A tutorial on MS Project James Burns Learning Objectives Entering Tasks in the Gantt View Task subordination Linking of Tasks Setting start & stop dates Assigning ... – PowerPoint PPT presentation

Number of Views:104
Avg rating:3.0/5.0
Slides: 27
Provided by: Jam143
Learn more at: http://burns.ba.ttu.edu
Category:

less

Transcript and Presenter's Notes

Title: A tutorial on MS Project


1
A tutorial on MS Project
  • James Burns

2
Learning Objectives
  • Entering Tasks in the Gantt View
  • Task subordination
  • Linking of Tasks
  • Setting start stop dates
  • Assigning resources
  • Calculating costs

2
2
3
More Learning Objectives
  • Recurring tasks
  • STATISTICS
  • Zoom out/zoom in
  • Precedence relationships
  • Lags between links

4
PM Software in general
5
Popular Project Management Software Packages
  • CA-SuperProject
  • Microsoft Project
  • Project Scheduler
  • SureTrak Project Manager
  • Time Line
  • High-End Project Management Software

6
Criteria for Selecting Project Management Software
  • Capacity
  • Documentation and on-line help facilities
  • Ease of use
  • Features available
  • Integration with other systems

4
7
Additional Criteria
  • Installation requirements
  • Reporting capabilities
  • Security
  • Vendor Support

8
Advantages of Using Project Management Software
  • Accuracy
  • Affordability
  • Ease of use
  • Ability to handle complexity
  • Maintainability and modifiability
  • Record keeping
  • Speed
  • What-if analysis

5
9
Concerns about Using Project Management Software
  • Becoming distracted by the software
  • A false sense of security
  • Information overload
  • The learning curve
  • Over-reliance on software

6
10
Must start with
  • A list of tasks
  • Or
  • A Work Breakdown Structure
  • Always make your first task a PROJECT summary
    task to which all other tasks are subordinate

11
Bring up MS Project
  • Start in the Gantt View
  • Enter task detail in the entry table to the left
  • Subordinate tasks appropriately
  • Link Tasks as appropriate

12
Project Information Box
13
Project Information Box
  • Can schedule from a start date or backward from a
    stop date
  • Can choose a particular calendar typethat makes
    assumptions about when people will be working

14
The Main Window of MS Project
15
Entering Tasks in the Gantt View
  • Enter Tasks into the entry table on the GANTT
    view
  • Entry table is behind the GANTT chart and works
    just like a spreadsheet
  • Can also enter tasks in the network diagram or
    the task usage views

16
Tables
  • You can choose a variety of tables to view in
    conjunction with the Gantt view
  • Entry, Cost, Schedule, Tracking, Earned value,
    Usage, Variance, Work, Hyperlink are just some
    of the tables you can choose from
  • Click on View on the Menu bar and then click on
    Table
  • To view all the tables, click on More Tables

17
Columns
  • You can add columns to any table in the Gantt
    view
  • Click on Insert and then Columns
  • Select the column you want included in the table
    by clicking on the dropdown arrow associated with
    the first box and selecting the desired column
    name
  • Click on OK
  • That column will be included in the table to the
    left of the point where the selected cell
    appears

18
Predefined Reports
  • MS Project provides a number of predefined,
    static reports that can be displayed and printed
  • Click on View and the Reports
  • The categories are Overview, Current Activities,
    Costs, Assignments, Workload and Custom

19
Task subordination
  • Use indent arrow
  • MS Proj has a WBS understanding and assigns a WBS
    code even though it does not explicitly exhibit a
    WBS chart

20
Linking of Tasks
  • Select tasks to be linked
  • Click on the chain-link icon
  • Decide on precedence relationship FS, SS, FF,
    SF

21
Setting start stop dates
  • When you set a date in the entry table of the
    Gantt view, MS Project treats it as if it were a
    hard constraint
  • It schedules everything around such hard dates

22
Assigning resources
  • Resources have to be created before they can be
    assigned
  • You can use the faces icon in the Gantt view to
    both create and assign resources
  • Resources are created once they are named
  • Alternatively, you can create resources in the
    Resources Sheet view
  • Simply click on this view in the column on the
    left.

23
Calculating costs
  • Fixed costs
  • Enter these in the cost table
  • From the VIEW menu item change to the cost table
  • Enter fixed costs
  • Variable costs
  • Enter resource hourly rates
  • MS Project will calculate

24
Project Management Software Features
  • Budgeting and cost control
  • Calendars
  • Email
  • Graphics
  • Importing/exporting data
  • Handling multiple projects and subprojects
  • Report generation

3
3
25
Project Management Software Additional Features
  • Resource management
  • Planning
  • Project monitoring and tracking
  • Scheduling
  • Security
  • Sorting and filtering
  • What-if analysis