Sources of Changes in Design-Build Contracts for a Governmental Owner - PowerPoint PPT Presentation

About This Presentation
Title:

Sources of Changes in Design-Build Contracts for a Governmental Owner

Description:

Dr. Robert A. Perkins, PE Associate Professor, Dept. of Civil and Environmental Engineering, University of Alaska Fairbanks, 907 474 7694. ffrap_at_uaf.edu – PowerPoint PPT presentation

Number of Views:123
Avg rating:3.0/5.0
Slides: 43
Provided by: robertp92
Category:

less

Transcript and Presenter's Notes

Title: Sources of Changes in Design-Build Contracts for a Governmental Owner


1
Sources of Changes in Design-Build Contracts for
a Governmental Owner
  • Dr. Robert A. Perkins, PE
  • Associate Professor, Dept. of Civil and
    Environmental Engineering, University of Alaska
    Fairbanks, 907 474 7694. ffrap_at_uaf.edu
  • http//www.faculty.uaf.edu/ffrap/

2
William M. Tweed
3
1858
  • New York county allocated 250,000 for a new
    courthouse.
  • Escalated to 13 million
  • Boss Tweed and his gang got a 30 Commission on
    all contracts
  • Siphoned off 9 million
  • (135 million in 2007 dollars.)

4
Government Procurement Virtues
  • Public Confidence underpinned by attributes of
    accountability, transparency, equity and fair
    dealing in relation to procurement processes
  • Efficiency and effectiveness in use of pubic
    monies to achieve value for money and efficiency
    of delivery of procurement outcomes and
  • Policy compliance and consistency of both the
    processes and outcomes of procurement in relation
    to public welfare objectives and expectation of
    the public sector such as environmental issues,
    training and apprenticeships, international
    obligation and especially business and regional
    employment impacts

5
Government Contracting
  • Orville and Wilbur Wrights contract to build the
    first military aircraft was three and half pages
    long.
  • 19 different agencies surveyed 1978 and 1979
  • 877 different sets of procurement regulations,
    including directive, bulletins, and instructions
  • 64,600 pages of regulations, of which
  • 29,900 pages of which were promulgated or revised
    annually.

6
Construction
  • A 1970 federal survey found government building
    projects took 59 months to design and build while
    equivalent private sector projects took 24 months
  • 1986 through 1988, eight federal entities
    completed 268 building projects valued at more
    than 10 million each. 44 of those projects
    experienced time delays over 6 months and 23
    experienced cost increases over 10

7
Contracting Strategy for Procurement of
Construction
  • Project Delivery System
  • Procurement Method
  • QBS
  • Low bidder
  • Contract type
  • Lump Sum
  • TM

8
Project Delivery Systems
  • Design-Bid-Build
  • Design-Build
  • Construction Manager at Risk
  • Job Order Contracting
  • PPP, Public Private Partnerships
  • BOT, Build Own Transfer
  • BOOT, Build, own, operate, transfer
  • DBFO, design, build, finance, operate

9
DBB Traditional
  • Owner hires A/E
  • A/E designs and produces a bid package
  • Owner advertises for sealed bids
  • Opened publicly
  • Lowest bid gets the job
  • Must provide bond
  • Qualified bondable

10
Advantages of DBB
  • A/E designs what owner wants
  • Competition assures lowest price
  • Sufficient bidders
  • Transparent process
  • Fair process
  • No discretion no favoritism
  • Bonding can force performance

11
Disadvantages of DBB
  • Bids may come in over budget
  • Changes, Always changes
  • Design errors
  • Differing site conditions
  • Owner changes
  • Third party issues
  • Access, permits
  • Acts of God

12
Changes
  • Advantage goes to contractor
  • Essentially non-performance or breach by the
    owner
  • Contract clauses cover, but asymmetrical
    negotiations
  • Risks, i.e., schedule
  • Grey Areas

13
Opportunistic Bidding
  • Bid low just to get the opportunity
  • Contingency
  • Equipment

14
Design Build
  • Owner develops design criteria
  • Bridging design
  • Advertises for proposals
  • Two envelope proposals
  • Qualifications and Outline of Design
  • Price

15
Best Value
  • Might have presentations
  • Select best value for government
  • Most building for money

16
Criteria for a 46.6 Million Bridge
  • Durability 20
  • Quality of Design 17
  • Maintenance of Traffic 15
  • Maintainability 12
  • Quality of Construction 10
  • Understanding the Scope of Work 10
  • Quality of Schedule 5
  • Community Impacts 5
  • Aesthetics 5
  • Navigational Vertical Clearance 1
  • Total 100

17
Advantages of DB
  • Can consider contractors past business practices
  • Can compare actual price with outline design
  • Contractor and A/E work together to assure
    constructability
  • Innovation
  • Faster
  • Changes due to design errors reduced or
    eliminated

18
Disadvantages of DB
  • Design not entirely under Owners control
  • Can still have changes

19
Governmental DB
  • Prior to 1990, DBB was the preferred project
    delivery system
  • Could use DB and others, but needed special
    permission
  • often required a finding that DBB was not
    practical
  • Started to change rapidly in the 1990s

20
  • 1990, Federal Highway Administration SEP-14
  • 1996. Clinger-Cohen Act, 10 USC 2304,.
  • 2000 revision of the Model Procurement Code
  • Today about half the states have laws that allow
    some sort of best value procurement and
    design-build delivery.
  • But

21
Inertia
22
Select
  • Quality
  • Schedule
  • Cost

23
Quality
  • Pretty Good

24
Schedule
25
Cost
  • Terms
  • Construction Phase Cost Growth
  • Actual vs. planning
  • Construction Contract Cost Growth
  • changes
  • AKA delivery contract cost growth

26
  • A 2002 study by the National Institute of
    Standards and Technology and CII
  • Not statistically significant on construction
    phase
  • DB significantly better in changes
  • Not enough public projects
  • A 2003 study of 67 projects, mostly domestic but
    some overseas,
  • DBB had less cost growth
  • DB and DBB had similar changes
  • Government and non-governmental not distinguished

27
  • The 2005 Design-Build Effectiveness Study (USDOT
    2006)
  • Paired 11 similar DB and DBB transportation-relate
    d projects and compared the cost growth and
    changes the average project size was about 50
    million.
  • Contract cost growth was 6.0 for DB and 4.3 for
    DBB.
  • DB projects averaged 16 change orders with a
    total average cost of 837,000 per project, while
    DBB had 22 change orders that had an average of
    588,000 per project.
  • DB had fewer change orders but they cost more.
  • None of the results statistically significant.

28
Causes of Changes DB vs. DBB
  • Controllable vs. Non-controllable
  • Owner Project Managers Viewpoint
  • Controllable
  • Design Errors
  • Should have less
  • Uncontrollable
  • Differing site conditions
  • Same
  • User Changes
  • Could have more????

29
Schedule vs. Contracting
30
A/E works for Contractor
  • In DBB, the owner/user select the A/E
  • A/E has many design reviews with chances to
    sell features to the owner
  • A/E is trying to please owner, happy to make
    minor changes
  • In DB, the A/E works for the contractor and is
    reluctant to change
  • May lead to more changes

31
Causes of Changes
  • Owners change vs. Design error
  • 65 design review
  • User notices fixture is not optimum
  • Contractor says his design conforms to design
    criteria he bid on
  • If owners PM was in charge of design criteria,
    he will tend to see this as a user change rather
    than a design error.

32
Methods
  • Corps of Engineers
  • Northern and Southern Alaska Area Offices
  • Military Construction Projects
  • Resident Management System

33
Question
  • Are the causes of change different between the DB
    and DBB governmental contracts?
  • Specifically, were there more owner/user
    requested changes in DB than DBB.

34
No. of DB No. of DB No. of DBB
Housing 2 2 4
Barracks/Dormitory 2 2 5
Industrial 5 5 4
Utilidor 3 3 4
Other 2 2 3
Total 14 14 20
34 DB and DBB Combined 34 DB and DBB Combined 34 DB and DBB Combined
Average Cost 15.9 Million 15.9 Million
SD 11.8 Million 11.8 Million
35
Method
  • RMS, Resident Management System
  • Has all contract changes and causes
  • Type 1, Design Errors
  • Type 4, User Changes
  • Type 7, Differing Site Conditions
  • Others value engineering, miscellaneous changes,
    administrative changes, and construction changes,
    suspension of work, government furnished equipment

36
Construction Contract Cost Growth, Average No. of Changes Average Growth Cost,
DBB 6.6 25 1,069,882
DB 3.1 14 480,046
p value 1.7 1.5 4.6
37
Controllable vs. Uncontrollable
Controllable Changes Controllable Changes Uncontrollable Changes Uncontrollable Changes
No./average contract /average contract No./average contract /average contract
DBB 17 739,667 7 330,215
DB 6 190,791 9 290,539
p value 0.1 3.8 30.5 40.3
38
Source of Change
Type 1, Engineering Changes Type 1, Engineering Changes Type 4, User Changes Type 4, User Changes Type 7, Differing Site Conditions Type 7, Differing Site Conditions
No./avg contract /avg. contract No./avg. contract /avg. contract No./avg. contract /avg. contract
DBB 15 482,513 1 5,033 5 226,020
DB 4 195,714 5 71,514 3 221,524
p value 0.1 5.1 0.4 2.4 27.1 49
39
But, from raw data
  • 12 of 14 DB contracts had user changes
  • Only 9 of 20 DBB had any user changes
  • More user changes were work/cost reduction in DBB
  • Average DB change was 48,000 while average DBB
    change was -32,000
  • Absolute value of changes was similar, DB was
    53,000 and DBB was 59,000

40
  • There were no significant differences between the
    housing and industrial groups
  • There were no type 4 changes in the first few
    months of DB contracts.

41
Answers
  • There is clear advantage in DB in
    construction/delivery contract cost growth
  • This is primarily in reduced cost of design
    errors
  • There were statistically significant increase in
    number of user changes in DB over DBB
  • There were statistically significant increase in
    cost of user changes in DB over DBB, but
  • Cost difference may be anomaly

42
Conclusions
  • Construction contact cost growth is less with DB
  • Strong evidence there are more owner/user changes
    in DB
  • Advantage in design error cost growth outweighs
    disadvantage in owner/user changes
  • Future work should explore why there are more
    user changes (they did not occur early in the
    project).
Write a Comment
User Comments (0)
About PowerShow.com