Title: Chapter 10 - Cash Flows and Other Topics in Capital Budgeting
1Chapter 10 - Cash Flows and Other Topics in
Capital Budgeting
2Useful Guidelines
- Use free cash flow rather than accounting profits
- Think incrementally
- Beware of cash flows diverted from existing
products - Synergistic effects
3Useful Guidelines
- Working capital requirements are considered a
cash flow even though they do not leave the
company. - They are tied up over the life of the project.
- When projects terminate, working capital will be
recovered.
4Useful Guidelines
- Consider incremental expenses
- Sunk costs are not incremental cash flow
- Ignore interest payments and financing flows
- Free cash flow change in operating cash flow
change in net working capital change in capital
spending
5Useful Guidelines
- Use simple straight line method to calculate
depreciation expense - Though depreciation is not a cash flow item, it
does affect cash flow by lowering profit, so we
will add it back
6Useful Guidelines
- Sale of old machine
- Old asset is sold for a price above depreciated
value - eg old machine purchased for 15,000, had a book
value of 10,000, and was sold for 17,000 (34
tax rate), how much tax the firm should pay? - (17,000 10,000) 34 2,380
7Useful Guidelines
- Sale of old machine
- 2. Old asset is sold at depreciated value.
- since there is no gain or loss, no tax
- 3. Old asset is sold less than its depreciated
value. - eg book value is 10,000 and sold for 7,000,
what is the tax? - we have a cash inflow due to loss
- (10,000 7,000) 34 1,020
8Capital Budgeting The process of planning for
purchases of long-term assets.
- For example Our firm must decide whether to
purchase a new plastic molding machine for
127,000. How do we decide? - Will the machine be profitable?
- Will our firm earn a high rate of return on the
investment? - The relevant project information follows
9- The cost of the new machine is 127,000.
- Installation will cost 20,000.
- 4,000 in net working capital will be needed at
the time of installation. - The project will increase revenues by 85,000 per
year, but operating costs will increase by 35 of
the revenue increase. - Simplified straight line depreciation is used.
- Class life is 5 years, and the firm is planning
to keep the project for 5 years. - Salvage value at the end of year 5 will be
50,000. - 14 cost of capital 34 marginal tax rate.
10Capital Budgeting Steps
- 1) Evaluate Cash Flows
- Look at all incremental cash flows occurring as
a result of the project. - Initial outlay
- Differential Cash Flows over the life of the
project (also referred to as annual cash flows). - Terminal Cash Flows
11Capital Budgeting Steps
Terminal Cash flow
Initial outlay
Annual Cash Flows
12Capital Budgeting Steps
- 2) Evaluate the Risk of the Project
- Well get to this in the next chapter.
- For now, well assume that the risk of the
project is the same as the risk of the overall
firm. - If we do this, we can use the firms cost of
capital as the discount rate for capital
investment projects.
13Capital Budgeting Steps
- 3) Accept or Reject the Project
14Step 1 Evaluate Cash Flows
- a) Initial Outlay What is the cash flow at
time 0? - (Purchase price of the asset)
- (shipping and installation costs)
- (Depreciable asset)
- (Investment in working capital)
- After-tax proceeds from sale of old asset
- Net Initial Outlay
15Step 1 Evaluate Cash Flows
- a) Initial Outlay What is the cash flow at
time 0? - (127,000) Purchase price of asset
- (20,000) Shipping and installation
- (147,000) Depreciable asset
- (4,000) Net working capital
- 0 Proceeds from sale of old
asset - (151,000) Net initial outlay
16Step 1 Evaluate Cash Flows
- b) Annual Cash Flows What incremental cash
flows occur over the life of the project?
17For Each Year, Calculate
- Incremental revenue
- - Incremental costs
- - Depreciation on project
- Incremental earnings before taxes
- - Tax on incremental EBT
- Incremental earnings after taxes
- Depreciation reversal
- Annual Cash Flow
18For Years 1 - 5
- 85,000 Revenue
- (29,750) Costs
- (29,400) Depreciation
- 25,850 EBT
- (8,789) Taxes
- 17,061 EAT
- 29,400 Depreciation reversal
- 46,461 Annual Cash Flow
19Step 1 Evaluate Cash Flows
- c) Terminal Cash Flow What is the cash flow at
the end of the projects life? - Salvage value
- /- Tax effects of capital gain/loss
- Recapture of net working capital
- Terminal Cash Flow
20Tax Effects of Sale of Asset
- Salvage value 50,000.
- Book value depreciable asset - total amount
depreciated. - Book value 147,000 - 147,000
- 0.
- Capital gain SV - BV
- 50,000 - 0 50,000.
- Tax payment 50,000 x .34 (17,000).
21Step 1 Evaluate Cash Flows
- c) Terminal Cash Flow What is the cash flow at
the end of the projects life? - 50,000 Salvage value
- (17,000) Tax on capital gain
- 4,000 Recapture of NWC
- 37,000 Terminal Cash Flow
22Project NPV
- CF(0) -151,000.
- CF(1 - 4) 46,461.
- CF(5) 46,461 37,000 83,461.
- Discount rate 14.
- NPV 27,721.
- We would accept the project.
23Capital Rationing
- Suppose that you have evaluated five capital
investment projects for your company. - Suppose that the VP of Finance has given you a
limited capital budget. - How do you decide which projects to select?
24Capital Rationing
- You could rank the projects by IRR
Our budget is limited so we accept only projects
1, 2, and 3.
5
4
2
3
1
X
25Capital Rationing
- Ranking projects by IRR is not always the best
way to deal with a limited capital budget. - Its better to pick the largest NPVs.
- Mutually exclusive projects perform same task,
so accepting one means rejection of the other
26Problems with Project Ranking
- 1) Mutually exclusive projects of unequal size
(the size disparity problem) - The NPV decision may not agree with IRR or PI.
- Solution select the project with the largest NPV.
27Size Disparity Example
- Project B
- year cash flow
- 0 (30,000)
- 1 15,000
- 2 15,000
- 3 15,000
- required return 12
- IRR 23.38
- NPV 6,027
- PI 1.20
- Project A
- year cash flow
- 0 (135,000)
- 1 60,000
- 2 60,000
- 3 60,000
- required return 12
- IRR 15.89
- NPV 9,110
- PI 1.07
28Problems with Project Ranking
- 2) The time disparity problem with mutually
exclusive projects. - NPV and PI assume cash flows are reinvested at
the required rate of return for the project. - IRR assumes cash flows are reinvested at the IRR.
- The NPV or PI decision may not agree with the
IRR. - Solution select the largest NPV.
29Time Disparity Example
- Project B
- year cash flow
- 0 (48,000)
- 1 36,500
- 2 24,000
- 3 2,400
- 4 2,400
- required return 12
- IRR 22.78
- NPV 6,955
- PI 1.14
- Project A
- year cash flow
- 0 (48,000)
- 1 1,200
- 2 2,400
- 3 39,000
- 4 42,000
- required return 12
- IRR 18.10
- NPV 9,436
- PI 1.20
30Mutually Exclusive Investments with Unequal Lives
- Suppose our firm is planning to expand and we
have to select one of two machines. - They differ in terms of economic life and
capacity. - How do we decide which machine to select?
31- The after-tax cash flows are
- Year Machine 1 Machine 2
- 0 (45,000) (45,000)
- 1 20,000 12,000
- 2 20,000 12,000
- 3 20,000 12,000
- 4 12,000
- 5 12,000
- 6 12,000
- Assume a required return of 14.
32Step 1 Calculate NPV
- NPV1 1,433
- NPV2 1,664
- So, does this mean 2 is better?
- No! The two NPVs cant be compared!
- One way is to create replacement chain
33Step 2 Equivalent Annual Annuity (EAA) method
- If we assume that each project will be replaced
an infinite number of times in the future, we can
convert each NPV to an annuity. - The projects EAAs can be compared to determine
which is the best project! - EAA Simply annuitize the NPV over the projects
life.
34EAA with your calculator
- Simply spread the NPV over the life of the
project - Machine 1 PV 1433, N 3, I 14,
- solve PMT -617.24.
-
- Machine 2 PV 1664, N 6, I 14,
- solve PMT -427.91.
35- EAA1 617
- EAA2 428
- This tells us that
- NPV1 annuity of 617 per year.
- NPV2 annuity of 428 per year.
- So, weve reduced a problem with different time
horizons to a couple of annuities. - Decision Rule Select the highest EAA. We would
choose machine 1.
36Step 3 Convert back to NPV
- Assuming infinite replacement, the EAAs are
actually perpetuities. Get the PV by dividing
the EAA by the required rate of return. - NPV 1 617/.14 4,407
- NPV 2 428/.14 3,057
- This doesnt change the answer, of course it
just converts EAA to an NPV that can be compared.
37Options in Capital Budgeting
- Option to delay a project
- Option to expand a project
- Option to abandon a project
38Practice ProblemsCash Flows Other Topics in
Capital Budgeting
39Problem 1a
- Project Information
- Cost of equipment 400,000.
- Shipping installation will be 20,000.
- 25,000 in net working capital required at setup.
- 3-year project life, 5-year class life.
- Simplified straight line depreciation.
- Revenues will increase by 220,000 per year.
- Defects costs will fall by 10,000 per year.
- Operating costs will rise by 30,000 per year.
- Salvage value after year 3 is 200,000.
- Cost of capital 12, marginal tax rate 34.
40Problem 1a
- Initial Outlay
- (400,000) Cost of asset
- ( 20,000) Shipping installation
- (420,000) Depreciable asset
- ( 25,000) Investment in NWC
- (445,000) Net Initial Outlay
41For Years 1 - 3
Problem 1a
- 220,000 Increased revenue
- 10,000 Decreased defects
- (30,000) Increased operating costs
- (84,000) Increased depreciation
- 116,000 EBT
- (39,440) Taxes (34)
- 76,560 EAT
- 84,000 Depreciation reversal
- 160,560 Annual Cash Flow
42Problem 1a
- Terminal Cash Flow
- Salvage value
- /- Tax effects of capital gain/loss
- Recapture of net working capital
- Terminal Cash Flow
43Problem 1a
- Terminal Cash Flow
- Salvage value 200,000.
- Book value depreciable asset - total amount
depreciated. - Book value 420,000 384,000 168,000.
- Capital gain SV - BV 32,000.
- Tax payment 32,000 x .34 (10,880).
44Problem 1a
- Terminal Cash Flow
- 200,000 Salvage value
- (10,880) Tax on capital gain
- 25,000 Recapture of NWC
- 214,120 Terminal Cash Flow
45Problem 1a Solution
- NPV and IRR
- CF(0) -445,000
- CF(1 ), (2), 160,560
- CF(3 ) 160,560 214,120 374,680
- Discount rate 12
- IRR 22.1
- NPV 93,044. Accept the project!
46Problem 1b
- Project Information
- For the same project, suppose we can only get
100,000 for the old equipment after year 3, due
to rapidly changing technology. - Calculate the IRR and NPV for the project.
- Is it still acceptable?
47Problem 1b
- Terminal Cash Flow
- Salvage value
- /- Tax effects of capital gain/loss
- Recapture of net working capital
- Terminal Cash Flow
48Problem 1b
- Terminal Cash Flow
- Salvage value 100,000.
- Book value depreciable asset - total amount
depreciated. - Book value 168,000.
- Capital loss SV - BV (68,000).
- Tax refund 68,000 x .34 23,120.
49Problem 1b
- Terminal Cash Flow
- 100,000 Salvage value
- 23,120 Tax on capital gain
- 25,000 Recapture of NWC
- 148,120 Terminal Cash Flow
50Problem 1b Solution
- NPV and IRR
- CF(0) -445,000.
- CF(1), (2) 160,560.
- CF(3) 160,560 148,120 308,680.
- Discount rate 12.
- IRR 17.3.
- NPV 46,067. Accept the project!
51Problem 2
- Automation Project
- Cost of equipment 550,000.
- Shipping installation will be 25,000.
- 15,000 in net working capital required at setup.
- 8-year project life, 5-year class life.
- Simplified straight line depreciation.
- Current operating expenses are 640,000 per yr.
- New operating expenses will be 400,000 per yr.
- Already paid consultant 25,000 for analysis.
- Salvage value after year 8 is 40,000.
- Cost of capital 14, marginal tax rate 34.
52Problem 2
- Initial Outlay
- (550,000) Cost of new machine
- (25,000) Shipping installation
- (575,000) Depreciable asset
- (15,000) NWC investment
- (590,000) Net Initial Outlay
53For Years 1 - 5
Problem 2
- 240,000 Cost decrease
- (115,000) Depreciation increase
- 125,000 EBIT
- (42,500) Taxes (34)
- 82,500 EAT
- 115,000 Depreciation reversal
- 197,500 Annual Cash Flow
54For Years 6 - 8
Problem 2
- 240,000 Cost decrease
- ( 0) Depreciation increase
- 240,000 EBIT
- (81,600) Taxes (34)
- 158,400 EAT
- 0 Depreciation reversal
- 158,400 Annual Cash Flow
55Problem 2
- Terminal Cash Flow
- 40,000 Salvage value
- (13,600) Tax on capital gain
- 15,000 Recapture of NWC
- 41,400 Terminal Cash Flow
56Problem 2 Solution
- NPV and IRR
- CF(0) -590,000.
- CF(1 - 5) 197,500.
- CF(6 - 7) 158,400.
- CF(10) 158,400 41,400 199,800.
- Discount rate 14.
- IRR 28.13 NPV 293,543.
- We would accept the project!
57Problem 3
- Replacement Project
- Old Asset (5 years old)
- Cost of equipment 1,125,000.
- 10-year project life, 10-year class life.
- Simplified straight line depreciation.
- Current salvage value is 400,000.
- Cost of capital 14, marginal tax rate 35.
58Problem 3
- Replacement Project
- New Asset
- Cost of equipment 1,750,000.
- Shipping installation will be 56,000.
- 68,000 investment in net working capital.
- 5-year project life, 5-year class life.
- Simplified straight line depreciation.
- Will increase sales by 285,000 per year.
- Operating expenses will fall by 100,000 per
year. - Already paid 15,000 for training program.
- Salvage value after year 5 is 500,000.
- Cost of capital 14, marginal tax rate 34.
59Problem 3 Sell the Old Asset
- Salvage value 400,000.
- Book value depreciable asset - total amount
depreciated. - Book value 1,125,000 - 562,500
- 562,500.
- Capital gain SV - BV
- 400,000 - 562,500 (162,500).
- Tax refund 162,500 x .35 56,875.
60Problem 3
- Initial Outlay
- (1,750,000) Cost of new machine
- ( 56,000) Shipping installation
- (1,806,000) Depreciable asset
- ( 68,000) NWC investment
- 456,875 After-tax proceeds (sold old
machine) - (1,417,125) Net Initial Outlay
61For Years 1 - 5
Problem 3
- 385,000 Increased sales cost savings
- (361,200) Extra depreciation
- 23,800 EBT
- (8,092) Taxes (34)
- 15,708 EAT
- 361,200 Depreciation reversal
- 376,908 Differential Cash Flow
62Problem 3
- Terminal Cash Flow
- 500,000 Salvage value
- (170,000) Tax on capital gain
- 68,000 Recapture of NWC
- 398,000 Terminal Cash Flow
63Problem 3 Solution
- NPV and IRR
- CF(0) -1,417,125.
- CF(1 - 4) 376,908.
- CF(5) 376,908 398,000 774,908.
- Discount rate 14.
- NPV 83,539.
- IRR 16.18.
- We would accept the project!