Title: New Jersey Dept. of Transportation Office of Maritime Resources
1New Jersey Dept. of TransportationOffice of
Maritime Resources
Environmental Management of Maritime
Infrastructure An Introduction to Beneficial
Use of Dredged Material
2(No Transcript)
3Beneficial Use of Dredged Materials
- History and rationale for the policy of
beneficial use in NY/NJ Harbor, USA - Processing dredged material
- Applications in construction/remediation
- Issues and Lessons Learned
4Silty Dredged Material
- Sand, silt or clay particles
- Not soil (but may be amended and used as soil
more on that later today) - Storm events
- Landside runoff
- May contain contaminants
5Historical Dredged Material Management in NY/NJ
Harbor
6Aquatic Disposal
7Confined Upland Disposal
8Beach Replenishment
91993 Mudlock begins
10What was Mudlock all about?
- Sediment and soil particles adsorb and
concentrate pollutants - Contaminants in sediments can be accumulated in
organisms that are eaten by humans - Increased public awareness and concern about
industrial contaminants, particularly in the
ocean - No alternatives ready and available
- Cost of disposal rose from 5 to 130 per cubic
yard overnight. - Threatened the Ports plans to deepen harbor
channels
11(No Transcript)
12Regional Dredged Materials Management Plan (DMMP)
- Reduce Need to Dredge
- Reduce Contamination
- Beneficially use as much as possible
- Dispose of only what cannot be used
13Confined Aquatic Disposal (CAD)
14DMMP Point ThreeBeneficially use as much as
possible
- Construction Aggregate/Beach Replenishment
- Remediation Material (HARS)
- Fill and Capping Material
- Value added products (decon)
- Capacity and Throughput
- Economics (5/cyd - 47/cyd)
- Health and Safety
15Landfill Capping
16Brownfield Reclamation
17Abandoned Mine Reclamation
18Characteristics of Good Sites
- Historically Contaminated
- Industrial or Commercial Use
- Not near residences, schools, churches, or parks
- Desire for Remediation among PRPs and Owner
- Fill and/or capping needed
- Easy Barge, Rail or Truck Access
19Sediment Stabilization
20Raw Dredged Material
21Debris
22Dewatering (Decanting)
- 24 Hour Settling time
- Discharge to same water body or through
permitted discharge
23In-barge Mixing
- 18,000 CY/day
- Poor control of mix
- Must be offloaded within 24 hours
24Pugmill Mixing
25Processed Dredged Material
26Transportation and Placement
27Dredging Logistics
- 5-20,000 cyd per day
- 24/7 operation
- Weather delays
- Equipment delays
- Debris
28Bayonne Landfill2,000,000 cyd
29Elizabeth Landfill800,000 cyd
30Bark Camp Mine Demonstration400,000 cyd
31Program Successes
- OENJ Elizabeth 800,000 cyd
- Koppers/Seaboard 1,000,000 cyd
- OENJ Bayonne 2,000,000 cyd
- Port Liberte 200,000 cyd
- Linden Landfill 500,000 cyd
- Bark Camp Mine 400,000 cyd
- Penn and Fountain 200,000 cyd
- 1E Landfill 800,000 cyd
- FDP Enterprises 250,000 cyd
- Encap 1,000,000 cyd
- Total to date 7,150,000 cyd
32Encap Golf Holdings
- 500 hectares acres of former landfills
- Adjacent to NJ Turnpike
- 1.5 billion liters of leachate per year
- 300 million cleanup
- 150 hectares of wetlands
33Encap Golf Holdings
- 3.5 mcm ADM
- Eliminate leachate
- Restore and preserve 150 hectares of wetlands
- 4 - 18 hole golf courses
- 1.5 million square feet of office, retail, and
recreational space - 2000 housing units
- 20 million annual tax revenue
- 7,000 jobs
34(No Transcript)
35Regulation of Clean Sediment
36Non-Residential CC
Avg. NY/NJ DM
37(No Transcript)
38Regulation of challenged material
39Upland Beneficial Use as a Risk Reduction Strategy
- Reduction 1 Removal of contaminated sediment
from sensitive aquatic environment - Reduction 2 Eliminate contaminant transfer to
ocean - Reduction 3 Capping of highly contaminated
terrestrial soils - Reduction 4 Providing economic incentive to
construct engineering controls on contaminated
sites.
40Dredged Material as Construction Aggregate
- Common or engineered fill
- Grading and cover layers
- Recycling Operations
- Habitat Creation
41Highway Construction
- 80,000 cyd dredged material
- 2 monitored berms
- Settlement, strength and workability
- No significant environmental impacts or human
health exposure concerns - 8/cyd cost escalation over conventional
materials - Best if placed immediately requires remixing if
stored - Heavily impacted by freeze/thaw
42Old Confined Disposal Facilities
Resource for construction materials AND Resource
for future dredged material management
43Beneficial Use of CDF Material
44Free Fill!!
45Riverwinds Golf Course160,000 cyd
46Palmyra Cove Beneficial Use Technology Campus
47Jersey Flats Habitat Enhancement
48Economics
Line Item Costs
Line Item Revenue
- Dredging
- Land
- Design/Permitting
- Equipment
- Stabilization
- Transportation
- Placement
- Monitoring
- Host Fee
- Tipping Fee - sediment
- Tipping Fee - waste materials for stabilization
- Savings on fill/cap
- Sale of Land
49Implementation Challenges
Government
Proponent
- Streamline Contracting
- Improve Planning
- Improve Dredging Technology
- Regional Cooperation
- Partnering with Dredgers
- Flexibility on Fill
- No tipping fees
- Cooperation with Agencies
50Bayshore Recycling, Keasbey, NJ
- Characteristics of a Regional Dredged Material
Processing Facility - Barge access
- Multiple treatment options, including
decontamination - On-site analytical capability
- At least 50,000 cyd storage
- Ready access to aggregate and soil markets via
road, rail and barge - Alternative work lines for year-round operation
51Environmental Manufacturing