Activity Since November 2002 Workshop DEA on
surrender application issued June 2003. WQC
issued Nov. 25, 2003. FEA to be issued Jan. 2004.
- Remaining Actions Need formal ESA consultation
(upon issuance of FEA). -