Watermain Rehabilitation Eliminating the need for temporary bypass Derrick Horsman, P.Eng. Alltech Solutions INC Overview Watermain problems and issues Spray Lining ... – PowerPoint PPT presentation

Number of Views:93
Avg rating:3.0/5.0
Slides: 26
Provided by: Allt4
Category:

less

Transcript and Presenter's Notes

Title: Watermain Rehabilitation Eliminating the need for temporary bypass


1
Watermain RehabilitationEliminating the need for
temporary bypass
Derrick Horsman, P.Eng. Alltech Solutions INC
2
Overview
  • Watermain problems and issues
  • Spray Lining Overview
  • Same Day Return to Service ?

Eliminating Temporary Bypass
3
The Problem Despite recent increases in public
infrastructure investments, municipal
infrastructure is decaying faster than it is
being renewed.1
1 National Guide to Sustainable Municipal
Infrastructure.
Eliminating Temporary Bypass
4
The Cause Internal (External) corrosion Watermain
breaks Pipe surpassed useful life
Eliminating Temporary Bypass
5
High Rate of Leakage
  • Inadequate Fire Protection

Eliminating Temporary Bypass
6
Eliminating Temporary Bypass
7
Eliminating Temporary Bypass
8
What do we do?
Eliminating Temporary Bypass
9
  • Conventional open cut replacement
  • Low dig options
  • Directional drilling
  • Sliplining
  • Pipebursting
  • CIPP lining
  • Traditional Cleaning and Spray Lining
  • Cement lining process
  • Epoxy lining process
  • Modern Cleaning and Spray Lining
  • Rapid cure polyurethane system
  • Rapid cure high build system

Eliminating Temporary Bypass
10
Spray Lining
  • TRADITIONAL CLEANING AND SPRAY LINING
  • Cement Lining process
  • Epoxy Lining process
  • Less expensive
  • No reduction in flow capacity
  • No requirement to re-tap services
  • Some disruption
  • Not suitable for certain water types
  • Superseded in Europe by polyurethane lining
    systems.
  • Requires above ground temporary water supply
    ??

Eliminating Temporary Bypass
11
Spray Lining
TRADITIONAL CLEANING AND CEMENT LINING
Eliminating Temporary Bypass
12
Eliminating Temporary Bypass
13
Eliminating Temporary Bypass
14
Spray Lining
MODERN CLEANING AND SPRAY LINING Rapid Cure
Polyurethane system Rapid Cure High Build
system
Eliminating Temporary Bypass
15
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • Only approved rapid cure material lt15 sec
  • Potential for contamination effectively
    eliminated
  • No leaching
  • Immediate rectification of lining faults

Eliminating Temporary Bypass
16
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • No requirement for above ground bypass
  • Improved customer services multi-stage
    notification process
  • Operations carried out during working hours
  • Removes potential hazards (ie. Tripping hazards,
    random breaks, security issues)

Eliminating Temporary Bypass
17
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • No requirement for above ground bypass
  • Substantially less expensive
  • - cost of bypass 20-45 of total job
    (Awwarf)
  • Cost of temporary resources reduced
  • Shorter construction duration

Eliminating Temporary Bypass
18
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • No requirement for above ground bypass
  • Substantially less expensive
  • Greatly reduced disruption
  • Minimal setup time
  • Rapid road reinstatement
  • Small job site footprint

Eliminating Temporary Bypass
19
Spray Lining
Eliminating Temporary Bypass
20
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • No requirement for above ground bypass
  • Substantially less expensive
  • Greatly reduced disruption
  • Some revaluation of capital asset?
  • No reduction in flow capacity
  • Application of 1mm 5mm

Eliminating Temporary Bypass
21
Spray Lining
  • MODERN CLEANING AND SPRAY LINING
  • Rapid Cure Polyurethane system
  • Rapid Cure High Build system
  • Same day return to service
  • No requirement for above ground bypass
  • Substantially less expensive
  • Greatly reduced disruption
  • Some revaluation of capital asset?
  • No reduction in flow capacity
  • No requirement to re-tap services

Eliminating Temporary Bypass
22
Spray Lining High Build Structural System
Performance Requirements for Lining Material
  1. Tough enough to survive dynamic loading at
    failure
  2. Ductile enough to accommodate movement after
    failure
  3. Sufficient shear strength to maintain
    longitudinal continuity
  4. Sufficient flexural strength to provide long term
    corrosion void spanning capability

Eliminating Temporary Bypass
23
Spray Lining High Build Structural System
1 Bar 14.5 psi _at_3mm 145psi _at_5mm 348 psi
Eliminating Temporary Bypass
24
Spray Lining Rapid Cure Polyurethane
  • Rapid Cure Polyurethane North American Experience
  • City of Saint John, NB
  • City of Moncton, NB
  • Atlantic Health Sciences Corporation, Saint John,
    NB
  • Millstone Nuclear Power Plant, Niantic, CT, USA
  • Region of Niagara, ON
  • New York Department of Environmental Protection
  • Rapid Cure Polyurethane International Experience
  • United Kingdom, Russia, India, Switzerland and
    Malaysia
  • More than 8,000 km in the UK by our partner
    affiliates

Eliminating Temporary Bypass
25
QUESTIONS ???