Title: LAT Integration and Test
1MRB NCR 562 Bay 0 and 4 TPS Removal and
Replacement
- LAT Integration and Test
- and Systems Engineering
2Recommendation
- Option 3 TPS Removal
- Allows repair of TPS
- Minimizes risk of damage to Flight Hardware
- ELX has recalibration method for TEM/TPS
telemetry - Accurate shim determination requires TPS or
TPS/TEM/CAL measurement - TPS height and flatness data will be used to
determine offset - TPS selection determined by best fit for shim,
then ELX criteria - TEM or TEM/CAL could be removed if TPS data fails
to meet criteria
3Options
- Options 1 through 5 are discussed in subsequent
charts - Option 1 Use As Is
- Option 2 TPS Removal and Rework
- Option 3 TPS Removal
- Option 4 TEM/TPS Removal
- Option 5 CAL/TEM/TPS Removal
4Option 1 Use-As-Is
- IT Mechanical Pros
- No demate of flight connections
- No change to accurately measured CAL/TEM/TPS
stack height - IT Mechanical Cons
- None
- IT Electrical Pros
- No additional testing required
- IT Electrical Cons
- None
- ELX Pros
- No immediate change to TEM/TPS calibration or
performance - ELX Cons
- Power supply circuit design is marginally stable
with temperature - 2 different TPS configurations within the LAT
- Potential Risks
- Power supply oscillation could negatively impact
detector performance - Power supply oscillation could worsen over
temperature and time - Rework later in the program could increase risk.
- Discussion
5Option 2 TPS Removal and Rework
- IT Mechanical Pros
- Demate TPS/TEM connection in Grid Low Risk
- Demate TPS/PDU connection in Grid Low Risk, but
connector jack screw may loosen - Maintains CAL/TEM/TPS stack height
- IT Mechanical Cons
- None
- IT Electrical Pros
- Maintains TEM/TPS telemetry calibration
- Maintains calibration of Tracker and Calorimeter
detectors - IT Electrical Cons
- Need regression test definition to validate
re-assembled TEM/TPS in the grid - ELX Pros
- Permits rework of TPS for power supply
oscillation - Maintains TEM/TPS telemetry accuracy
- Maintains TEM/TPS Performance
- ELX Cons
- Testing of removed TPS required
- Potential Risks
- Impact to IT schedule while TPS is reworked and
retested
6Option 3 TPS Removal
- IT Mechanical Pros
- Good access to the interface between TEM and TPS
- Shimming may not be required if TPS box height
meets criteria - Demate TPS/TEM connection in Grid Low Risk
- Demate TPS/PDU connection in Grid Low Risk, but
connector jack screw may loosen - IT Mechanical Cons
- Stack height measurement is invalidated and
becomes inferred - If shimming is required it is a more complex
operation to loosen and shim at the CAL interface - IT Electrical Pros
- None
- IT Electrical Cons
- Requires recalibration of TEM/TPS telemetry
- Need regression test definition to validate new
TEM/TPS Assembly in the grid - Requires recalibration of Tracker and Calorimeter
detectors - ELX Pros
- Permits rework of TPS for power supply
oscillation - ELX Cons
- Degradation in TEM/TPS telemetry accuracy
- TEM/TPS measured performance becomes inferred
7Option 3 TPS Removal (contd)
- Potential Risks
- Unknown where or how shimming will be performed,
if required - Shimming in the Grid has not been demonstrated.
- Discussion
- 18 TPS units have measured flatness variation
within 1 mil - 17 TPS units have measured height variation
within 4 mils - Height was not measured for TPS units currently
installed in Bays 0 GLAT1749 sn 22 and 4
GLAT1750 sn 03 - GLAT1749 and GLAT1750 height and flatness would
be measured after removal - GLAT1813 sn 11 and GLAT1828 sn 02 height and
flatness would be measured prior to installation - Height variance of measured TPS chassis is 0.004
- Flatness variance of TPS measured chassis is 0.001
8Option 3 TPS Removal (contd)
- Discussion (contd)
- Suggested re-calibration method for new assembled
units - CAL and TKR HV Bias Currents
- Maintain the slope constants for both CAL and TRK
Bias currents. - Re-calibrate the intercept constants by taking
current average of one thousand measurements
before and after TPS replacement, and then adjust
the new average measurement to old reading with
new value of Intercept point. - For Total TEM/TPS current
- Re-calibrate the slope and intercept constants by
taking the average of one thousand measurements
before and after replacement of TPS in
conditions - no TRK or CAL FE is powered
- CAL FE is powered and TRK FE is not - TRK
FE is powered and CAL FE is not - TRK and CAL
FE is poweredThese four points allow make it
easy to make fit and find new calibration
constants for new assembly.Telemetry points can
be verified by recording external PS current
reading for all 4 points before and after
replacement.
9Option 3 TPS Removal (contd)
- RR of TPS Basic Steps
- Measure relative height of TEM/TPS assembly to
CAL base plate in the GRID. - Remove TPS from TEM on CAL in GRID.
- Measure height of TPS removed from GRID on
granite table. - Measure new power supply on granite table.
- Determine new shim thickness.
- Install new shims.
- Install new TPS.
- Verify relative height obtained in step 1.
10Option 3 TPS Removal (contd)
- TPS Replacement IT Risk Summary
Risk Description Weight Factor (1-5) Risk (1-3) Score Mitigation Plan
Demate and mate of new TPS to TEM connector. 4 2 8 Dry run assembly procedure
If shimming is required it is a more complex operation to loosen and shim at the CAL interface 4 3 12 Demonstrate with EM units in 1x4.
Regression Testing to Validate 2 2 4 Utilize existing single tower tests
Total 24
If shimming is not required the overall risk
score is reduced by 12 pts.
11Option 4 TEM/TPS Removal
- IT Mechanical Pros
- Demate TPS/TEM connection outside Grid Low Risk
- Demate TPS/PDU connection in Grid Low Risk, but
connector jack screw may loosen - Exposes existing shimming interface between
TEM/CAL - Shimming operation is cleaner and consistent with
technique used in the metrology bay. Needs
pathfinding. - Installation of thermistor cable is simplified
with the box removed. - IT Mechanical Cons
- Re-shimming required
- Requires new in Grid shimming procedure
- Demate 8 TEM/TKR flex cables in Grid Elevated
Risk, EXTREMELY LOW Risk Tolerance - Demate 4 Calorimeter flex cables in Grid
Elevated Risk - IT Electrical Pros
- None
- IT Electrical Cons
- Need regression test definition to validate new
TEM/TPS Assembly in the grid - Requires recalibration of Tracker and Calorimeter
detectors
12Option 4 TEM/TPS Removal (contd)
- ELX Pros
- Permits rework of TPS for power supply
oscillation - No degradation in TEM/TPS telemetry accuracy
- TEM/TPS performance is based on measurements
- ELX Cons
- None
- Potential Risks
- Shimming in the Grid has not been demonstrated
- Requires demate of TEM/TKR flex cables that could
require extensive TKR rework if damaged. There
are no spares. - Requires demate of TEM/CAL cables.
13Option 4 TEM/TPS Removal (contd)
- RR of TEM/TPS - Basic Steps
- Measure relative height to CAL base plate of
TEM/TPS assembly in GRID. - De-mate CAL, TKR, TEM to GASU, and TPS to PDU
cables from TEM/PSU assembly. - Remove TEM/TPS from CAL in GRID.
- Measure height of TEM/TPS removed from GRID on
granite table. - Measure new TEM/TPS on granite table.
- Determine new shim thickness based on the height
differences between the removed and replacement
assemblies. - Install new TEM/TPS with shim stack up determined
in previous step. - Verify relative height obtained in step 1.
- Install thermistor cable.
- Mate CAL, TKR, TEM to GASU, and TPS to PDU
cables to the newly installed TEM/TPS assembly
14Option 4 TEM/TPS Removal (contd)
- TEM/TPS Replacement IT Risk Summary
Risk Description Weight Factor (1-5) Risk (1-3) Score Mitigation Plan
Requires breaking flight connections to CAL, TKR, GASU and PDU connections (13 Connectors). 5 3 15 Proceed cautiously. Do not use excessive force for mate or demate.
Re-shimming Required 4 2 8 Demonstrate with EM units in 1x4.
Regression Testing to Validate 2 1 2 Utilize existing single tower tests
Total 25
15Option 5 CAL/TEM/TPS Removal
- IT Mechanical Pros
- Demate TPS/TEM connection outside Grid Low Risk
- Demate TPS/PDU connection in Grid Low Risk, but
connector jack screw may loosen - Permits accurate CAL/TEM/TPS shimming in
metrology bay - IT Mechanical Cons
- Demate 8 TEM/TKR flex cables in Grid Elevated
Risk, EXTREMELY LOW Risk Tolerance - Demate 4 Calorimeter flex cables outside Grid
- Removal of installed shear plates for Bays 0 and
4 may not be desirable with existing nut failure
(NCR 579) - IT Electrical Pros
- TEM/TPS regression testing could be performed
outside of Grid - Permits TEM/CAL re-calibration in metrology bay
- IT Electrical Cons
- Requires re-calibration of TKR detector in Grid
- ELX Pros
- Permits rework of TPS for power supply
oscillation - No degradation in TEM/TPS telemetry accuracy
- TEM/TPS performance is based on measurements
- ELX Cons
- None
16Reference
- Completed Action Items From Previous MRB
- COMPLETE - QA identify which TPS chassis s/n are
installed and to be installed. - TPS TPS/TEM ASSY TPS CHASSIS Height
- GLAT1749 GLAT1752 LAT-DS-00995-51-22 Not
measured - GLAT1750 GLAT1753 LAT-DS-00995-51-03 N
ot measured - GLAT1813 GLAT1832 LAT-DS-00995-51-11 3
.0618 - GLAT1828 GLAT1845 LAT-DS-00995-51-02
3.0597 - COMPLETE - SE Assess impact of TPS swap based on
chassis dimensions with inputs from IT and M.
Nordby. - See Recommendation
- Only 19 of the 23 TPS chassis were measured.
- Flatness data variance of 19 boxes is .001
- Height data variance of 18 boxes is .004
- IT and M. Nordby will attend MRB.
- COMPLETE QA How were TPS chassis heights
measured? - The measured TPS units were measured on the CMM
(Coordinate Measurement Machine). The height
measurement of 3.060 0.005 was measured by the
CMM's gaussian best fit plane. The part was
constrained to the granite table per drawing
instructions for parallelism. The TPS units were
measured for a 0.010" parallelism free state
condition, there were a few close to the limit,
but not out of tolerance. The parallelism
measurement was performed with an indicator and
height gage. - COMPLETE (See presentation) - IT assess
feasibility of performing height measurements in
Grid for all options. - COMPLETE (See presentation) - IT assess
shimming in Grid shimming for all options. - COMPLETE - ELX identify candidate TPS for
installation in to Bays 0 and 4 - Suggestion is to use for TPS replacement on
tower A and B the following units1. GLAT1813
TPS from Assembly GLAT1832 should replace TPS
GLAT1749 from assembly GLAT1752 2. GLAT1828 TPS
from Assembly GLAT1845 should replace TPS
GLAT1750 from assembly GLAT1753.
17Reference
- COMPLETE - ELX identify candidate TPS for
installation in to Bays 0 and 4 - Suggestion is to use for TPS replacement on
tower A and B the following units - 1. GLAT1813 TPS from Assembly GLAT1832 should
replace TPS GLAT1749 from assembly GLAT1752 - 2. GLAT1828 TPS from Assembly GLAT1845 should
replace TPS GLAT1750 from assembly
GLAT1753.Selection of these units are based on
similarity of HV calibration constants
18Reference
- Bay 0 GLAT1813 -gt GLAT17491752 (TPS GLAT1749)
Calibration Date Slope Intercept
CAL Bias Current 2/2/05 0.930382662178 -0.0014032780581
TKR Bias Current 2/2/05 0.935558213381 0.00234355041672
TEM/TPS Current 2/2/05 66.973583 -1.518328
Calibration Date Slope Intercept
CAL Bias Current 5/9/05 0.917697111398 0.000884641517652
TKR Bias Current 5/9/05 0.937436903933 0.0211388061165
TEM/TPS Current 5/9/05 66.993715 -0.837730
19Reference
- Bay 4 GLAT1828 -gt GLAT1750
- 1753 (TPS GLAT1750)
Calibration Date Slope Intercept
CAL Bias Current 1/31/05 1.05784628111 0.00439458111717
TKR Bias Current 1/31/05 0.930910460477 -0.0122075240151
TEM/TPS Current 1/31/05 66.510847 0.064750
Calibration Date Slope Intercept
CAL Bias Current 5/9/05 1.00367085354 -0.00551484961688
TKR Bias Current 5/9/05 0.956402741661 0.00380408724678
TEM/TPS Current 5/9/05 66.388597 0.089839
20Reference
- NCR 562 - TPS CCAs on GLAT 1752 and GLAT 1753
TEM/TPS assys have not been reworked per NCR 397
to correct observed oscillation of CAL 3.3V
digital. Assemblies were integrated onto the
Grid before the problem was observed in TEM/TPS
test data - From Parent NCR 397
- Description of Non Conformance
- Oscillation of CAL-3.3V Digital when TEM/TPS
tester board is connected. Amplitude was found
around 100mV, 1-2 KHz frequency. - Oscillation is triggered at power-on of
calorimeter and sustained. No oscillation is
present when turning the power on at cold
temperatures (-40C). At room-temperature
oscillation might or might not be triggered by
power-on. At hot temperatures (50C) oscillation
was always triggered at power-on. Whether or not
the oscillation is triggered at power-up, is
dependant of the temperature at power-up. If the
temperature of the module is changed after power
up, the presence of oscillation (or not) is
maintained and is independent of whether the
temperature is changed. - Test showed that the supply only oscillates with
loads drawing around/more than 1.2A. It does not
oscillate at loads of around 600mA (the CAL has
lt1A). In addition it appears to only oscillate
when capacitive loads are added in parallel to
the resistive loads. - No oscillation was observed at the TPS-only test.
That tester includes tests at 150 of the cal
nominal load, but does not have capacitive loads
in parallel. It is not clear whether the problem
is present when CAL AFEE boards are connected. It
is known that on tower A and B the TPS system is
stable at room-temperature. - Dispositions
- (Cullinan, 4/5/05) Per MRB discussion 4/1/05 and
4/4/05, the following rework on the qual TPS
board is underway on AIDS 974 to resolve the
oscillation issue observed - 1. Conformal coating on board in areas adjacent
to CAL resistors R53, R58, TKR resistors R122,
R142, R61, TEM resistor R20, R50 has been removed
using wooden stick in preparation for attaching
capacitors to be connected in parallel with these
resistors, per direction from G. Haller. Caps
will use 30 gauge wire pigtails to connect to on
board resistors. Caps CDR33BX473AKUS will be
used in this application. Caps will be bonded to
board using Hysol EA9394.
21Reference
- NCR 562 (contd)
- 2. On board CAL resistors R28, R25, R51, R52
will be removed and replaced with 2.74KOhm
resistors M55342K06B2E74R per G. Haller
direction. - 3. On board Compensation Capacitors C531, C532
(CAL bias) and C631, C632, C633 (TKR bias) have
present value of 10pF. Remove and replace these
caps with 100pF caps (on TPS CCA parts list), P/N
CDR31BP101BKUS. - Dispo 2 (Cullinan, 4/7/05) Rework was completed
4/6/05 and the qual TPS board was tested on the
TPS tester and connected to the AFEE/MCMs and
tested up to 75 deg. C. Per G. Haller,
oscillation was not observed with simulated load
of greater than 150 of expected TKR load.
Oscillations were noted on high voltage when
simulated load was approx. 250 of expected TKR
load. MRB was held 4/7/05. In attendance were
Haller, Sapozhnikov, Hascall, Bright, Klaisner,
Cullinan, Bloom, J. Lohr, B. Graf, N. Johnson to
discuss test results. MRB concurred that testing
performed to date was sufficient to validate new
qual TPS board configuration and the elimination
of the oscillation within TPS performance
requirements. - Additional TPS board testing will be completed
4/7/05. All testing will be performed to AIDS
974, with data packages attached to this AIDS.
Qual TPS board will be reinstalled into TPS base.
Thermal compound CV-2946 will not be used (SLAC
does not have material on hand) between board and
TPS base. Analysis by DAQ showed temperature
rise of TPS board was approximately 3-4 deg C
without the thermal compound. Also, areas where
conformal coating was removed and newly added
pigtailed capacitors will not be covered with
Arathane conformal coating at this time. In
addition, all screws securing the TPS board into
the TPS base, securing the TPS lid, and securing
the TPS to the TEM will not be staked with Hysol
0151. These materials are not immediately
available at SLAC. Need for qual TEM/TPS for
testing at NRL is urgent and the qual TPS board
can be used for NRL testing in this
configuration. When Qual TEM/TPS is returned to
SLAC, the TPS will be reassembled to include
these materials to return the unit to meet the
assembly drawing. - MRB also discussed the plan to document these
configuration changes. Relevant TPS assembly
drawings, schematics and BOMs will need to be
revised. Report list of documents that will be
revised to this NCR once list is compiled.
22Reference
- NCR 562 (contd)
- MRB also concurred to rework remaining TPS boards
at SLAC prior to pre-conformal coat performance
testing and thermal cycle testing. The CCAs will
arrive from General Technology and will be
reworked per this NCR and AIDS 994. The
redlined schematic used to document configuration
changes for the qual TPS CCA will be used for
reworking the other TPS boards. The TPS CCA
schematic diagram, assembly drawing and BOM/parts
list will be revised to capture redline changes.
GSFC inspection of reworked CCAs will be
performed by Tracy Shepherd. Following rework,
TPS CCAs will complete performance and thermal
cycle testing and returned to General Technology
for final assembly. - Dispo 3 (Cullinan, 4/12/05) Rework (including
capacitor/jumper wire staking with EA9394),
inspection and Performance testing has been
completed on TPS CCAs GT104, 105, 106, 108, 109,
110. GT104, 105, 106 and 108 to be shipped to
GT GT109, 110 still require performance and
thermal cycle testing following rework.
Photographs of individually staked
capacitors/jumper wires and overall board views
were taken for all boards and are stored on V
drive under Ancillary file in Electronics folder
(under GLAST folder on V drive). - All remaining boards received from GT will be
reworked per this NCR and AIDS 994. - Dispo 4 (cullinan, 4/20/05) TPS boards GT109
and GT110 successfully completed EICIT
(LAT-TD-04850-1), SVT (LAT-TD-04849-1),
performance testing (LAT-TD-01652-4), thermal
cycling (5 cycles) and post thermal cycle
performance testing (LAT-TD-01652-4) on AIDS 872
following rework. - All test results have been retained in the work
order binders generated for each CCA and archived
in bonded stores. - The following drawings have been revised to
document this TPS CCA rework and are currently in
sign off cycle - 1. TPS CCA assembly LAT-DS-02388, update to rev.
58 - 2. TPS CCA Schematic, LAT-DS-02390, updated to
rev. 57 - 3. TPS CCA BOM, LAT-DS-02391, updated to rev. 57
- Per MRB 4/14/05, DAQ Electronics group to provide
an advisory memo to Systems Engineering
documenting this anomaly and directing test and
service operations of the TEM/TPS to avoid any
condition that would risk initiating oscillation.
23Reference
- NCR 562 (contd)
- MRB concluded that no additional EMI/EMC testing
or workmanship vibration testing is required for
the reworked qual TEM/TPS module. - Plan is to close this NCR with MRB approval, and
open new NCR to document required rework for TPS
CCAs currently installed in TPS boxes of GLAT
1752 and GLAT 1753 flight modules currently
integrated onto Towers 1 and 2. Plan is to
remove these TPS boxes and rework/replace with
reworked TPS CCAs. - (Cullinan, 7-14-05) NCR 562 created per MRB to
direct disposition of GLAT 1752 and GLAT 1753
TEM/TPS for reworking the TPS CCAs of these two
assemblies.