Title: Sources of Changes in Design-Build Contracts for a Governmental Owner
1Sources of Changes in Design-Build Contracts for
a Governmental Owner
- Dr. Robert A. Perkins, PE
- Associate Professor, Dept. of Civil and
Environmental Engineering, University of Alaska
Fairbanks, 907 474 7694. ffrap_at_uaf.edu - http//www.faculty.uaf.edu/ffrap/
2William M. Tweed
31858
- New York county allocated 250,000 for a new
courthouse. - Escalated to 13 million
- Boss Tweed and his gang got a 30 Commission on
all contracts - Siphoned off 9 million
- (135 million in 2007 dollars.)
4Government Procurement Virtues
- Public Confidence underpinned by attributes of
accountability, transparency, equity and fair
dealing in relation to procurement processes - Efficiency and effectiveness in use of pubic
monies to achieve value for money and efficiency
of delivery of procurement outcomes and - Policy compliance and consistency of both the
processes and outcomes of procurement in relation
to public welfare objectives and expectation of
the public sector such as environmental issues,
training and apprenticeships, international
obligation and especially business and regional
employment impacts
5Government Contracting
- Orville and Wilbur Wrights contract to build the
first military aircraft was three and half pages
long. - 19 different agencies surveyed 1978 and 1979
- 877 different sets of procurement regulations,
including directive, bulletins, and instructions - 64,600 pages of regulations, of which
- 29,900 pages of which were promulgated or revised
annually.
6Construction
- A 1970 federal survey found government building
projects took 59 months to design and build while
equivalent private sector projects took 24 months
- 1986 through 1988, eight federal entities
completed 268 building projects valued at more
than 10 million each. 44 of those projects
experienced time delays over 6 months and 23
experienced cost increases over 10
7Contracting Strategy for Procurement of
Construction
- Project Delivery System
- Procurement Method
- QBS
- Low bidder
- Contract type
- Lump Sum
- TM
8Project Delivery Systems
- Design-Bid-Build
- Design-Build
- Construction Manager at Risk
- Job Order Contracting
- PPP, Public Private Partnerships
- BOT, Build Own Transfer
- BOOT, Build, own, operate, transfer
- DBFO, design, build, finance, operate
9DBB Traditional
- Owner hires A/E
- A/E designs and produces a bid package
- Owner advertises for sealed bids
- Opened publicly
- Lowest bid gets the job
- Must provide bond
- Qualified bondable
10Advantages of DBB
- A/E designs what owner wants
- Competition assures lowest price
- Sufficient bidders
- Transparent process
- Fair process
- No discretion no favoritism
- Bonding can force performance
11Disadvantages of DBB
- Bids may come in over budget
- Changes, Always changes
- Design errors
- Differing site conditions
- Owner changes
- Third party issues
- Access, permits
- Acts of God
12Changes
- Advantage goes to contractor
- Essentially non-performance or breach by the
owner - Contract clauses cover, but asymmetrical
negotiations - Risks, i.e., schedule
- Grey Areas
13Opportunistic Bidding
- Bid low just to get the opportunity
- Contingency
- Equipment
14Design Build
- Owner develops design criteria
- Bridging design
- Advertises for proposals
- Two envelope proposals
- Qualifications and Outline of Design
- Price
15Best Value
- Might have presentations
- Select best value for government
- Most building for money
16Criteria for a 46.6 Million Bridge
- Durability 20
- Quality of Design 17
- Maintenance of Traffic 15
- Maintainability 12
- Quality of Construction 10
- Understanding the Scope of Work 10
- Quality of Schedule 5
- Community Impacts 5
- Aesthetics 5
- Navigational Vertical Clearance 1
- Total 100
17Advantages of DB
- Can consider contractors past business practices
- Can compare actual price with outline design
- Contractor and A/E work together to assure
constructability - Innovation
- Faster
- Changes due to design errors reduced or
eliminated
18Disadvantages of DB
- Design not entirely under Owners control
- Can still have changes
19Governmental DB
- Prior to 1990, DBB was the preferred project
delivery system - Could use DB and others, but needed special
permission - often required a finding that DBB was not
practical - Started to change rapidly in the 1990s
20- 1990, Federal Highway Administration SEP-14
- 1996. Clinger-Cohen Act, 10 USC 2304,.
- 2000 revision of the Model Procurement Code
- Today about half the states have laws that allow
some sort of best value procurement and
design-build delivery. - But
21Inertia
22Select
23Quality
24Schedule
25Cost
- Terms
- Construction Phase Cost Growth
- Actual vs. planning
- Construction Contract Cost Growth
- changes
- AKA delivery contract cost growth
26- A 2002 study by the National Institute of
Standards and Technology and CII - Not statistically significant on construction
phase - DB significantly better in changes
- Not enough public projects
- A 2003 study of 67 projects, mostly domestic but
some overseas, - DBB had less cost growth
- DB and DBB had similar changes
- Government and non-governmental not distinguished
27- The 2005 Design-Build Effectiveness Study (USDOT
2006) - Paired 11 similar DB and DBB transportation-relate
d projects and compared the cost growth and
changes the average project size was about 50
million. - Contract cost growth was 6.0 for DB and 4.3 for
DBB. - DB projects averaged 16 change orders with a
total average cost of 837,000 per project, while
DBB had 22 change orders that had an average of
588,000 per project. - DB had fewer change orders but they cost more.
- None of the results statistically significant.
28Causes of Changes DB vs. DBB
- Controllable vs. Non-controllable
- Owner Project Managers Viewpoint
- Controllable
- Design Errors
- Should have less
- Uncontrollable
- Differing site conditions
- Same
- User Changes
- Could have more????
29Schedule vs. Contracting
30A/E works for Contractor
- In DBB, the owner/user select the A/E
- A/E has many design reviews with chances to
sell features to the owner - A/E is trying to please owner, happy to make
minor changes - In DB, the A/E works for the contractor and is
reluctant to change - May lead to more changes
31Causes of Changes
- Owners change vs. Design error
- 65 design review
- User notices fixture is not optimum
- Contractor says his design conforms to design
criteria he bid on - If owners PM was in charge of design criteria,
he will tend to see this as a user change rather
than a design error.
32Methods
- Corps of Engineers
- Northern and Southern Alaska Area Offices
- Military Construction Projects
- Resident Management System
33Question
- Are the causes of change different between the DB
and DBB governmental contracts? - Specifically, were there more owner/user
requested changes in DB than DBB.
34No. of DB No. of DB No. of DBB
Housing 2 2 4
Barracks/Dormitory 2 2 5
Industrial 5 5 4
Utilidor 3 3 4
Other 2 2 3
Total 14 14 20
34 DB and DBB Combined 34 DB and DBB Combined 34 DB and DBB Combined
Average Cost 15.9 Million 15.9 Million
SD 11.8 Million 11.8 Million
35Method
- RMS, Resident Management System
- Has all contract changes and causes
- Type 1, Design Errors
- Type 4, User Changes
- Type 7, Differing Site Conditions
- Others value engineering, miscellaneous changes,
administrative changes, and construction changes,
suspension of work, government furnished equipment
36Construction Contract Cost Growth, Average No. of Changes Average Growth Cost,
DBB 6.6 25 1,069,882
DB 3.1 14 480,046
p value 1.7 1.5 4.6
37Controllable vs. Uncontrollable
Controllable Changes Controllable Changes Uncontrollable Changes Uncontrollable Changes
No./average contract /average contract No./average contract /average contract
DBB 17 739,667 7 330,215
DB 6 190,791 9 290,539
p value 0.1 3.8 30.5 40.3
38Source of Change
Type 1, Engineering Changes Type 1, Engineering Changes Type 4, User Changes Type 4, User Changes Type 7, Differing Site Conditions Type 7, Differing Site Conditions
No./avg contract /avg. contract No./avg. contract /avg. contract No./avg. contract /avg. contract
DBB 15 482,513 1 5,033 5 226,020
DB 4 195,714 5 71,514 3 221,524
p value 0.1 5.1 0.4 2.4 27.1 49
39But, from raw data
- 12 of 14 DB contracts had user changes
- Only 9 of 20 DBB had any user changes
- More user changes were work/cost reduction in DBB
- Average DB change was 48,000 while average DBB
change was -32,000 - Absolute value of changes was similar, DB was
53,000 and DBB was 59,000
40- There were no significant differences between the
housing and industrial groups - There were no type 4 changes in the first few
months of DB contracts.
41Answers
- There is clear advantage in DB in
construction/delivery contract cost growth - This is primarily in reduced cost of design
errors - There were statistically significant increase in
number of user changes in DB over DBB - There were statistically significant increase in
cost of user changes in DB over DBB, but - Cost difference may be anomaly
42Conclusions
- Construction contact cost growth is less with DB
- Strong evidence there are more owner/user changes
in DB - Advantage in design error cost growth outweighs
disadvantage in owner/user changes - Future work should explore why there are more
user changes (they did not occur early in the
project).