Title: The earth is like a solar battery absorbing nearly half of the suns energy' The ground stays a relat
1(No Transcript)
2Space the final Frontier
17 reflected by clouds.
100
6 reflected by surface.
Atmosphere
19 absorbed by water vapor, dust
4 absorbed by clouds.
46 absorbed by ground
Earth
The earth is like a solar battery absorbing
nearly half of the suns energy. The ground stays
a relatively constant temperature through the
seasons, providing a warm source in winter a
cool heat sink in summer.
3(No Transcript)
4Geothermal technology is friendlier to the
environment, because a) it uses the earth's own
free and renewable energy, b) no flame or gas is
required, and c) it produces zero emissions, so
it doesn't pollute the air or contribute to
global warming. According to the Environmental
Protection Agency (EPA), replacing an ordinary
HVAC system with a geothermal system is the
equivalent of planting 750 treesbenefiting the
environment. The average residential geothermal
unit saves the electric utility from burning an
additional 9.24 tons of coal each year,
dramatically reducing greenhouse gas
emissions. Installing just 400,000 geothermal
units each year could reduce greenhouse gas
emissions by more than one million metric tons of
carbon each year. This reduction in carbon
emissions is equivalent to converting more than
half a million cars to zero-emission vehicles, or
planting more than a million acres of trees. The
earth is a huge energy storage device that
absorbs 47 percent of the sun's energymore than
500 times more energy than mankind needs every
yearin the form of clean, renewable energy.
Geothermal systems take this heat during the
heating season at efficiencies that approach or
exceed 400 percent, and return it during the
cooling season. The EPA and the DOE have found
that geothermal systems can reduce energy
consumptionand corresponding greenhouse gas
emissionsby more than 40 percent compared to
air-source heat pumps and by more than 70 percent
compared to electric resistance heating with
standard air-conditioning equipment.
5How Much Is Available?
24
The Accessible Resource Base is 14x10 J the
resources are 5,000 EJ the reserves are reduced
to 500 EJ. Finally the reserve on land RoL,
which can be economically exploited for all the
geothermal energy utilization are 370 EJ it is
twice the total production of oil in 1996. Of
this RoL 2/3 can be accounted for low temperature
(lt150C), 1/3 for high temperature, suitable for
electricity production.
6(No Transcript)
7Basic Geothermal System with Water to Water Heat
Pump
8(No Transcript)
9Mole Hill Housing Society
- The Affordable, Sustainable Energy Alternative
10Mole Hill Community housing
- Located in the Vancouver Downtown
- 27 complete stand alone buildings
- 6-7 suites per building
- First Social housing in North America to
incorporate ground source heating into separate
buildings
11Pre Construction Concerns
- Will it supply the capacity to heat the heritage
homes - How to distribute the heat to the suites with
individual control - Enough physical space to drill the needed
boreholes - Cost effective manner for life cycle
- Justify cost difference over conventional system
12Heating Capacity
- Thorough heat loss calculation done for each
house - Thermal conductivity test done on the ground
- Back-up Water to Water heat exchanger added for
extreme cold cases
13Suite Distribution
- Koolfire Comfort coils used to distribute the
120F water from the Heat pump - Koolfire allows separate zone control for each
suite
14Suite Distribution
- Uses 24 VAC therefore allows for easy wiring
- Basement levels all have radiant in-floor heating
- This combination of distribution would be
impossible without the use of the Comfort coils
15House Distribution
- Common ground loop pumping station in center
home
Each home complete with Heat pump, Heating water
tank, Central hot water distribution piping
system
16House Distribution
- Each heat pump energizes pumps on Flow center to
average ground loop temperature - Helps eliminate need for large pumps normally
used to turbulent flow
17Drilling Boreholes
- Formation thermal conductivity test was done
- First of its kind to be done for a major
project in BC - A smaller rock mining drill rig was brought in
due to the limited space - 83 boreholes totaling 23,000 vertical feet was
drilled
18Life cycle and system performance
- Guarantee maintenance cost would be no more then
conventional - After 3 yrs of operation and regular maintenance
there has been almost no repair costs related to
the heat pump system - 80 less maintenance cost from a conventional
fossil fuel
19Cost Advantage
- Based on average 4000 Square Feet Mole Hill Home
20Cost advantage
21Environmental Advantages
- 605 tones of CO2 is reduced from the atmosphere
just from using the ground source heating system
22Mole Hill Housing Society
- The Affordable, Sustainable Energy Alternative
23Drilling Boreholes
- Formation thermal conductivity test was done
- A smaller rock mining drill rig was brought in
due to the limited space - 83 boreholes totaling 23,000 vertical feet was
drilled
24Oklahoma State Capital Bore Field
Oklahoma State Capital
Bore Field
25GEOTHERMAL GROUND SOURCE SYSTEMS USE A LOT OF
PIPE
26Bore Holes, Trench and Header
27Pre-fabricated Header Vault
28Interior of Pre-fabricated Vault
29Building Equipment Room
30Water Source Heat Pumps
31Greenhouses
32Standing Column Well Open System
Cased
Cased
To Heat Pumps
From Heat Pumps
Pump
Recirculation Depth
Bedrock
Bedrock
Tail Pipe
Uncased
Uncased
NTS
33Slinky Installation
34Hybrid System
35Apartment Complex-Shanghai
36SCHOOL
37SCHOOL
38Geothermal School Annual Energy Operating Costs
Comparison
Avg - 39 Savings
Dollars
275,271 SF
228,678 SF
171,185 SF
Arnold High - Closed-Loop Geothermal System
(completed Aug, 2000) School A - Gas
Boiler/Chiller System (Updated w/ new equipment
1996) School B - Multiple Systems
39Cost Advantage
- Based on average 4000 Square Feet Mole Hill Home
40Cost advantage
41(No Transcript)
42Low Cost Housing
- 3 Bed room
- 960 square feet
- Heating, Cooling and Water Heating averages
17/month at 0.07/kWh - Water to Air Heat Pumps (Forced Air Heating Air
Cond)
43Design Procedure
- Determine the heating/cooling loads (Btuh)
- Select heat pump size
- Select indoor air/water distribution system
- Estimate the ground heat exchanger loads
- Annual load
- Design months load
44System Components
- Buried Plastic Pipe
- Material
- Specifications
- Joining
- Heat Pumps
- Antifreeze Fluids
- Circulators
-
45Building Load (Btu/hr)ACCA Manual J
Outdoor Air Temperature
Ceilings
Doors
Windows
Walls
Indoor Air Temperature
46(No Transcript)
47(No Transcript)
48(No Transcript)
49Building Heating and Cooling Load Profile
Design Heating Load
Design Cooling Load
50,000 Btuh
36,000 Btuh
50,000 Btuh
36,000 Btuh
67
62
67
13
96
Outdoor Temperature F
50System Design
- Open Loop
- Pump and dump
- Standing column
- Ponds/lakes (direct and indirect)
- Closed Loop
- Vertical
- Horizontal
- Hybrid
- Soil/Rock Thermal Testing
- Grouting
51Existing Resources for Designers
- IPEX
- Design Manuals
- Computer Software
- Residential
- Commercial
- Manufactures Training
- Conferences
52Whos Involved
- Utility companies
- Installing contractors or dealers
- Heat pump manufacturers and distributors
- Plastic pipe manufacturers IPEX
- Fusion joining manufacturers
- Trenching and drilling manufacturers
- Research organizations, and professional
associations
53Benefits to HVAC Contractor
- Competes with low cost fossil fuels for customers
who prefer radiant heating - Higher profit margins than with conventional
equipment - System has an expected lifetime equal or greater
than conventional gas and electric systems - Well recognized as the highest efficient system
available a premier system
54Geothermal System
ISO 13256-1
IGSHPA
55Heat Pump Terminology
- Sensible Heat Factor (SHF)
- Sensible Cooling Load / Total Cooling Capacity
- Energy Efficiency (EFF)
- Energy Delivered / Energy Supplied
- Energy Efficiency Ratio (EER)
- Total Cooling Capacity (Btu/hr) / Power Input
(Watts)
56Heat Pump Terminology(continued)
Coefficient of Performance (COP) Heating
Capacity (Btu/hr) / Power Input
(Btu/hr) Entering Water Temperature (EWT) Water
Flow Rate (GPM) Air Flow Rate (CFM)
57Heat Pump Terminology(continued)
- Water pressure drop (WPD)
- Entering air temperature (EA)
- Total Heating Capacity (HC)
- Total Cooling Capacity (TC)
- Sensible Capacity (SC)
- Heat rejected (HR)
- Heat absorbed/extracted (HE)
58Heat Pump Sizing
- The SHF for the unit must be less than or equal
to the SHF for the space. - The cooling unit should be sized based on the
sensible cooling load for the space and the
sensible cooling capacity of the unit. - The latent requirement must be satisfied.
59Load 26,600 Btuh SHF 0.83
HP 025 26,700 Btuh SHF 0.69
HP 033
HP 033 31,800 Btuh SHF 0.70
9,600
Latent (Btuh)
4,300
8,200
3,800
Sensible (Btuh)
22,300
22,200
18,500
NTS
Heat Pump Sizing
60Heat Pump Sizing Example
61Heat Pump Data
- Entering Water Temperature
- Heating Capacity (Btu/hr)
- Coefficient of Performance (COP)
- Cooling Capacity (Btu/hr)
- Energy Efficiency Ratio (EER)
62Ground Water GWHP
Water Loop WLHP
Ground Loop GLHP
Tabulated performance data is at noted entering
water temperatures and entering air condition of
80.6o F DB / 66.2o F WB at ARI / ISO 13256-1
rated CFM.
63Annual Soil Temperature VariationStillwater, OK
USA
- Soil Type
- Annual Temperature Swing _at_ Surface - F
- Phase Constant _at_ Surface days
- Soil Depth feet
- Day of year
64Mean Temperature Variations
average soil (0.6 ft²/day or 0.025 ft²/hr)
65Mean Temperature Variations
20
10
0
10
20
groundtemperature, F
average soil (0.6 ft²/day or 0.025 ft²/hr)
66Heat Exchanger Design Menu
67Horizontal Single Pipe
- Single flow path
- Large land area required
- Larger pipe diameters required to reduce friction
loss - Increased antifreeze fluid volume
68Two-Pipe Horizontal Ground Heat Exchanger
- Single flow path
- Shorter trench required than a single pipe system
- Larger pipe diameter than a parallel system
69Horizontal 4-pipe System
- Reduced trench length
- Parallel flow
- Deeper trench is generally required
70Parallel Vertical System
- Small diameter pipe than series system
- Larger capacity heat exchanger can be designed
- ¾ and 1 inch pipe loops are common
- Bore hole depths can be increased in limited land
areas
71Vertical Series Heat Exchanger
- Larger pipe required for series system
- Large pipe difficult to handle
- Heat exchanger limited to about 3-tons because of
pipe friction
72Extended Slinky Four foot of pipe per foot of
trench
73Adequate supply of water Non-corrosive Place to
discharge water
74Standing Column Well Can Include Bleed
75Lake / Pond Heat Exchangers
- Slinky Type (HDPE 3408)
- Plate Type (stainless)
- Coiled Copper
- HDPE Pipe Rolls with Spacers
76(No Transcript)
77Pond Coil (with spacers)
Photographs courtesy of Jay Hammond Geothermal-Des
ign Associates Ft. Wayne, Indiana
78Great River uses a 1500-ton loop system on a 12
acre lake! Great River Medical Center is a
707,000 sq. ft. building, with 800 heat pumps and
a 100-mile-long piping system.
79Header Vault
1- inch vertical loops, Heat fusion joined,
Flanged connections
Air Vents
Shut Off Valves
Multiple Parallel Header Pipes (3 inch)
Pressure/Temp. Ports
Main Supply Header ( 8 inch)
80Chautauqua Lake Central Schools (K-12)Mayville,
NYBuilding Size 400,000 sq. ft.
81Designing Buried Pipe Systems(to facilitate air
removal)
- Air purging 2 ft/sec fluid velocity in all
piping sections of the ground heat exchanger
reference number 4 - Reduce purging power close header
- Air vents for initial filling
- Air trap systems during operation
82Parallel Vertical Configured Ground Heat
Exchanger
Supply Header (1-½ inch) Return Header (1½
inch) Reverse Return (1-½ inch) Loop (3/4
inch) U-Bend (3/4 inch)
83Debris Flushing and Air Removal
84Design and Layout Considerations
- Redundancy
- Pumping Options
- Central System
- Fluid Circulator Load Matched to Heat Pump
- Air Removal Capability and Serviceability
- Standard Header Design for Improved Air Purging
- System Performance Evaluation
8527 Ton Header
13 loops on 3 inch pipe
- Reverse return
- ¾ inch loops
- 3/4 , 1-1/2, 2 and 3
- inch header pipe
- SDR 11 and 15.5 HDPE pipe
7 loops on 2 inch pipe
4 loops on 1 -1/2 inch pipe
3 loops on ¾ inch pipe Close Header
86Thermal Properties of Soils Rocks
87Rules of Thumb 1 2
88Rules of Thumb 3 4
89 90Commercial Life Cycle Cost Analysis
- the sum of time-equivalent costs of
construction, operation, and maintenance of a
building, system or equipment over a designated
study period for alternatives that equally
satisfy functional requirements
91Variable Initial cost
- Equipmenthigh efficiency recommended
- Drilling cost and site conditions
- Controls--simple or complex-----------
- Piping type and sizing
- Piping accessories-----------
- Distribution system equivalent
- System design------------
- Value of floor square footage--
- Additional cost for structural reinforcement
- Additional cost for sound proofing
92Replacement
- Life Expectancy of air conditioning and heating
equipment - Life of ground Heat Exchanger
- Life of Air and Water Distribution Equipment
93How does the cost of fuels compare in equivalent
energy?
94- Electricity at .06/kwh---cop at 3.5
- .06/kwh x kw/3412btu x 100000btu/therm x
1/cop -
- .50/therm or 5.00/MMbtu
-
- Natural gas at .65/therm at 80 AFUE
- .65/therm x 1/afue
- .81/therm or 8.10/MMbtu
-
- Propane at .87/gal---afue 80(91,547 btu/gal)
- .87/91547btu x 100,000btu/therm x 1/afue
- 1.18/therm or 11.80/MMbtu
95Energy Costs
- Equipment Efficiencies
- Pumping efficiency based upon design and sizing
- Inflation variable
- Complex Utility Structure of Electric Rates
- Demand cost-Summer versus Winter
- Energy cost
- Meter Charge
- Fuel adjustment
- All electric Rate----Omaha Postal
- Franchise, local, state, ad valorem
96(No Transcript)
97Typical Natural Gas Billing
- Variable Fuel Cost/Mcf-month to month
- Well head price
- Plus Pipe line charges
- Plus Any approved Service fees
- Plus Meter Charge
- Plus Taxes
98Natural Gas Average Commodity Cost
99Operating, Maintenance and Replacement (OMR)
costs
- ASHRAE
- MEANS Estimating
- Manufacturers
- Contractors
- Owners
- Build your own actual database for Documentation
100Salvage Value
- Manufacturers
- Contractors
- Zero out at end of life for all alternatives
- Ground Heat exchanger is often 25-35 or more of
first cost. - Re-use or no Salvage
101Cost of Money
- Customer Provided Info only
- Accounting Depreciation Method
- Inflation rate-energy cost and money
- financed
- Income tax rate
- Study Life
- Depreciation Life
- IRRrequired internal hurdle rate---time
- 5years payback approx. 20 IRRTexaco
- Simple Payback-yearly savings/first costs
102Construction First Cost (/sq.ft.)based on
400sq.ft. per ton and approx 10k-50k sq.f.t bldg.
- Unitary Systems
- Geothermal Heat Pump 8-10
- Water Source Heat Pump 7-8
- Air Source Heat Pump Split 4-6
- Self-Contained DX Roof Top 3-4
- Thru-wall 2-3
- Central Station Systems
- Fan Coil (2-pipe) 8-9
- Fan Coil (4-pipe) 9-11
103Fan Coil Unit Controllers
- FCU 1 Fan, two pipe, modulating valve
- FCU 2 Fan, two pipe, floating point valve
- FCU 3 Fan, four pipe, modulating valve
- FCU 4 Fan, four pipe, floating point valve
104 Real Estate/Structural Savings
- No boilers, or chillers to house with
Geothermal,Air-cooled unitary, and Thru-wall
systems - No cooling towers or rooftop penthouses with
Geothermal Heat Pump, Air-cooled unitary, and
Thru-wall systems - Installed in wasted space such as ceilings
cavities core areas, and storage areas - Conventional floor mounted
- 2 to 4 of gross floor area
- Geothermal
- ½ to 1 of gross floor area w/ no outdoor
equipment
105Conventional GHP System Effect on Building
Components
- Do not have to have roof curbs components, but
available for roof mount - Less structural steel for supporting equipment
- Fewer roof access requirements
- Fewer roof membrane pads
- Less rigging required
- Without boiler, no boiler room, breeching, vent
or chimney, combustion air, fuel piping or
storage tank - Can provide more Rentable space
106Annual Maintenance Cost (/sf)
- Geothermal Heat Pump
- .11-.25
- Water Source Heat Pump
- .20-.30
- Fan Coil (2-pipe)
- .32-.50
- Air Source Dx/Heat Pump Split
- .23-.33
- Fan Coil (4-pipe)
- .40-.50
- Self-Contained Roof Top
- .29-.35
- Thru-Wall
- .28-.32
107Spreadsheet for LCC/ Sq. Ft.
108(No Transcript)
109(No Transcript)
110Limitations of Geothermal Heating and Cooling
- Maximum water temperatures 120F
- Land mass required
- Initial capital expense
- Lack of qualified personnel