SEASAT Lessons Learned . . . And Not Learned - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

SEASAT Lessons Learned . . . And Not Learned

Description:

Lessons Learned . . . And Not Learned Rick Obenschain Acting Director of Flight Programs and Projects NASA Goddard Space Flight Center Rick Obenschain – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 19
Provided by: BrianK70
Learn more at: http://klabs.org
Category:

less

Transcript and Presenter's Notes

Title: SEASAT Lessons Learned . . . And Not Learned


1
SEASATLessons Learned . . .And Not Learned
Rick Obenschain Acting Director of Flight
Programs and Projects NASA Goddard Space Flight
Center
Rick Obenschain Arthur.F.Obenschain_at_nasa.gov
2
COLUMBIA
  • Physical cause of the loss of Shuttle Columbia
    a breach in the Thermal Protection System on the
    leading edge of the left wing caused by a piece
    of insulating foam which separated from the left
    bipod ramp section of the external tank at 81.7
    seconds after launch, and struck the wing in the
    vicinity of the lower half of Reinforced Carbon
    panel number 8.
  • Organizational Contributions to Loss
  • Original design/implementation shortfalls
    required to stay within budgetary limitation that
    enabled the Shuttle program
  • Continuing schedule/funding constraints find
    ways to do more with less
  • Workforce downsized
  • Outsourced various shuttle program
    responsibilities including safety oversight
  • Reliance on past success as a substitute for
    sound engineering practices
  • Organizational barriers that prevented effective
    communication of critical safety information
  • Unwillingness to listen to alternate
    view/concerns
  • Evolution of an informal chain of command and
    decision making processes that operated outside
    of organizations rules

3
WIRE
  • Physical Cause FPGA Transient on startup clock
    oscillator start time
  • Organization Contributions to loss
  • Pyro Box Simple, not focused on, never reviewed,
    fell through cracks
  • NASA attempts to penetrate design review blocked
  • Failures in IT Didnt go through schematics
    blamed on test equipment by similarity
  • Didnt contact designer or design organization
  • Didnt write malfunction report which prevented
    failures from being reviewed
  • Result immediate failure on orbit

4
CHALLENGER
  • Physical cause of the loss of Shuttle a
    failure of the joint and seal between the lower
    segments of the right Solid Rocket Booster. Hot
    gases blew past a rubber O-ring in the joint,
    leading to structural failure and explosive
    burning of the shuttles Hydrogen fuel.
  • A number of significant NASA management failures
    highlighted
  • Communication failures and incomplete/misleading
    information
  • Key shuttle managers unaware of flight safety
    program
  • Contractors required to prove it was not safe to
    launch, rather than proving it was safe
  • Multiple missed warning signs seal and joint
    degradations accepted as deviations
  • Safety Management displayed a lack of problem
    reporting requirements, inadequate trend
    analysis, misrepresentation of criticality and
    lack of involvement in critical decisions
  • NASA Human Space Flight Culture
  • Despite many outward management changes, the
    culture remained largely intact
  • By the winter of 2003 institutional practices
    that were in effect at the time of Challenger
    inadequate concern over deviations from expected
    performance, a silent safety program and
    schedule pressure - had returned

5
SEASAT
  • Spacecraft launched June 26, 1978, Spacecraft
    failed October 9, 1978 Mission Lifetime 1503
    revolutions/105 days
  • Fully Redundant Spacecraft Bus a single
    redundant system failed and caused mission loss

6
SEASAT
  • Spacecraft failure caused by loss of electrical
    power resulting from a massive, progressive short
    in one of the ship ring assemblies used to
    connect the rotating solar arrays into the power
    system

7
SEASAT
  • Arc between two adjacent ship ring brush
    assemblies most adjacent brush assemblies were
    of opposite electrical polarity
  • Wire-to-brush assembly contact
  • Brush-to-brush contact
  • Momentary short caused by a contaminant that
    bridged internal components of opposite
    electrical polarity

8
SEASAT
  • Slip ring failure possibilities well known within
    prime contractor facility failures occurred on
    other programs. No communication within company
    of failures

9
SEASAT Contd.
  • Feeling that existing spacecraft bus design was
    standard, although three of the major subsystems
    were substantially modified
  • Even when it became evident that significant
    changes were being made, belief in qualification
    by similarity persisted
  • Program policy to minimize testing and
    documentation
  • Program direction to minimize penetration into
    standard bus by government
  • Important component failures were not reported to
    project management, tests were waived without
    proper approval and compliance with specification
    was weak
  • Failure modes and effects analyses incomplete
    did not even consider shorting failure mode did
    not provide a basis for development of a full
    complement of safing command sequences that could
    be used by the flight controllers in responding
    to in-flight anomalies
  • Proper FMECA would have demonstrated risk areas
    and permitted simple design changes to be
    implemented
  • Controllers not sufficiently knowledgeable of
    systems being controlled post failure analysis
    demonstrated that it would have been possible to
    separate bus into two sections with associated
    reduction in capabilities

10
What Caused the Failure
  • Environment
  • Seasat conceived/initiated during post Apollo era
  • Apollo characterized by extensive test programs,
    large formal documentation systems and
    comprehensive/frequent technical and management
    reviews
  • NASA Low Cost Systems Office established to
    promote use of standardized hardware
  • Emphasis on shifting work out-of-house to reduce
    NASA workforce base
  • Design-to-cost techniques, cost benefits of
    heritage through use of hardware and software
    developed for other programs emphasized in the
    approval cycle
  • Management Philosophy
  • Design to cost fundamental tenet of Seasat
    Project definition overruns to be offset by
    descoping mission content
  • To satisfy small funding contingency for the
    spacecraft bus, only government role was
    monitoring contractors activity maximum
    reliance placed on existing contractor management
    systems and procedures

11
What Caused the Failure Contd.
  • Treat Launch Readiness date as a Planetary
    Launch Opportunity
  • Program initiation delayed 8 months launch date
    shipped 6 weeks
  • As cost escalations were experienced on both the
    instrumentation and spacecraft platforms, HQ
    pressure to cut back/eliminate penetration of
    spacecraft bus
  • Increasing reliance on tenet that spacecraft bus
    had extensive, flight proven history despite fact
    many changes were creeping in
  • In power system alone, solar arrays were first
    application of a rotating array on the aft end of
    the spacecraft bus, the slip ring assembly had no
    applicable flight experience and the solar array
    drive electronics had undergone extensive
    redesign

12
What Caused the Failure Contd.
  • Hardware
  • Slip ring assembly design, development and parts
    qualification completed for earlier program
    cancelled prior to flight
  • Although not a direct match for requirements,
    decision made to use existing hardware
  • Unnecessarily crowded mechanical design
  • Subcontractor request to lengthen assembly denied
    due to programmatic reasons that did not apply
    to SEASAT
  • Decision made to alternate positive/negative
    communication to brushes to reduce magnetic
    moments requirement that did not exist
  • Significant slip ring problems noted a contractor
    facility on other program never conveyed to
    SEASAT
  • Slip ring assembly on another program at
    contractors plant modified wiring to eliminate
    alternating plus/minus power configuration
    SEASAT decided not necessary as slip rings not
    powered during launch vibration environment
    (Prelaunch operational change did apply power to
    slip rings during launch)

13
Slip Ring Assembly
14
What Caused the Failure Contd.
  • Quality Assurance and Flight Readiness
  • Compliance with requirements weak requirement
    that all electronic assemblies undergo at least
    eight thermal/thermal vacuum cycles not contained
    in slip ring component assembly specification
  • No closed loop compliance system to validate
    contractual requirements met
  • Qualification by similarity very loosely
    interpreted
  • Failure modes effects criticality analysis showed
    no power system single point failure

15
What Caused the Failure Contd.
  • Mission Operations
  • Nature of low earth orbit operation requires
    different philosophy than deep space mission
  • Spacecraft not in continuous communication with
    ground station
  • Snapshot pictures of spacecraft/instrument
    operation
  • Extreme emphasis on ability to quickly analyze
    operations situation and Safe the Spacecraft
    before an anomaly cascades into a total failure
  • All credible single point failure modes should be
    removed in redundant bus applications and
    recovery procedures put in place and practiced
  • Major deficiencies in flight controller training
    and in development of mission roles and
    procedures
  • Spacecraft training at very high level
  • Insufficient to ensure capability of real-time
    anomaly assessment
  • Total of two Spacecraft anomalies practiced
  • No preplanned emergency safing sequence when
    failure observed, no actions undertaken

16
Concluding Thoughts
  • To stay within tight fiscal constraints,
    fundamental decisions made early on that resulted
    in fatal design/implementation shortfalls
  • Continuing schedule and funding pressure reduce
    insight, testing, documentation
  • Over reliance on Standard Flight Proven Bus
    resulted in belief that past history justifies
    elimination of sound engineering practices
  • Lack of penetration into hardware developments
    precluded knowledge gaining communication
  • Alternate views/opinions stifled
    contractor/government team attempts to convey
    magnitude of concerns resulting from overly
    constrained resources ignored by management
  • Lack of vigor in chain of command review/approval
    of documentation, testing modifications,
    performance waivers and training set stage for
    failure

17
9/3/04
16
18
Credible Failure Modes Not Considered by Program
  • Connectors
  • Pin-to-pin short RJD output command pin to
    28VDC resulting in inadvertent thruster firing.
  • Wire Shorts
  • Low resistance shorts between RJD control wiring
    and any voltage sources capable of 12.5V or more
    and 1A or more (circuit analysis and WSTF data
    determined this threshold for fuel oxidizer
    valve actuation)
  • Valve coil command wire short to 28 volt
    conductor due to wire insulation flaws caused by
    aging
  • Valve coil command wire short to 28 volt
    conductor due to conductive liquid between wire
    and cracked insulation causing low resistance
    short
  • Valve coil command wire short to 28 volt
    conductor due to shield braid wire foreign object
    debris (36AWG strand) bridging between 28V and
    command line through ring-cracks in insulation. 
    Note  Braid foreign object debris would need to
    "float" over from nearby LRU that uses tag-ring
    back shell with shielded wire

Note These 14 of 38 failure modes identified
were not considered by Program
Write a Comment
User Comments (0)
About PowerShow.com