BE.18.2, Shock Wave Inc began work on $ 7,000,000 contract in 2005 to construct an office building. During 2005, Shock Wave Inc, incurred costs of $ 1,715,000, billed their customers for $ 1,200,000 and collected $ 960,000. At December 31, 2005, the - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

BE.18.2, Shock Wave Inc began work on $ 7,000,000 contract in 2005 to construct an office building. During 2005, Shock Wave Inc, incurred costs of $ 1,715,000, billed their customers for $ 1,200,000 and collected $ 960,000. At December 31, 2005, the

Description:

Exercise 1, 2 BE.18.2, Shock Wave Inc began work on $ 7,000,000 contract in 2005 to construct an office building. During 2005, Shock Wave Inc, incurred costs of $ ... – PowerPoint PPT presentation

Number of Views:310
Avg rating:3.0/5.0
Slides: 8
Provided by: JepR5
Category:

less

Transcript and Presenter's Notes

Title: BE.18.2, Shock Wave Inc began work on $ 7,000,000 contract in 2005 to construct an office building. During 2005, Shock Wave Inc, incurred costs of $ 1,715,000, billed their customers for $ 1,200,000 and collected $ 960,000. At December 31, 2005, the


1
Exercise 1, 2
  • BE.18.2, Shock Wave Inc began work on 7,000,000
    contract in 2005 to construct an office building.
    During 2005, Shock Wave Inc, incurred costs of
    1,715,000, billed their customers for 1,200,000
    and collected 960,000. At December 31, 2005,
    the estimated future costs to complete the
    project total 3,185,000. Prepare Shock Waves
    2005 journal entries using the percentage of
    completion method.
  • BE.18.4, Use the information above, but assume
    Shock Wave uses the completed contract method.
    Prepare the companys 2005 journal entries.

2
Answer of Exercise 1
  • Construction in Process 1,715,000
  • Materials, Cash, Payables, etc. 1,715,000
  • Accounts Receivable 1,200,000
  • Billings on Construction in Process 1,200,000
  • Cash 960,000
  • Accounts Receivable 960,000
  • Construction in Process
    735,000
  • Construction Expenses 1,715,000
  • Revenue from Long-term Contract 2,450,000
  • ( 1,715,000 4,900,000) x 2,100,000
    735,000

3
Answer of Exercise 2
  • Construction in Process 1,715,000
  • Materials, Cash, Payables, etc. 1,715,000
  • Accounts Receivable 1,200,000
  • Billings on Construction in Process 1,200,000
  • Cash 960,000
  • Accounts Receivable 960,000

4
Exercise 3
  • BE.18.10, Yogi Bear Co sold equipment to Magilla
    Co for 20,000. The equipment is on Yogis books
    at a net amount of 14,000. Yogi collected
    10,000 in 2004, 5,000 in 2005 and 5,000 in
    2006. If Yogi uses the cost recovery method, what
    amount of gross profit will be recognized in each
    year ?.

5
Answer of Exercise 3
  • 2004 0
  • 2005 1,000 ( 15,000 14,000)
  • 2006 5,000

6
Exercise 4
  • E.18.6, On April 1, 2004, Brad Bridgewater Inc
    entered into a cost plus fixed free contract to
    construct an electric generator for Tom Dolan Co.
    At the contract date, Bridgewater estimated that
    it would take 2 years to complete the project at
    a cost of 2,000,000. The fixed free stipulated
    in the contract is 450,000. Bridgewater
    appropriately accounts for this contract under
    the percentage of completion method. During 2004,
    Bridgewater incurred costs of 700,000 related
    to the project. The estimated cost at December
    31, 2004, to complete the contract is
    1,300,000. Dolan was billed 600,000 under the
    contract.
  • Instructions
  • Prepare a schedule to compute the amount of gross
    profit to be recognized by Bridgewater under the
    contract for the year ended December 31, 2004.
    Show the supporting computations in good form.

7
Answer of Exercise 4
  • Computation of Gross Profit to Be
  • Recognized on Uncompleted Contract
  • Year Ended December 31, 2004
  • Total contract price
  • Estimated contract cost at completion
    2,000,000
  • ( 700,000 1,300,000)
  • Fixed fee
    450,000
  • Total
    2,450,000
  •  
  • Total estimated cost
    2,000,000
  • Gross profit
    450,000
  • Percentage of completion ( 700,000
    2,000,000) 35
  • Gross profit to be recognized ( 450,000 x 35
    ) 157,500
  •  
Write a Comment
User Comments (0)
About PowerShow.com