Title: Ethan A. Battiston 2004 AE Senior Thesis Construction Management
1Ethan A. Battiston2004 AE Senior
ThesisConstruction Management
The Edgemoor CondominiumsBethesda, Maryland
2Ethan A. Battiston2004 AE Senior
ThesisConstruction Management
- Project Overview
- PN Hoffman Construction Development
- The Edgemoor Condominiums
- Schedule Reduction of Finishing Trades
- Matrix Scheduling
- Activity Train Development
- Improves Cash Flow
- 3D MEP Coordination
- 3D Model of Single Unit
- Avoiding Design Busts
- Structural Floor Slab Redesign
- Reduces Construction Cost
- Reduces the Number of Activities Associated with
Buildings Structure
3Project Overview
- PN Hoffman Construction Development
- Owner and General Contractor
- Construction Management Team
- Design Development Team (Sales)
- QA Department
4Project Overview
- Edgemoor Condominiums
- 10 Floors with 3 Sub-Grade Garage levels
- Traditional Double-Hung Windows
- Two Floors of Pre-Cast Stone
5Project Overview
- Edgemoor Condominiums
- Balconies with Cast Iron Decorative Railings
- Fiber Reinforced Plastic (FRP)
- Mansard Roof with Copper Gutters and Down Spouts
6Project Overview
- Edgemoor Interior
- Open Floor Plan
- Bamboo or Oak Flooring
- Oversized Base Board
- Wood Paneled Doors
7Project Overview
- Edgemoor Interior
- Open Kitchen design
- Stainless Steel Appliances
- Granite Kitchen Counters
- Maple or Cherry Cabinet Finishes
- Ventless Gas Fireplaces
8Schedule Reduction
- Existing Conditions
- SIPS
- Work Zones
- Matrix Schedule
- Activity Train
- Overall Schedule Reduction
9Schedule Reduction
- Existing Conditions
- Large Amount of Trade Work on Lower Floors
- Weekend Shifts Mandatory
- Interior Trades Became Increasingly Off Schedule
- Delays Due to Shipping and Weather
10Schedule Reduction
- Short Interval Production Schedule SIPS
- Ideal For Repetitive Projects and Activities
- Utilizes High Level of Detail
- Sets Crew Sizes to Unify Activity Durations
11Schedule Reduction
- SIPS
- Uses Many Efficient Tools
- Work Zone Identification
- Activity Trains
- Matrix Scheduling
12Schedule Reduction
- Work Zones Identification
- East Zone Mirrors West Zone
13Schedule Reduction
- Activity Train
- Activity Train
14Schedule Reduction
- Activity Train
- Activity Train
Duration in Weeks
1st Floor East Zone
1st Floor West Zone
Activities 1-36 1 Activity Per Week Per Zone
15Schedule Reduction
- Matrix Schedule
- Microsoft Excel Worksheet
- Intended For Weekly Updates
16Schedule Reduction
Actual Date
Scheduled Date
1 Day Off Schedule
Floor
Actual Start
Actual Finish
Scheduled Start
Scheduled Finish
Actual Duration
17Schedule Reduction
- Conclusion
- 2 Week Overall Reduction
18Schedule Reduction
- Conclusion
- Large Schedule Reduction on Lower Floors
- Improves Cash Flow
19MEP Coordination
- MEP Coordination
- Limited Pre-Construction MEP Coordination
- First Come, First Serve Approach
- Limited Bulkhead Space
- 3D CAD
20MEP Coordination
21MEP Coordination
22MEP Coordination
- 3D CAD
- No Direct Routing Due to Exposed Ceiling Finish
23MEP Coordination
Ductwork Space
- 3D CAD
- Trade Work Locations
Bulkhead Framing
Electrical Space
Fire Protection Space
Exhaust Vent
24MEP Coordination
- 3D CAD
- Identifies Problem Areas
Fire Protection Space
Exhaust Vent
Problem Area
25Structural Floor Slab Redesign
- Hollow Core Planks ILO Post Tension Slab
- Existing Floor Slab System
- Hollow Core Planks
- Girder Dimensions
- Hollow Core vs. Post Tension Cost Analysis
26Structural Floor Slab Redesign
- Existing Floor Slab System
- Cast-In-Place Concrete on all Columns and Garage
Levels - 7 Thick Post Tensioned Concrete Slab (2nd Floor
to Roof Slab) - 5,000 PSI _at_ 28 Day Compressive Strength
- Design Live Load 40 PSF 20 PSF for partitions
60 PSF
27Structural Floor Slab Redesign
- Hollow Core Planks w/ 2 Top Coat (Nitterhouse,
Inc.) - Max Clear Span 25
- Thickness 8 ( 2 Top Coat)
- Allowable Live Load _at_ 25 98 PSF gt 60 PSF
Design Live Load - 5,000 PSI _at_ 28 Day Compressive Strength
28Structural Floor Slab Redesign
- Hollow Core Plank Layout
- 127 Planks per Floor x 10 Floors 1,270 Total
29Structural Floor Slab Redesign
- Average Estimated Girder Dimensions
- Avg. Clear Span 20
- Width Depth
- Mu 69K-Ft
- d2 (R Mu)/b ? (d2 (30 71K-Ft)/8 )
- b 8 d16
- Bar Sizes
- As (Mu Musw)/4d ? (78.3K-Ft)/(4 16)
1.45 in2 - 2 8 Bars 1.58 in2
- Mn (1.58 in2)(60ksi)(13.5 (1.74/2))
99.8K-Ft - 99.8K-Ft gt 78.3K-Ft ? O.K.
30Structural Floor Slab Redesign
- Average Estimated Girder Dimensions
31Structural Floor Slab Redesign
- Girder Layout
- Avg. Clear Span 20
- 5,200 Linear Feet
32Structural Floor Slab Redesign
- Hollow Core vs. Post Tension Cost Analysis
- Post Tensioned System
- 3,470 CY
- Unit Price 370 per CY
- Total Cost 1,283,000
- Hollow Core System Estimate
- 115,000 SQFT
- Unit Price of Planks 4.71 per SQFT 541,000
- Pre-Cast Girders 126 per LNFT 655,000
- Total Cost 1,196,000
- 87,000 Savings in Construction Costs
33Structural Floor Slab Redesign
- Conclusion
- Minimal Overall Building Height Increase lt 3 FT
- Allows for Early Start Dates For Other Activities
by Eliminating Most of the Scaffolding and
Formwork Activities - Minimal Altercation to Existing Floor Plan
- Total Cost Savings 87,000
34Summary
- Schedule Reduction of Finishing Trades
- Matrix Schedule Worksheet Helps Manage Finishing
Trades - Overall Schedule Reduction is 2 Weeks
- Improves Cash Flow Due to Early Owner Occupancy
on Lower Floors - 3D MEP Coordination
- Helps Contractors Graphically Identify Problem
Areas - Improves On-Site MEP Contractor Efficiency
- Structural Floor Slab Redesign
- Pre-Cast Hollow Core Planks Reduces Construction
Cost by 87,000 - Minimal Impact on Interior Architectural
Integrity
35Special Thanks
- AE Faculty Staff
- PN Hoffman Construction Development
- Steve Schrenk Project Executive
- Tom Kenton Project Manager
- Gary Ward Site Manager
- Brian Zemcik Asst. Site Manager
36Questions?