Title:
1Research in dam breaching"
Sílvia Amaral PhD Student (1st year) December,
14th 2009
2Framework of the study
Although overtopping is the most common cause of
failure in recent dams, there is still an evident
need of reliable prediction tools to assess the
flood impacts in river floodplains following dam
failure Dam failure by overtopping have been
object of several laboratory studies (Vaskinn et
al. 2004) that have provided useful data like
discharge hydrographs for model validation
3Our believes
We believe that the improvement of the current
ability for reliable prediction of breach
formation by overtopping and its evolution in
earth embankments can only be achieved by
synthesizing hydrodynamic and geotechnical
phenomena into detailed conceptual models
4Laboratorial WorkMain Objectives
- Improving current ability to perform a more
reliable prediction of breach formation by
overtopping and its evolution in earth dams - advancing the state-of-the-art in the
characterization of the hydrodynamic and
geotechnical phenomena involved in the evolution
of a breach in earth dams
Provide empirical data that can be used to access
the most important parameters that influence
breach formation and flow hydrograph shape
5Methodology
- The laboratorial work will encompassing breach
simulations in homogeneous and zoned earth dams
- The empirical data will be provided by the
large-scale (0.70 m and 1.4 m tall) dam breach
tests whose laboratorial conditions will be
closely controlled - the morphological time evolution of the breach
- strain and pressure fields in the body of the
embankment - flow discharge (direct measurement)
6Laboratorial Facility (1/4)Main characteristics
- 1 storing tank with approximately 90 m3 of
maximum stored volume - 1 pumping circuit with a flow controller with 200
l/s with a maximum capacity (2 pumps - 100 l/s
each) - 1 pool representative of a reservoir Vmáx 50
m3 - Prepared to perform earth dam breach tests with
6,65 m wide embankments, variable heights
(0.80lthlt1,30m) and variable upstream and
downstream bank slopes (between 1V1.4H-1V3.0H) - a 14,5 m length flume downstream the dam toe
- with a constant width of 6,65 m in the first 11,5
m and a - convergent width in the last 3 m (between 6,65
and 1,70m). - a settling basin, located at the end of the flume
with 1,7 m width, 4,5 m length and a maximum
water/sediments height of 0,60 m
7Laboratorial Facility (2/4)Pictures
6.65 m
8Laboratorial Facility (3/4)Pictures
Perspective View
9Laboratorial Facility (4/4)Advantages and
limitations
- Pore pressure measured directly
- geotechnical instabilization should depend on
reduction of suction head this may be directly
assessed.
- Embankments compaction energy defined by
geotechnical engineers - experimental studies have not attended to some
geotechnical aspects as compaction energy of the
embankment layers (one, to this date)
- 20 cm granular bed under the embankments
compacting against a rigid surface modifies the
layer compaction characteristics in a way that
the first 2 compactions layers (near the rigid
surface) wouldnt behave like a real dam
- Direct measurement of the flow discharge laser
visualization fro breach evolution, flow
elevation measurements and synchronized velocity
measurements
- Variable input discharge Allows for virtually
increasing the size of the reservoir
10Laboratorial Facility (4/4)Advantages and
limitations
- Embankments dimensions (0,70-1,40m height)
Taller dams would be desirable
- Synchronization of all equipment
- such work can only be performed within a
multidisciplinary research group
- Variable input discharge limited to the pump
capacity and to small kinetic head
11Instrumentation and methods
- Direct measurement of the breach evolution
- underwater camera collecting a footage of the
trace generated by a 0.2 w laser
laser
camera
12Instrumentation and methods
- Synch flow elevation and velocity measurements
- velocity UVPs
- elevation level acoustic probes
laser
acoustic probes
UVPs
camera
13Pilot Facility (1/2)
- Before performing the experimental campaign of
tests on the main facility it is envisaged that a
2,9 m high homogeneous embankment, already
existent at LNEC, should be induced to fail by
overtopping
- Our goals are
- To win experience with the collecting and
acquisition data equipment - To perform a preliminary dam breach test to help
refining the main facility similarity conditions
and choosing the main parameters of dimensional
analysis and defining the experimental procedure.
- It will allow to win sensitivity to some
parameters and - To use the knowledge acquired in the improvement
of the main facility characteristics and
measuring methods
14Pilot Facility (2/2)
15Data Interpretation
- Scale issues, how to deal with breaking of
hydraulic and geotechnical similitude when the
scale of the grain is not the scale of the
embankment?
16Data Interpretation
- Reduction of the specific weight of the bank
material is the solution. -
- What about the CLAY CORE?
-
17Geotechnical Phenomena
- Scale issues on geotechnical similitude.
18Geotechnical Phenomena
- Reducing the specific gravity will help Tests
on centrifuge?
19Main uncertainties
- Instrumentation - placement of pore pressure
probes - - synchronization of instrumentation
- Bank material pumice? plastic?
(advantages/disadvantages)
- Boundary conditions infinite reservoir? test
several reservoir sizes?