Overview of Legal Issues in Renewable Energy Projects

Description:

Turnkey versus separate contracts (FIDIC). Price check scope of work and stage payments schedule. Assignment security assignment and step-in rights for bank. – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 14
Provided by: omck7
Category:

less

Transcript and Presenter's Notes

Title: Overview of Legal Issues in Renewable Energy Projects


1
Overview of Legal Issues in Renewable Energy
Projects Renewable Energy Summit Ainsley
HeffernanPartner, Beauchamps Solicitors. Dundalk
, 21st January 2009
2
Wind Farm Contracts Matrix
3
Lease Option
  • Purpose legal right to call for a Lease within
    a specified period.
  • Term long enough to obtain planning and grid
    connection offer.
  • Description of Lands retain flexibility to
    alter location of turbines and access road.
  • Assignment proviso allowing assignment to group
    company.
  • Landowners obligations restrictions on use of
    retained lands and objecting to planning.
  • (vi) Wayleaves from landowner and/or any third
    party for grid connection route.

4
Lease Agreement
  • Rent minimum annual rent plus uplift calculated
    as a percentage of gross income.
  • Term - 20 to 25 years with option to renew
    (minimum gt PPA term).
  • Assignment proviso re group companies and
    security assignments.
  • Landlords obligations possible limited use of
    demised lands and certain restrictions on use of
    retained lands (buffer zone).
  • Break option if PPA terminated.

5
Turbine Supply Agreement
  1. Turnkey versus separate contracts (FIDIC).
  2. Price check scope of work and stage payments
    schedule.
  3. Assignment security assignment and step-in
    rights for bank.
  4. Financing letter of credit from developers
    bank.
  5. Completion timetable and penalties for delay
    (excluding Force Majeure).
  6. Defects Liability Period typically 2 to 5
    years.
  7. Tests on completion and taking over pre
    commissioning test / commissioning test / trial
    operation test / Taking-Over Cert.
  8. Insurance and guarantee evidence of insurance
    before commencement of works and requirement for
    a performance bond or parent guarantee.

6
Service and Warranty Agreement
  • Availability warranty minimum 95 availability
    and 5 downtime in any operational year
    (excluding force majeure and maintenance).
  • (ii) Performance warranty each turbine will
    produce X amount of power at Y wind speed based
    on power curve.
  • (iii) Compensation if these warranties are
    breached but subject to cap based on contract
    price.
  • (iv) Scheduled and unscheduled maintenance by
    turbine supplier for annual fee.

7
Operation and Maintenance Agreement
  • Developer as operator versus third party
    operator.
  • Performance standards based on results of
    commissioning and trial operation tests.
  • Right to replace operator for under-performance.
  • Bonus and penalty provisions.
  • (v) Step-in rights for bank.

8
Civil/Electrical Works Contracts
  • (i) Clear scope of work and duty to co-operate
    with other contractors on site.
  • (ii) Defects liability period for the works and
    warranties in relation to the quality of work and
    materials used.
  • (iii) Time for completion of works and the
    payment terms.
  • (iv) Responsibility for putting all necessary
    insurances in place.
  • (v) Collateral Warranties to be provided to the
    bank.

9
Power Purchase Agreement
  • Price fixed for term of PPA therefore providing
    cashflow guarantee to developer and REFIT hedging
    for supplier.
  • Term usually 15 years with option to extend.
  • Green rights split of any future green
    certificates?
  • Assignment beware of overly restrictive
    assignment clauses which effectively amount to a
    veto.
  • Pre-emption rights right of first refusal.
    Formula for calculation of sale price.
  • Termination - if developer commits a material
    breach or REFIT payments stopped.
  • Step-in rights for bank.

10
Grid Connection Agreement
  • Connection Agreement, ESB General Conditions and
    Quotation letter.
  • Cost based on assumptions in quotation letter,
    subject to change.
  • Capacity bond refunded provided customer
    reaches 90 of agreed MEC within one year.

11
CER Authorisation to Construct and Licence to
Generate
  • Non negotiable.
  • Apply to the CER with correct information.
  • Application forms and related guidance are
    available from the CER website.
  • Subject to compliance with Trading and Settlement
    Code.

12
Bank Documentation
  • Full due diligence and approval of all project
    documentation.
  • Facility Agreement.
  • Debenture over companys assets, undertakings,
    contracts and warranties.
  • Charge over the land Lease and all wayleaves /
    rights of way.
  • Charge over the shares in the development
    company.
  • A charge over the debt service reserve account.
  • Collateral Warranties from turbine supplier and
    all professionals involved in the design,
    construction and maintenance of the project.

13
Overview of legal issues in renewable energy
projects Renewable Energy Summit