Title: Seal and Bearing Failure on a Two-Stage Overhung Pump (3x6x13.5 CJA 2 Stage)
1Seal and Bearing Failure on a Two-Stage Overhung
Pump (3x6x13.5 CJA 2 Stage)
John Schmidt, PE CSS Field Engineering
Sulzer Pumps (US), Inc
2Outline
- What Happened ?
- In short User 'moved / simplified' piping on the
pump, which affected Axial Thrust. - Mini-tutorial on calculating Axial thrust for
this pump.
3Pump Cross Section
4The Problem What Happened ?
- Pump design assumed by the user to have both a
seal piping Plan 13 and a Plan 11.
5The Problem What Happened ?
- Pump was simplified to only use the Plan 11.
- The "Plan 13" was removed. Which actually was a
Balance Line.
6The Problem What Happened ?
7The Problem What Happened ?
- Plan 11, with
- Balance Line Removed
- No flow through the seal seal failure
8The Problem What Happened ?
- Since Seal Failure occurred
- Changed the seal piping from a Plan 11 to a Plan
13. - Plan 13
- Flush is restored through the Seal.
- But Balance Line not restored.
9- Consequence
- Seal is no longer failing.
- But bearings are, every 6-9 months.
- Axial Thrust !
10- Axial Thrust
- Mainly a function of Pressure distribution on
the rotor. - Also Momentum force.
11Axial Thrust Pressure Distribution on Impeller
Shrouds
- Rule of thumb 0.75Pd (differential pressure)
for the shroud pressure profile - (from the wear-ring-labyrinth to Impeller OD)
- Used in this Case Study.
- But in reality it is more complicated...
12 Axial Thrust Pressure Distribution on Shroud
- Dependent on fluid dynamics in Side-Rooms
- Off-BEP operation
- Leakage direction and amount.
- Side-room geometry.
- Rotor to Case Alignment.
- For Example
13Example Effect of off-BEP operation.
- If pump is back on the curve, Flow is less, Head
is higher The 0.75Pd can go to 0.8Pd (shutoff
0.9Pd) - If pump is out on the curve, Flow is more, Head
is less The 0.75Pd can go to 0.7Pd (end of
curve 0.6Pd)
14 Example Effect of leakage on Pressure
Distribution
Actual pressure profile is decreased because
greater swirl in side-room due to fluid entering
side-room with high pre-rotation.
Actual pressure profile is increased because
Less swirl in side-room due to fluid entering
hub seal with no pre-rotation.
pressure profile if rotation factor assumed to be
0.5
pressure profile if rotation factor assumed to be
0.5
15Axial Thrust Momentum Force
- Very low. Is typically not included.
- Thrust due to momentum change.
- Momentum Force
- (Capacity2 x density) / (Eye Area)x722
- Momentum force in lbf.
- Capacity in GPM,
- Density in SG
- Eye Area in Square Inches.
- 722 is unit conversion factor.
- Assumes 90 deg turn of fluid.
- For This Pump (at design flow) -gt
lbf
16Calculate Axial Thrust for this Pump
- What do we Need to start ?
- Cross section
- Diameters of wear ring labyrinths.
- Pressures
- Suction Pressure 111 psi
- Differential Pressure 340 psi
- Flush plan
- General idea of leakage direction, labyrinth
clearances, leakage flow, etc.
- We are assuming the simplified 0.75Pd on
Shrouds. - Initially show all pressures on rotor, and then
show the typical simplification.
17Axial Thrust - As designed. (all pressures on
rotor)
18Axial Thrust - As designed. (Simplified)
19Axial Thrust - As designed. (Fully simplified)
20Axial Thrust Plan 11 with No Balance Line
21Axial Thrust Plan 11 with No Balance Line
22Plan 13 with no Balance Line
- In Series Flow
- Hub Seal,
- Throat Bush,
- Plan 13 Orifice
- What is the pressure behind the 2nd Stage
Impeller?
23Plan 13 with no Balance Line
- Cross section area of each Restriction
24Plan 13 with no Balance Line
- The Orifice is greatest restriction (by far)
- Find flow rate through the orifice (assume water)
General / Simple Equation for Orifice
_careful with units_
25Plan 13 with no Balance Line
- Flow rate through this line is 5 GPM (or less if
we include other restrictions and resistances..) - Given 5 GPM flow what is the pressure drop across
the hub seal? - Re-Arrange Orifice Eqn, solve for pressure across
hub seal gap.
26- Pressure Drop across Hub 1.2 psi
- Therefore Pressure Behind 2nd Stg Impeller is
338.8 psi -
27Axial Thrust Plan 13 with No Balance Line
28Bearing L10h.
- The most simple method for Bearing Life
Calculation is "L10" - ISO or AFBMA equation for basic rating life
L10 (C/P)p - L10 basic rating life, millions of revolutions
- CBasic dynamic Load Rating (from Bearing Tables)
- PEquivalent Dynamic Bearing Load
- pExponent, 3 for ball, 3.333 for roller.
- Operating hours at constant speed before onset of
fatigue. - L10h (1 000 000/ (60n))L10 n RPM
29Bearing L10h.
30Bearing L10.
- Alternative, Use C/P basic load dynamic rating /
dynamic load and nomograph from the bearing
supplier.
31Problem Resolution
- User realized the issue after reading about pump
axial thrust and better understood what they had
affected. - Solution Pump User returned the pump to the
original configuration and reliability was
improved.
Lessons Learned
- Continuing Education / pump training should be
included in the maintenance/operation/reliability
sections of any plant in order to achieve
success. - Modifications can have un-intended consequences.
- You should contact the OEM as necessary.
32Questions ?