New Jersey Dept. of Transportation Office of Maritime Resources - PowerPoint PPT Presentation

1 / 51
About This Presentation
Title:

New Jersey Dept. of Transportation Office of Maritime Resources

Description:

New Jersey Dept' of Transportation Office of Maritime Resources – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 52
Provided by: non8143
Category:

less

Transcript and Presenter's Notes

Title: New Jersey Dept. of Transportation Office of Maritime Resources


1
New Jersey Dept. of TransportationOffice of
Maritime Resources
Environmental Management of Maritime
Infrastructure An Introduction to Beneficial
Use of Dredged Material
2
(No Transcript)
3
Beneficial Use of Dredged Materials
  • History and rationale for the policy of
    beneficial use in NY/NJ Harbor, USA
  • Processing dredged material
  • Applications in construction/remediation
  • Issues and Lessons Learned

4
Silty Dredged Material
  • Sand, silt or clay particles
  • Not soil (but may be amended and used as soil
    more on that later today)
  • Storm events
  • Landside runoff
  • May contain contaminants

5
Historical Dredged Material Management in NY/NJ
Harbor
6
Aquatic Disposal
7
Confined Upland Disposal
8
Beach Replenishment
9
1993 Mudlock begins
10
What was Mudlock all about?
  • Sediment and soil particles adsorb and
    concentrate pollutants
  • Contaminants in sediments can be accumulated in
    organisms that are eaten by humans
  • Increased public awareness and concern about
    industrial contaminants, particularly in the
    ocean
  • No alternatives ready and available
  • Cost of disposal rose from 5 to 130 per cubic
    yard overnight.
  • Threatened the Ports plans to deepen harbor
    channels

11
(No Transcript)
12
Regional Dredged Materials Management Plan (DMMP)
  • Reduce Need to Dredge
  • Reduce Contamination
  • Beneficially use as much as possible
  • Dispose of only what cannot be used

13
Confined Aquatic Disposal (CAD)
14
DMMP Point ThreeBeneficially use as much as
possible
  • Construction Aggregate/Beach Replenishment
  • Remediation Material (HARS)
  • Fill and Capping Material
  • Value added products (decon)
  • Capacity and Throughput
  • Economics (5/cyd - 47/cyd)
  • Health and Safety

15
Landfill Capping
16
Brownfield Reclamation
17
Abandoned Mine Reclamation
18
Characteristics of Good Sites
  • Historically Contaminated
  • Industrial or Commercial Use
  • Not near residences, schools, churches, or parks
  • Desire for Remediation among PRPs and Owner
  • Fill and/or capping needed
  • Easy Barge, Rail or Truck Access

19
Sediment Stabilization
20
Raw Dredged Material
21
Debris
22
Dewatering (Decanting)
  • 24 Hour Settling time
  • Discharge to same water body or through
    permitted discharge

23
In-barge Mixing
  • 18,000 CY/day
  • Poor control of mix
  • Must be offloaded within 24 hours

24
Pugmill Mixing
25
Processed Dredged Material
26
Transportation and Placement
27
Dredging Logistics
  • 5-20,000 cyd per day
  • 24/7 operation
  • Weather delays
  • Equipment delays
  • Debris

28
Bayonne Landfill2,000,000 cyd
29
Elizabeth Landfill800,000 cyd
30
Bark Camp Mine Demonstration400,000 cyd
31
Program Successes
  • OENJ Elizabeth 800,000 cyd
  • Koppers/Seaboard 1,000,000 cyd
  • OENJ Bayonne 2,000,000 cyd
  • Port Liberte 200,000 cyd
  • Linden Landfill 500,000 cyd
  • Bark Camp Mine 400,000 cyd
  • Penn and Fountain 200,000 cyd
  • 1E Landfill 800,000 cyd
  • FDP Enterprises 250,000 cyd
  • Encap 1,000,000 cyd
  • Total to date 7,150,000 cyd

32
Encap Golf Holdings
  • 500 hectares acres of former landfills
  • Adjacent to NJ Turnpike
  • 1.5 billion liters of leachate per year
  • 300 million cleanup
  • 150 hectares of wetlands

33
Encap Golf Holdings
  • 3.5 mcm ADM
  • Eliminate leachate
  • Restore and preserve 150 hectares of wetlands
  • 4 - 18 hole golf courses
  • 1.5 million square feet of office, retail, and
    recreational space
  • 2000 housing units
  • 20 million annual tax revenue
  • 7,000 jobs

34
(No Transcript)
35
Regulation of Clean Sediment
36
Non-Residential CC
Avg. NY/NJ DM
37
(No Transcript)
38
Regulation of challenged material
39
Upland Beneficial Use as a Risk Reduction Strategy
  • Reduction 1 Removal of contaminated sediment
    from sensitive aquatic environment
  • Reduction 2 Eliminate contaminant transfer to
    ocean
  • Reduction 3 Capping of highly contaminated
    terrestrial soils
  • Reduction 4 Providing economic incentive to
    construct engineering controls on contaminated
    sites.

40
Dredged Material as Construction Aggregate
  • Common or engineered fill
  • Grading and cover layers
  • Recycling Operations
  • Habitat Creation

41
Highway Construction
  • 80,000 cyd dredged material
  • 2 monitored berms
  • Settlement, strength and workability
  • No significant environmental impacts or human
    health exposure concerns
  • 8/cyd cost escalation over conventional
    materials
  • Best if placed immediately requires remixing if
    stored
  • Heavily impacted by freeze/thaw

42
Old Confined Disposal Facilities
Resource for construction materials AND Resource
for future dredged material management
43
Beneficial Use of CDF Material
44
Free Fill!!
45
Riverwinds Golf Course160,000 cyd
46
Palmyra Cove Beneficial Use Technology Campus
47
Jersey Flats Habitat Enhancement
48
Economics
Line Item Costs
Line Item Revenue
  • Dredging
  • Land
  • Design/Permitting
  • Equipment
  • Stabilization
  • Transportation
  • Placement
  • Monitoring
  • Host Fee
  • Tipping Fee - sediment
  • Tipping Fee - waste materials for stabilization
  • Savings on fill/cap
  • Sale of Land

49
Implementation Challenges
Government
Proponent
  • Streamline Contracting
  • Improve Planning
  • Improve Dredging Technology
  • Regional Cooperation
  • Partnering with Dredgers
  • Flexibility on Fill
  • No tipping fees
  • Cooperation with Agencies

50
Bayshore Recycling, Keasbey, NJ
  • Characteristics of a Regional Dredged Material
    Processing Facility
  • Barge access
  • Multiple treatment options, including
    decontamination
  • On-site analytical capability
  • At least 50,000 cyd storage
  • Ready access to aggregate and soil markets via
    road, rail and barge
  • Alternative work lines for year-round operation

51
Environmental Manufacturing
Write a Comment
User Comments (0)
About PowerShow.com