Title: Watermain Rehabilitation Eliminating the need for temporary bypass
1Watermain RehabilitationEliminating the need for
temporary bypass
Derrick Horsman, P.Eng. Alltech Solutions INC
2Overview
- Watermain problems and issues
- Spray Lining Overview
- Same Day Return to Service ?
Eliminating Temporary Bypass
3The Problem Despite recent increases in public
infrastructure investments, municipal
infrastructure is decaying faster than it is
being renewed.1
1 National Guide to Sustainable Municipal
Infrastructure.
Eliminating Temporary Bypass
4The Cause Internal (External) corrosion Watermain
breaks Pipe surpassed useful life
Eliminating Temporary Bypass
5High Rate of Leakage
- Inadequate Fire Protection
Eliminating Temporary Bypass
6Eliminating Temporary Bypass
7Eliminating Temporary Bypass
8What do we do?
Eliminating Temporary Bypass
9- Conventional open cut replacement
- Low dig options
- Directional drilling
- Sliplining
- Pipebursting
- CIPP lining
- Traditional Cleaning and Spray Lining
- Cement lining process
- Epoxy lining process
- Modern Cleaning and Spray Lining
- Rapid cure polyurethane system
- Rapid cure high build system
Eliminating Temporary Bypass
10Spray Lining
- TRADITIONAL CLEANING AND SPRAY LINING
- Cement Lining process
- Epoxy Lining process
- Less expensive
- No reduction in flow capacity
- No requirement to re-tap services
- Some disruption
- Not suitable for certain water types
- Superseded in Europe by polyurethane lining
systems. - Requires above ground temporary water supply
??
Eliminating Temporary Bypass
11Spray Lining
TRADITIONAL CLEANING AND CEMENT LINING
Eliminating Temporary Bypass
12Eliminating Temporary Bypass
13Eliminating Temporary Bypass
14Spray Lining
MODERN CLEANING AND SPRAY LINING Rapid Cure
Polyurethane system Rapid Cure High Build
system
Eliminating Temporary Bypass
15Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- Only approved rapid cure material lt15 sec
- Potential for contamination effectively
eliminated - No leaching
- Immediate rectification of lining faults
Eliminating Temporary Bypass
16Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- No requirement for above ground bypass
- Improved customer services multi-stage
notification process - Operations carried out during working hours
- Removes potential hazards (ie. Tripping hazards,
random breaks, security issues)
Eliminating Temporary Bypass
17Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- No requirement for above ground bypass
- Substantially less expensive
- - cost of bypass 20-45 of total job
(Awwarf) - Cost of temporary resources reduced
- Shorter construction duration
Eliminating Temporary Bypass
18Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- No requirement for above ground bypass
- Substantially less expensive
- Greatly reduced disruption
- Minimal setup time
- Rapid road reinstatement
- Small job site footprint
Eliminating Temporary Bypass
19Spray Lining
Eliminating Temporary Bypass
20Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- No requirement for above ground bypass
- Substantially less expensive
- Greatly reduced disruption
- Some revaluation of capital asset?
- No reduction in flow capacity
- Application of 1mm 5mm
Eliminating Temporary Bypass
21Spray Lining
- MODERN CLEANING AND SPRAY LINING
- Rapid Cure Polyurethane system
- Rapid Cure High Build system
- Same day return to service
- No requirement for above ground bypass
- Substantially less expensive
- Greatly reduced disruption
- Some revaluation of capital asset?
- No reduction in flow capacity
- No requirement to re-tap services
Eliminating Temporary Bypass
22Spray Lining High Build Structural System
Performance Requirements for Lining Material
- Tough enough to survive dynamic loading at
failure - Ductile enough to accommodate movement after
failure - Sufficient shear strength to maintain
longitudinal continuity - Sufficient flexural strength to provide long term
corrosion void spanning capability
Eliminating Temporary Bypass
23Spray Lining High Build Structural System
1 Bar 14.5 psi _at_3mm 145psi _at_5mm 348 psi
Eliminating Temporary Bypass
24Spray Lining Rapid Cure Polyurethane
- Rapid Cure Polyurethane North American Experience
- City of Saint John, NB
- City of Moncton, NB
- Atlantic Health Sciences Corporation, Saint John,
NB - Millstone Nuclear Power Plant, Niantic, CT, USA
- Region of Niagara, ON
- New York Department of Environmental Protection
- Rapid Cure Polyurethane International Experience
- United Kingdom, Russia, India, Switzerland and
Malaysia - More than 8,000 km in the UK by our partner
affiliates
Eliminating Temporary Bypass
25QUESTIONS ???
Eliminating Temporary Bypass