Title: Practice of Large Penetration Test after 1999 Ji-Ji Earthquake
1Practice of Large Penetration Test after 1999
Ji-Ji Earthquake
- Jiin-Song Tsai and Yean-Jhe Liou
- Department of Civil Engineering National Cheng
Kung University - 11. 4. 2003
2 Aspects
- Field Conditions
- Facilities Instrumentation
- Experiment Results
- Summaries Lessons
3Liquefaction of Gravelly Ground
- BPT (Harder and Seed, 1986)
- Effects of hammers and casings
- BPT-SPT correlation
- FBPT (Sy and Lum, 1997)
- Effects of casing friction (Mud-injection Becker)
- LPT (Daniel, Howie and Sy, 2003)
- Scale effect of LPTs (scale-up SPT)
- TLPT (Tsai, Huang and Liou, 2003)
- Measurement of Energy Transfer
4TLPT Project
Dr. D.H. Lee NSC Coordinator
Dr. A.B. Huang Joint Project Coordinator
TLPT Research Team
Dr. A.B. Huang (Planning and Coordination)
Dr. P.S. Lin (Soil Investigation and Job Site
Preparation)
Dr. J.S. Tsai and Diagnostic Eng. Consultant LTD.
(Energy Measurement)
5Test Site Ground Condition
6Location
7Liquefaction of Test Site
8Layout
Da Li River
9Test Pit
10Profile ( B-14 )
11Facilities Instrumentation
12Casings of TLPT
Comparisons with BPT and FBPT
BPT FBPT
TLPT (Close end)
Mud-Injection (Close end)
Conventional (Open end)
405mm
13Steel Shoes
P1, P2
P3, P4 , P5
14BPT and TLPT Hammers
15Three-Segment Casings
P1, P2
P3, P4 , P5
16Instrumentation - Setup
Strain transducerAccelerometer
TNOsignal conditioner
Notebookcomputer
Set-A
Loadcell
InstruNet M100signal conditioner
Notebookcomputer
Set-B
17Instrumentation Set-A
18Loadcell Set-B Development
19Loadcells
P3, P4 , P5
P1, P2
20Q 1 How to place the sensors properly inside the
tube under limit working space ?
- A 1 Prefabricate the sensors module on a plastic
sheet for one-time easy pasting
21Q 2 How to effectively cover sensors under limit
working space to resist high water pressure ?
- A 2 Fill up the tube with silica gel
22Q 3 How to isolate the sensors and wire cords
from high temperature induced by welding ?
- A 3 Wrap them carefully using asbestos belts
23Loadcell Calibration
500t MTS
24Shop Prefabrication
25Experiment Procedure
26Installation Steps
- Double-check Set-B, and label 30cm markson the
tube. - Erect the lower segment and slightly pound to
the ground.
27Pounding Steps
- Bolt Set-A sensors onto casing. Connect Set-A and
Set-B to signal conditioners. - Record blow counts of 30cm penetration.
- Stop pounding before Set-A sensors were dragged
into the ground. Dismount Set-A.
28Steps for next cycle
- Stretch Set-B cords to new outlet hole.
- Welding.
- Repeat the pounding
- steps until the uppersegment done.
29Correlate BPT-Nb and SPT-N60
- Sy and Lum method (1997)
- No shaft friction Rs
30Results
31Discussions
32Unsolved puzzle 1Why size effects on ENTHRU
results are not clearly shown ?
33Unsolved puzzle 2Why NL30 numbers of same
size casing are scattering?
34Failure
- No meaningful data of Set B !!
- Why?
35 SimWave simulation Study
- Force-time history of Set-B
36- Interpretation
- High particle velocity fail the bounding
between casing tube and strain gauges. - Measures
- Adopt longer strain gauges (lower accuracy)
to provide larger glue area.
37Summaries
- The first trial of local LPT (TLPT) is described
and data are presented. - Results of TLPT give an explanation to
liquefaction of gravelly ground in the Ji-Ji
Earthquake. - Lessons learned give clues for future
improvements.
38Appreciate all involvedTo be Continued ..