Department of Industrial and Engineering Technology College of Science and Technology Morehead State University IET 317 Group 5 Project - PowerPoint PPT Presentation

About This Presentation
Title:

Department of Industrial and Engineering Technology College of Science and Technology Morehead State University IET 317 Group 5 Project

Description:

Department of Industrial and Engineering Technology College of Science and Technology Morehead State University IET 317 Group 5 Project Author: Forrest – PowerPoint PPT presentation

Number of Views:219
Avg rating:3.0/5.0
Slides: 13
Provided by: Forr56
Category:

less

Transcript and Presenter's Notes

Title: Department of Industrial and Engineering Technology College of Science and Technology Morehead State University IET 317 Group 5 Project


1
Department of Industrial and Engineering
Technology College of Science and Technology
Morehead State University IET 317Group 5
Project
Steel Wheel Assembly Work Cell
  • Group Members
  • James Forrest, Lowell Outland, Evan Scott,
  • Donald Snyder, Matt Wells

2
Central Motor Wheel of America(CMWA)
  • CMWA was established in 1987.
  • Location Paris, Kentucky
  • Employs approximately 500 people.

3
CMWA Products
  • OEM supplier of Steel and Aluminum Wheels.
  • Steel Wheel Customers
  • Toyota, Honda, and Hyundai
  • Aluminum Wheel Customers
  • Toyota and Lexus.

4
Rationale for selecting the Steel Wheel Assembly
Station
  • The rationale for our chosen process is simple
  • A work cell is a collection of equipment required
    to make a single complex part
  • The part being produced is the steel wheel
  • The Steel Wheel Assembly Station itself has many
    parts. (Including the operators, robotic
    loaders, punch press, date stamp device, welders,
    grinders and inspection)
  • Multiple factors can lead to the occurrence of
    waste

5
Rationale cont.
  • If diligent lean techniques arent practiced in
    this work environment, the efficiency of the work
    cell could easily deteriorate, wasting valuable
    company time and money
  • In our efforts to make improvements we analyzed
    the processes of the Steel Wheel Assembly Station
  • Identified areas that can be improved
  • Made suggestions on how to improve them to make
    it a more lean and efficient process

6
Description of Steel Wheel Assembly Station
  •   The cell is used to assemble two main
    components of a steel wheel. The two components
    are the center disk (wheel center) and the Rim
    (outer part of the wheel). These parts are placed
    near an operator at the beginning of the assembly
    line. At the beginning of the wheel assembly
    machine there is one operator. This individual is
    responsible for loading the center disk onto the
    conveyor belt and loading the rim into a small
    punch press. This punch press is responsible for
    punching out the valve stem hole.
  • The punch press side of the line will be
    discussed first. The operator grabs a rim (6sec.)
    and places it onto the punch press (3sec.), he
    then activates the press which locks the rim into
    place and almost simultaneously punches the hole
    for the valve stem (2 sec.). Once this operation
    is finished a mechanical arm pulls the rim onto a
    conveyor belt directly in front of the punch
    press (Note as the mechanical arm is pulling the
    rim on to the conveyor the operator is loading a
    center disk onto the other line). The rim
    continues down the conveyor to the stamp station
    which automatically positions and clamps the rim
    (2sec.). This station stamps a date (2sec.) onto
    the rim so that when the two parts are welded
    together the company has a record for quality
    assurance purposes. On the wheel center side of
    the line, the operator has to just load the part
    so that it travels down and stops near the two
    weld fixtures. Please note that the operator is
    responsible for keeping both conveyor lines full.
  • At this point two additional operators are
    simultaneously grabbing a rim or a center disk
    and loading it into a weld jig. They then
    retrieve the opposing part and place it into the
    jig (20 sec per operator). The operators then
    activate the hydraulic clamps (2sec. per
    operator) to hold the parts together during
    welding. The welding process automatically starts
    as soon as the parts are clamped together. The
    welding robot is equipped with four MIG (Metal
    Inert Gas) guns that feed the wire continuously
    to create a seamless weld. The pallet that the
    parts are clamped to only has to rotate
    approximately 92 degrees to create the finished
    weld. The welding process takes about (30sec per
    assembly.). Once the parts have been full welded
    the newly formed wheels are removed by mechanical
    arms and placed (8sec.) onto another conveyor
    belt. The wheels then travel to an automated
    grinder that grinds/polishes the welded seam
    (15sec per wheel).
  • The wheels then travel on to an inspection
    station where they are checked for visual and
    mechanical defects by a fourth individual. This
    takes approximately 15-25sec per wheel. There are
    time variances due to anomalies in the weld or
    grind finish that occurs from time to time and
    also indicated run out noticed on the inspection
    gage.
  • The total amount of allowed run out is 0.3mm.
    This is the end of the journey for the newly
    minted wheel. The wheels next stop will be the
    powder coat/paint booth which is another work
    cell. Please note that the work cell is full of
    parts at all times so conveyor length is not a
    factor. As it was explained to our group the
    work cell is not timed linearly due to the fact
    that mechanical breakdowns are anticipated
    especially where the welders and grinders are
    concerned. Also, the nozzles must be cleaned and
    guides replaced after X-amount of wheels are
    welded.

7
Work Cell Layout Steel Wheel Assembly Machine
Wheel Rim Rack
Punch Press (Valve Stem Hole)
Finish Grinder/ Polisher
Date Produced Stamped on Rim
Manual Load/1 person
Wheel Welder 1
Manual Load/1 Person
Inspection Gage
Wheel Welder 2
Manual Load/1 Person
Wheel Centers Rack
Manual offload/ 1 person
Note Four Person Work Cell
8
Time Study Analysis
Step Time (in seconds)
Acquiring materials 6
Loading Punch Press 3
Small Punch Press (valve stem hole punch) 2
Stamp Station Load 2
Date Stamp (for quality assurance) 2
Loading Weld Jig 20
Activate Hydraulic Clamp 2 (per operator)
Welding Process Approx. 30 (per operator)
Remove wheels 8
Grind weld seam 15
Visual inspection 15-25


Total cycle time 110-120 per assembly



Time anomalies due to defects found on assembly during inspection. Time anomalies due to defects found on assembly during inspection.



Times inaccurate due to required maintenance i.e. cleaning nozzle and replacing guards



9
Suggested Improvements
  • Improve /Eliminate Finish Grinder
  • Electric motors breaks down frequently
  • Change to more reliable air motors
  • Rotate conveyor belt 180 degrees
  • Will help make the process more
    linear(Refer to layout)
  • Move wok cell closer to punch press
  • Use conveyor between punch press and work
    cell
  • Help speed up production
  • Add robot to place parts onto conveyor at
    beginning of work cell
  • Eliminates need for manpower at this
    position
  • Helps speed up production
  • Consider adding a third welder(identified choke
    point)
  • Move worker from first station to
    third welder
  • Helps to alleviate choke point
  • Move closer to paint booth
  • Reduces travel time to paint
  • Condense entire wheel making operation
  • Help speed up production
  • cost prohibitive

10
  • Group Recommendations
  • Recommend changing electric motors to pneumatic
    motors for more reliability
  • Recommend moving work cell closer to paint booth
    to reduce part travel time after assembly
  • Recommend adding a third welding machine to
    eliminate bottleneck in production
  • Recommend rotating welding machines 180 degrees
    to create a more linier product flow as shown by
    recommended layout

11
Recommended /Revised Work Cell Layout Wheel
Assembly Machine
Wheel Rim Rack
Punch Press (Valve Stem Hole)
Finish Grinder/ Polisher
Date Produced Stamped on Rim
Manual Load 1st Person
Wheel Welder 1
Manual Load/1 person
Inspection Gage
Manual Load 2nd Person
Wheel Welder 2
Wheel Centers Rack
Manual offload/ 1 person
Note Four Person Work Cell
12
Conclusion
  • Using Time and Motion Studies are very useful
  • The assembly cell can be improved
  • The entire wheel production operation should be
    reexamined
  • Room for cycle time improvements
Write a Comment
User Comments (0)
About PowerShow.com