Title: FIDIC MDB HARMONISED CONSTRUCTION CONTRACT CONFERENCE Session 10: Client Perspective Borrowers, private clients, finance issues
1FIDIC MDB HARMONISED CONSTRUCTION CONTRACT
CONFERENCESession 10 Client PerspectiveBorrowe
rs, private clients, finance issues
- Jacques Bouillon
- Partner, White Case LLP
- 26 June 2012
2Introduction to Project FinancingsContractual
Scheme of a Project Finance
3Role of the Construction Contract in a BOT-
Concession Scheme within a Project Finance
Structure
- In a typical scheme a special purpose vehicle
(the SPV) has the rights and obligations under
a concession or a BOT agreement (the
Concession-BOT Contract) with a public body
(the Grantor) to design-finance-build and
operate an infrastructure (1) - The SPV finances the construction of the
facilities through loans from banks (4) or the
capital markets as well as through equity
investments from its shareholders (5) - Due to the non-recourse nature of these loans,
Lenders looks principally to the cash-flow
generated by the operation of the project (6) -
and not from the shareholders - as the source of
funds from which their loans will be repaid - To satisfy the SPVs obligation to the Grantor to
design and build the infrastructure, the SPV will
enter into a construction contract (the EPC
Contract) (2) with a contractor (the
Contractor) under such a contract, the
Contractor will be required to design-build test
and commission the project on a turnkey basis for
a fixed lump sum price and within a fixed time
for completion, guaranteeing a specific quality
or level of performance for the completed works - The terms of the EPC Contract will be as far as
possible back-to-back with the Concession-Bot
Contract and thus any construction risk placed
on the SPV by the Concession-BOT Contract will,
through the construction, flow down to the
Contractor - The price paid to the Contractor is usually the
largest capital expenditure incurred by the SPV
.and the EPC Contract is usually, the most
likely source of significant cost overruns.
4Lenders, Shareholders and Grantors expectations
Consequences on the construction Contract
- Shareholders seek to raise money for the
implementation of a project - Shareholders expecting a return on equity will
want to protect their expected returns by placing
construction risk on the Contractor - Shareholders also know the more risk they can
transfer to the Contractor, the less direct or
indirect support they are likely to be asked to
provide to the project by Lenders to cover such
risk (8) - Any Lender will want to satisfy itself as to the
expertise and experience of the Contractor and
check the terms and risk allocation under the EPC
Contract before committing itself into financing - The EPC Contract will result in the piece of
infrastructure that will be relied upon by the
Grantor during the term of the concession period
and will be handed over to the Grantor at the end
of the period - All these factors will put pressure on the
Contractor to accept an increasing amount of
responsibility and construction risk. - Lenders may be less concerned about having the
SPV pay a higher construction contract price in
order to induce the Contractor to accept as much
construction risks as possible the Shareholders
(in particular those not affiliated with the
Contractor) will generally view a higher price as
reducing their equity return and will be much
more sensitive to contract pricing
5Focus on the EPC Contract within a Project
Financing Framework
- To evaluate the bankability of a project, the
Lenders need to be able to assess with a certain
accuracy the residual risk borne by the SPV (the
borrower) in fine, i.e. the risk not borne by
either the Grantor through the Concession-BOT
Contract or by the co-contracting party through
the EPC Contract or the OM Contractor under the
OM Contract (3). Thus, to tend to such certainty
in a project financing, the construction contract
is - Usually a turnkey contract
- a design and build contract
- fully equipped facility delivered, ready for
operation at the turn of a key (the EPC
contract) - lump sum price
- strict construction timetable (damages
provisions) longstop date - must be bankable contractor with a good credit
risk or supported by a creditworthy guarantor. - A turnkey contract with specific technical
aspects - strict definition of the transparency principle
with the Concession-BOT Contract (back-to-back) - accurate treatment of the guarantees
- insurances
- payments
- Lenders rights (step-in rights).
6Which FIDIC Standard Forms to Tailor?
- As a consequence, the Silver Book, which was
originally intended for use in privately funded
projects such as a turnkey subcontract in
private-public partnerships (PPP), seems to be a
more suitable basis to tailor a standard form of
DB contract within a project financing
framework, notably for the following reasons - EPC/Turnkey contract
- Lump sum price
- Allocation of risks more risks borne by the
Contractor which avoids uncertainty of risks
borne by the SPV - The Pink Book (MDB Harmonised Edition), even if
including specific clauses adapted to
Multilateral Development Banks, seems less
suitable, notably as it is not drafted for
turnkey projects and the SPV is in charge of the
design (whereas, in the Silver Book as well as in
a project financing scheme, the Contractor is).
7The Back-to-Back Principle Definition
- Definition of the back-to-back principle
- Complete transparency between (i) the duties and
obligations of the SPV under the Concession-BOT
Contract and (ii) the duties and obligations of
the Contractor under the EPC Contract regarding
the design and construction aspects (same
mechanism as the one contemplated in the FIDIC
book Conditions of Subcontract for Construction).
- The back-to-back principle serves the bankability
of a project as it ensures that, except for those
which cannot be passed through because of law
restrictions, all the project risks pass
through the SPV directly to the most suitable
co-contracting party to bear it (in the case of
construction risks, to the Contractor). - Strict definition of the transparency principle
- Only if and when
- Claim mechanism due proportion with payment
devolved primarily to the Lenders (the Due
Proportion) - Documentation hierarchy (i) Concession-BOT
Contract and (ii) Contractor Direct Agreement
both prevail on the EPC Contract in case of
contradiction.
8The Back-to-Back Principle Consequences
- The back-to-back principle reflects on all the
DB Contract, notably - Payment of any sum due by the Grantor to the SPV
for the construction phase under the
Concession-BOT Contract like subsidies (if any)
or indemnities - Back-to-back guarantees bank guarantees (e.g.
performance guarantee) may be ordered directly by
the Contractor to the benefit of the Grantor to
avoid a two-level guarantee unnecessarily
expensive - Back-to-back penalties capped and specific
(e.g. delays, construction phase) allowing a
more accurate assessment of the maximum risk
incurred by the SPV (to reflect it on the
Contractor) - Force majeure, unforeseen events, change of law
(same grounds to claim additional time and
additional money to complete the works than those
provided for under the Concession-BOT Contract) - Administrative procedures
- Termination grounds grounds of general interest,
force majeure, unforeseen event, breach by a
party, breach by one party leading to the
termination of the Concession-BOT Contract - Termination indemnities the SPV will indemnify
the Contractor only up to the amount it received
from the Grantor, within the limits of the Due
Proportion and only once the SPV has actually
receive the payments from the Grantor.
9Additional Protections within the EPC Contract
- To minimize their exposure, in addition to the
protections offered by the back-to-back
principle, the Lenders usually also require - Additional guarantees
- Construction timetable shorter deadlines for the
Contractor to perform its obligations so as to
enable the SPV to comply with its own deadlines
under the Concession-BOT Contract - Additional penalties, notably those incurred in
relation to the Loans - Example of provision Within the limit of the
penalty cap, the Concessionaire may apply to the
Contractor any sum intended to repair damages
suffered by the Concessionaire as a result of a
failure to perform or poor performance of the DB
Contract by the Contractor, and, for example, an
increase in management costs for the
Concessionaire and/or late payment interest
and/or financial costs and/or costs connected
with adjusting or liquidating interest rate swap
agreements and/or loss of operation and/or
indemnities owed to the Operator and/or
indemnities owed to third parties. - Specific caps for more accurate assessment of the
risk borne by the SPV. - Liability cap, notably adjusted so as to cover
the remaining amount of the outstanding debt of
the SPV, not already covered by the indemnity
paid by the Grantor in case of termination for
breach of the Concession-BOT Contract. - Performance deadlines depending on completion (?
taking-over).
10Lenders Involvement
- Taking into consideration of the Lenders in the
project documentation and appointment of a
technical advisor by the Lenders (LTA) to ensure
there is no management of the project by the
Lenders but only a technical involvement. - Illustrations
- LTA
- Validation of (i) technical aspects such as key
milestones, (ii) payment to the Contractor - Participation in (i) the meetings, (ii) the
taking-over process - Access to the site and information (copy of
technical documentation, modification, studies) - Lenders
- No offset by the Contractor of any sum due to
the SPV with sums due by the SPV to the
Contractor until Lenders are entirely paid - In case of termination of the Concession-BOT
Contract, neither imputable to the Contractor or
to the SPV (i.e. force majeure), the Lenders have
to be repaid before the SPV indemnifies the
Contractor (Subordination principle) - Agreement by the Lenders to the EPC Contracts
assignment
11Construction Direct Agreement (7)
- The Construction Direct Agreement, as its name
implies, organizes the relationship of the
Contractor directly with the Lenders and the SPV.
- It notably contemplates major principles in favor
of the bankability of a project - Subordination principle the Contractor, in its
capacity as creditor towards the SPV, is
subordinated to the Lenders to be paid. - Remediation principle the Contractor may not
suspend or terminate the EPC Contract without
having notified the Lenders and granted them a
time extension to decide whether to remedy to the
SPVs breach or not. - Substitution principle in case of contractual
breach by the SPV under the Concession-BOT
Contract, the Lenders may substitute a new entity
to the SPV to avoid the termination of the
project. In this respect, the Contractor
undertakes to comply with its initial contractual
obligations towards the new entity as if it was
the initial SPV. - Representations and warranties towards the
Lenders and the SPV, notably in order to avoid
that its subcontractors compete with the Lenders
as creditors.
12Interface Agreement (9)
- The Interface Agreement organizes the
relationship between the SPV, the Contractor and
the OM Contractor as, during the construction
phase, the OM Contractor intervenes - to comment, or validate, design plans and
documents of the Works - to assist the SPV during the taking-over process.
- It notably tend to determine which actor assumes
which tasks, responsibility, indemnity and
penalty - Possible fronting the Contractor, during the
construction phase, assumes in back-to-back the
penalties potentially applied or the indemnities
claimed by the Grantor under the Concession-BOT
Contract. Thus, the SPV do not have to research
which of the Contractor or the OM Contractor has
actually caused the breach. And as (i) during the
construction phase, the Contractor is more likely
to be causing the contractual breach of the SPV
under the Concession-BOT Contract and (ii) the
liability cap of the Contractor is more suitable
to cover the sums potentially due (higher cap). - Afterwards, the Contractor may challenge the OM
Contractor. Sums paid under the fronting do not
impact the global liability of the Contractor.