FIDIC MDB HARMONISED CONSTRUCTION CONTRACT CONFERENCE Session 10: Client Perspective Borrowers, private clients, finance issues - PowerPoint PPT Presentation

About This Presentation
Title:

FIDIC MDB HARMONISED CONSTRUCTION CONTRACT CONFERENCE Session 10: Client Perspective Borrowers, private clients, finance issues

Description:

FIDIC MDB HARMONISED CONSTRUCTION CONTRACT CONFERENCE Session 10: Client Perspective Borrowers, private clients, finance issues Jacques Bouillon – PowerPoint PPT presentation

Number of Views:103
Avg rating:3.0/5.0
Slides: 13
Provided by: W4895
Learn more at: https://fidic.org
Category:

less

Transcript and Presenter's Notes

Title: FIDIC MDB HARMONISED CONSTRUCTION CONTRACT CONFERENCE Session 10: Client Perspective Borrowers, private clients, finance issues


1
FIDIC MDB HARMONISED CONSTRUCTION CONTRACT
CONFERENCESession 10 Client PerspectiveBorrowe
rs, private clients, finance issues
  • Jacques Bouillon
  • Partner, White Case LLP
  • 26 June 2012

2
Introduction to Project FinancingsContractual
Scheme of a Project Finance
3
Role of the Construction Contract in a BOT-
Concession Scheme within a Project Finance
Structure
  • In a typical scheme a special purpose vehicle
    (the SPV) has the rights and obligations under
    a concession or a BOT agreement (the
    Concession-BOT Contract) with a public body
    (the Grantor) to design-finance-build and
    operate an infrastructure (1)
  • The SPV finances the construction of the
    facilities through loans from banks (4) or the
    capital markets as well as through equity
    investments from its shareholders (5)
  • Due to the non-recourse nature of these loans,
    Lenders looks principally to the cash-flow
    generated by the operation of the project (6) -
    and not from the shareholders - as the source of
    funds from which their loans will be repaid
  • To satisfy the SPVs obligation to the Grantor to
    design and build the infrastructure, the SPV will
    enter into a construction contract (the EPC
    Contract) (2) with a contractor (the
    Contractor) under such a contract, the
    Contractor will be required to design-build test
    and commission the project on a turnkey basis for
    a fixed lump sum price and within a fixed time
    for completion, guaranteeing a specific quality
    or level of performance for the completed works
  • The terms of the EPC Contract will be as far as
    possible back-to-back with the Concession-Bot
    Contract and thus any construction risk placed
    on the SPV by the Concession-BOT Contract will,
    through the construction, flow down to the
    Contractor
  • The price paid to the Contractor is usually the
    largest capital expenditure incurred by the SPV
    .and the EPC Contract is usually, the most
    likely source of significant cost overruns.

4
Lenders, Shareholders and Grantors expectations
Consequences on the construction Contract
  • Shareholders seek to raise money for the
    implementation of a project
  • Shareholders expecting a return on equity will
    want to protect their expected returns by placing
    construction risk on the Contractor
  • Shareholders also know the more risk they can
    transfer to the Contractor, the less direct or
    indirect support they are likely to be asked to
    provide to the project by Lenders to cover such
    risk (8)
  • Any Lender will want to satisfy itself as to the
    expertise and experience of the Contractor and
    check the terms and risk allocation under the EPC
    Contract before committing itself into financing
  • The EPC Contract will result in the piece of
    infrastructure that will be relied upon by the
    Grantor during the term of the concession period
    and will be handed over to the Grantor at the end
    of the period
  • All these factors will put pressure on the
    Contractor to accept an increasing amount of
    responsibility and construction risk.
  • Lenders may be less concerned about having the
    SPV pay a higher construction contract price in
    order to induce the Contractor to accept as much
    construction risks as possible the Shareholders
    (in particular those not affiliated with the
    Contractor) will generally view a higher price as
    reducing their equity return and will be much
    more sensitive to contract pricing

5
Focus on the EPC Contract within a Project
Financing Framework
  • To evaluate the bankability of a project, the
    Lenders need to be able to assess with a certain
    accuracy the residual risk borne by the SPV (the
    borrower) in fine, i.e. the risk not borne by
    either the Grantor through the Concession-BOT
    Contract or by the co-contracting party through
    the EPC Contract or the OM Contractor under the
    OM Contract (3). Thus, to tend to such certainty
    in a project financing, the construction contract
    is
  • Usually a turnkey contract
  • a design and build contract
  • fully equipped facility delivered, ready for
    operation at the turn of a key (the EPC
    contract)
  • lump sum price
  • strict construction timetable (damages
    provisions) longstop date
  • must be bankable contractor with a good credit
    risk or supported by a creditworthy guarantor.
  • A turnkey contract with specific technical
    aspects
  • strict definition of the transparency principle
    with the Concession-BOT Contract (back-to-back)
  • accurate treatment of the guarantees
  • insurances
  • payments
  • Lenders rights (step-in rights).



6
Which FIDIC Standard Forms to Tailor?
  • As a consequence, the Silver Book, which was
    originally intended for use in privately funded
    projects such as a turnkey subcontract in
    private-public partnerships (PPP), seems to be a
    more suitable basis to tailor a standard form of
    DB contract within a project financing
    framework, notably for the following reasons
  • EPC/Turnkey contract
  • Lump sum price
  • Allocation of risks more risks borne by the
    Contractor which avoids uncertainty of risks
    borne by the SPV
  • The Pink Book (MDB Harmonised Edition), even if
    including specific clauses adapted to
    Multilateral Development Banks, seems less
    suitable, notably as it is not drafted for
    turnkey projects and the SPV is in charge of the
    design (whereas, in the Silver Book as well as in
    a project financing scheme, the Contractor is).

7
The Back-to-Back Principle Definition
  • Definition of the back-to-back principle
  • Complete transparency between (i) the duties and
    obligations of the SPV under the Concession-BOT
    Contract and (ii) the duties and obligations of
    the Contractor under the EPC Contract regarding
    the design and construction aspects (same
    mechanism as the one contemplated in the FIDIC
    book Conditions of Subcontract for Construction).
  • The back-to-back principle serves the bankability
    of a project as it ensures that, except for those
    which cannot be passed through because of law
    restrictions, all the project risks pass
    through the SPV directly to the most suitable
    co-contracting party to bear it (in the case of
    construction risks, to the Contractor).
  • Strict definition of the transparency principle
  • Only  if and when 
  • Claim mechanism due proportion with payment
    devolved primarily to the Lenders (the Due
    Proportion)
  • Documentation hierarchy (i) Concession-BOT
    Contract and (ii) Contractor Direct Agreement
    both prevail on the EPC Contract in case of
    contradiction.

8
The Back-to-Back Principle Consequences
  • The back-to-back principle reflects on all the
    DB Contract, notably
  • Payment of any sum due by the Grantor to the SPV
    for the construction phase under the
    Concession-BOT Contract like subsidies (if any)
    or indemnities
  • Back-to-back guarantees bank guarantees (e.g.
    performance guarantee) may be ordered directly by
    the Contractor to the benefit of the Grantor to
    avoid a two-level guarantee unnecessarily
    expensive
  • Back-to-back penalties capped and specific
    (e.g. delays, construction phase) allowing a
    more accurate assessment of the maximum risk
    incurred by the SPV (to reflect it on the
    Contractor)
  • Force majeure, unforeseen events, change of law
    (same grounds to claim additional time and
    additional money to complete the works than those
    provided for under the Concession-BOT Contract)
  • Administrative procedures
  • Termination grounds grounds of general interest,
    force majeure, unforeseen event, breach by a
    party, breach by one party leading to the
    termination of the Concession-BOT Contract
  • Termination indemnities the SPV will indemnify
    the Contractor only up to the amount it received
    from the Grantor, within the limits of the Due
    Proportion and only once the SPV has actually
    receive the payments from the Grantor.

9
Additional Protections within the EPC Contract
  • To minimize their exposure, in addition to the
    protections offered by the back-to-back
    principle, the Lenders usually also require
  • Additional guarantees
  • Construction timetable shorter deadlines for the
    Contractor to perform its obligations so as to
    enable the SPV to comply with its own deadlines
    under the Concession-BOT Contract
  • Additional penalties, notably those incurred in
    relation to the Loans
  • Example of provision Within the limit of the
    penalty cap, the Concessionaire may apply to the
    Contractor any sum intended to repair damages
    suffered by the Concessionaire as a result of a
    failure to perform or poor performance of the DB
    Contract by the Contractor, and, for example, an
    increase in management costs for the
    Concessionaire and/or late payment interest
    and/or financial costs and/or costs connected
    with adjusting or liquidating interest rate swap
    agreements and/or loss of operation and/or
    indemnities owed to the Operator and/or
    indemnities owed to third parties.
  • Specific caps for more accurate assessment of the
    risk borne by the SPV.
  • Liability cap, notably adjusted so as to cover
    the remaining amount of the outstanding debt of
    the SPV, not already covered by the indemnity
    paid by the Grantor in case of termination for
    breach of the Concession-BOT Contract.
  • Performance deadlines depending on completion (?
    taking-over).

10
Lenders Involvement
  • Taking into consideration of the Lenders in the
    project documentation and appointment of a
    technical advisor by the Lenders (LTA) to ensure
    there is no management of the project by the
    Lenders but only a technical involvement.
  • Illustrations
  • LTA
  • Validation of (i) technical aspects such as key
    milestones, (ii) payment to the Contractor
  • Participation in (i) the meetings, (ii) the
    taking-over process
  • Access to the site and information (copy of
    technical documentation, modification, studies)
  • Lenders
  • No offset by the Contractor of any sum due to
    the SPV with sums due by the SPV to the
    Contractor until Lenders are entirely paid
  • In case of termination of the Concession-BOT
    Contract, neither imputable to the Contractor or
    to the SPV (i.e. force majeure), the Lenders have
    to be repaid before the SPV indemnifies the
    Contractor (Subordination principle)
  • Agreement by the Lenders to the EPC Contracts
    assignment

11
Construction Direct Agreement (7)
  • The Construction Direct Agreement, as its name
    implies, organizes the relationship of the
    Contractor directly with the Lenders and the SPV.
  • It notably contemplates major principles in favor
    of the bankability of a project
  • Subordination principle the Contractor, in its
    capacity as creditor towards the SPV, is
    subordinated to the Lenders to be paid.
  • Remediation principle the Contractor may not
    suspend or terminate the EPC Contract without
    having notified the Lenders and granted them a
    time extension to decide whether to remedy to the
    SPVs breach or not.
  • Substitution principle in case of contractual
    breach by the SPV under the Concession-BOT
    Contract, the Lenders may substitute a new entity
    to the SPV to avoid the termination of the
    project. In this respect, the Contractor
    undertakes to comply with its initial contractual
    obligations towards the new entity as if it was
    the initial SPV.
  • Representations and warranties towards the
    Lenders and the SPV, notably in order to avoid
    that its subcontractors compete with the Lenders
    as creditors.

12
Interface Agreement (9)
  • The Interface Agreement organizes the
    relationship between the SPV, the Contractor and
    the OM Contractor as, during the construction
    phase, the OM Contractor intervenes
  • to comment, or validate, design plans and
    documents of the Works
  • to assist the SPV during the taking-over process.
  • It notably tend to determine which actor assumes
    which tasks, responsibility, indemnity and
    penalty
  • Possible fronting the Contractor, during the
    construction phase, assumes in back-to-back the
    penalties potentially applied or the indemnities
    claimed by the Grantor under the Concession-BOT
    Contract. Thus, the SPV do not have to research
    which of the Contractor or the OM Contractor has
    actually caused the breach. And as (i) during the
    construction phase, the Contractor is more likely
    to be causing the contractual breach of the SPV
    under the Concession-BOT Contract and (ii) the
    liability cap of the Contractor is more suitable
    to cover the sums potentially due (higher cap).
  • Afterwards, the Contractor may challenge the OM
    Contractor. Sums paid under the fronting do not
    impact the global liability of the Contractor.
Write a Comment
User Comments (0)
About PowerShow.com