Ethan A. Battiston 2004 AE Senior Thesis Construction Management The Edgemoor Condominiums Bethesda, Maryland Project Overview PN Hoffman Construction Development The ... – PowerPoint PPT presentation

Number of Views:87
Avg rating:3.0/5.0
Slides: 37
Provided by: Bat992
Learn more at: https://www.engr.psu.edu
Category:

less

Transcript and Presenter's Notes

Title: Ethan A. Battiston 2004 AE Senior Thesis Construction Management


1
Ethan A. Battiston2004 AE Senior
ThesisConstruction Management
The Edgemoor CondominiumsBethesda, Maryland
2
Ethan A. Battiston2004 AE Senior
ThesisConstruction Management
  • Project Overview
  • PN Hoffman Construction Development
  • The Edgemoor Condominiums
  • Schedule Reduction of Finishing Trades
  • Matrix Scheduling
  • Activity Train Development
  • Improves Cash Flow
  • 3D MEP Coordination
  • 3D Model of Single Unit
  • Avoiding Design Busts
  • Structural Floor Slab Redesign
  • Reduces Construction Cost
  • Reduces the Number of Activities Associated with
    Buildings Structure

3
Project Overview
  • PN Hoffman Construction Development
  • Owner and General Contractor
  • Construction Management Team
  • Design Development Team (Sales)
  • QA Department

4
Project Overview
  • Edgemoor Condominiums
  • 10 Floors with 3 Sub-Grade Garage levels
  • Traditional Double-Hung Windows
  • Two Floors of Pre-Cast Stone

5
Project Overview
  • Edgemoor Condominiums
  • Balconies with Cast Iron Decorative Railings
  • Fiber Reinforced Plastic (FRP)
  • Mansard Roof with Copper Gutters and Down Spouts

6
Project Overview
  • Edgemoor Interior
  • Open Floor Plan
  • Bamboo or Oak Flooring
  • Oversized Base Board
  • Wood Paneled Doors

7
Project Overview
  • Edgemoor Interior
  • Open Kitchen design
  • Stainless Steel Appliances
  • Granite Kitchen Counters
  • Maple or Cherry Cabinet Finishes
  • Ventless Gas Fireplaces

8
Schedule Reduction
  • Existing Conditions
  • SIPS
  • Work Zones
  • Matrix Schedule
  • Activity Train
  • Overall Schedule Reduction

9
Schedule Reduction
  • Existing Conditions
  • Large Amount of Trade Work on Lower Floors
  • Weekend Shifts Mandatory
  • Interior Trades Became Increasingly Off Schedule
  • Delays Due to Shipping and Weather

10
Schedule Reduction
  • Short Interval Production Schedule SIPS
  • Ideal For Repetitive Projects and Activities
  • Utilizes High Level of Detail
  • Sets Crew Sizes to Unify Activity Durations

11
Schedule Reduction
  • SIPS
  • Uses Many Efficient Tools
  • Work Zone Identification
  • Activity Trains
  • Matrix Scheduling

12
Schedule Reduction
  • Work Zones Identification
  • East Zone Mirrors West Zone

13
Schedule Reduction
  • Activity Train
  • Activity Train

14
Schedule Reduction
  • Activity Train
  • Activity Train

Duration in Weeks
1st Floor East Zone
1st Floor West Zone
Activities 1-36 1 Activity Per Week Per Zone
15
Schedule Reduction
  • Matrix Schedule
  • Microsoft Excel Worksheet
  • Intended For Weekly Updates

16
Schedule Reduction
  • Matrix Cells

Actual Date
Scheduled Date
1 Day Off Schedule
Floor
Actual Start
Actual Finish
Scheduled Start
Scheduled Finish
Actual Duration
17
Schedule Reduction
  • Conclusion
  • 2 Week Overall Reduction

18
Schedule Reduction
  • Conclusion
  • Large Schedule Reduction on Lower Floors
  • Improves Cash Flow

19
MEP Coordination
  • MEP Coordination
  • Limited Pre-Construction MEP Coordination
  • First Come, First Serve Approach
  • Limited Bulkhead Space
  • 3D CAD

20
MEP Coordination
  • Limited Bulkhead Space

21
MEP Coordination
  • 3D CAD

22
MEP Coordination
  • 3D CAD
  • No Direct Routing Due to Exposed Ceiling Finish

23
MEP Coordination
Ductwork Space
  • 3D CAD
  • Trade Work Locations

Bulkhead Framing
Electrical Space
Fire Protection Space
Exhaust Vent
24
MEP Coordination
  • 3D CAD
  • Identifies Problem Areas

Fire Protection Space
Exhaust Vent
Problem Area
25
Structural Floor Slab Redesign
  • Hollow Core Planks ILO Post Tension Slab
  • Existing Floor Slab System
  • Hollow Core Planks
  • Girder Dimensions
  • Hollow Core vs. Post Tension Cost Analysis

26
Structural Floor Slab Redesign
  • Existing Floor Slab System
  • Cast-In-Place Concrete on all Columns and Garage
    Levels
  • 7 Thick Post Tensioned Concrete Slab (2nd Floor
    to Roof Slab)
  • 5,000 PSI _at_ 28 Day Compressive Strength
  • Design Live Load 40 PSF 20 PSF for partitions
    60 PSF

27
Structural Floor Slab Redesign
  • Hollow Core Planks w/ 2 Top Coat (Nitterhouse,
    Inc.)
  • Max Clear Span 25
  • Thickness 8 ( 2 Top Coat)
  • Allowable Live Load _at_ 25 98 PSF gt 60 PSF
    Design Live Load
  • 5,000 PSI _at_ 28 Day Compressive Strength

28
Structural Floor Slab Redesign
  • Hollow Core Plank Layout
  • 127 Planks per Floor x 10 Floors 1,270 Total

29
Structural Floor Slab Redesign
  • Average Estimated Girder Dimensions
  • Avg. Clear Span 20
  • Width Depth
  • Mu 69K-Ft
  • d2 (R Mu)/b ? (d2 (30 71K-Ft)/8 )
  • b 8 d16
  • Bar Sizes
  • As (Mu Musw)/4d ? (78.3K-Ft)/(4 16)
    1.45 in2
  • 2 8 Bars 1.58 in2
  • Mn (1.58 in2)(60ksi)(13.5 (1.74/2))
    99.8K-Ft
  • 99.8K-Ft gt 78.3K-Ft ? O.K.

30
Structural Floor Slab Redesign
  • Average Estimated Girder Dimensions

31
Structural Floor Slab Redesign
  • Girder Layout
  • Avg. Clear Span 20
  • 5,200 Linear Feet

32
Structural Floor Slab Redesign
  • Hollow Core vs. Post Tension Cost Analysis
  • Post Tensioned System
  • 3,470 CY
  • Unit Price 370 per CY
  • Total Cost 1,283,000
  • Hollow Core System Estimate
  • 115,000 SQFT
  • Unit Price of Planks 4.71 per SQFT 541,000
  • Pre-Cast Girders 126 per LNFT 655,000
  • Total Cost 1,196,000
  • 87,000 Savings in Construction Costs

33
Structural Floor Slab Redesign
  • Conclusion
  • Minimal Overall Building Height Increase lt 3 FT
  • Allows for Early Start Dates For Other Activities
    by Eliminating Most of the Scaffolding and
    Formwork Activities
  • Minimal Altercation to Existing Floor Plan
  • Total Cost Savings 87,000

34
Summary
  • Schedule Reduction of Finishing Trades
  • Matrix Schedule Worksheet Helps Manage Finishing
    Trades
  • Overall Schedule Reduction is 2 Weeks
  • Improves Cash Flow Due to Early Owner Occupancy
    on Lower Floors
  • 3D MEP Coordination
  • Helps Contractors Graphically Identify Problem
    Areas
  • Improves On-Site MEP Contractor Efficiency
  • Structural Floor Slab Redesign
  • Pre-Cast Hollow Core Planks Reduces Construction
    Cost by 87,000
  • Minimal Impact on Interior Architectural
    Integrity

35
Special Thanks
  • AE Faculty Staff
  • PN Hoffman Construction Development
  • Steve Schrenk Project Executive
  • Tom Kenton Project Manager
  • Gary Ward Site Manager
  • Brian Zemcik Asst. Site Manager

36
Questions?