Lecture 22- Exterior Cladding Systems a.k.a skins - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Lecture 22- Exterior Cladding Systems a.k.a skins

Description:

Title: PowerPoint Presentation Author: Katherine Keane Last modified by: rcherf Created Date: 7/25/2002 10:52:43 PM Document presentation format: On-screen Show (4:3) – PowerPoint PPT presentation

Number of Views:327
Avg rating:3.0/5.0
Slides: 39
Provided by: Katherin179
Category:

less

Transcript and Presenter's Notes

Title: Lecture 22- Exterior Cladding Systems a.k.a skins


1
Lecture 22- Exterior Cladding Systems a.k.a skins
  • ARCH 330
  • Materials Methods
  • Fall 2008

2
Cladding/ Curtain Wall
  • Constructed in Place
  • Prefabricated

3
Cladding
  • A.K.A
  • Skin
  • Curtain Wall glass metal systems

4
Cladding
  • Non-load bearing exterior wall enclosure.
  • Most visible, most subject to attack by natural
    forces.
  • Separates indoor environment from outdoors in
    such a way that the indoor environment can be
    maintained at a level suitable for the building's
    intended use.

5
Primary Functions of Cladding
  • Keep Water Out
  • Prevent Air Leakage
  • Control Light (heat, glare, ultraviolet)
  • Control Radiation of Heat 
  • Control Conduction of Heat
  • Control Water Vapor 
  • Control Sound

6
Secondary Functions of Cladding
  • Resist Wind Forces 
  • Adjust to Movement
  • Thermal expansion and contraction,
  • Moisture expansion and contraction,
  • Structural deflections.
  • Resist Fire
  • Weather Gracefully

7
Forces that Move Water
  • Gravity
  • Momentum
  • Surface Tension
  • Capillary Action
  • Wind/ Air Currents

8
Rainscreen Principle
  • Let wind pressure differences between the outside
    and inside neutralize themselves

9
PECPressure Equalization Chamber
  • Pressure equalized wall design
  • Airtight barrier at the internal side
  • Rainscreen - loose fitting jointed layer
  • Current of air can pass back and forth through
    the unsealed joints.

10
Sealant Joints in Cladding
  • Fill/seal the joints
  • Prevent flow of air and/or water
  • Permit assembly tolerance
  • Permit movement

11
Design Process - Prefabricated 
  • (a) Curtain wall manufacturer selected and
    made a part of the building design team from the
    first stages of the project.
  •  
  • (b) The architect prepares a rough design and
    performance specification and submit these to
    several manufacturers for proposals.

12
  • STICK
  • 1. Anchor
  • 2. Mullion
  • 3. Horz rail
  • 4. Spandrel panel
  • 5. Horz rail
  • 6. Glass

13
Constructed in Place
  • Stiffening Method
  • Steel Sub Frame
  • Back-up Wall of Masonry
  • Back-up Wall of Light Gauge Studs

14
Prefabricated
  • Method of Assembly
  • Stick
  • Unit
  • Unit Mullion
  • Panel
  • Column Cover Sprandrel

15
Masonry
  • Constructed in place
  • Prefabricated

16
Metal Glass
  • Prefabricated

17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
  • Structural Glass

31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
  • Gehry - Guggenheim

38
Nicholas Grimshaw and Partners Ludwig Erhard Haus
Financial Centre