Title: Sea Water Intrusion in the Los Osos Groundwater Basin Presentation of Updated Technical Studies prep
1Sea Water Intrusion in theLos Osos Groundwater
BasinPresentation of Updated Technical Studies
prepared by Cleath Harris Geologists
2Definitions
- Acre foot 326,000 gallons, one single family
home uses approximately 1/3 acre-ft each year
(AFY) - Safe yield the amount of water that can be
pumped without creating adverse conditions - Seawater intrusion an adverse condition wherein
seawater degrades a freshwater groundwater basin,
usually due to over pumping
3(No Transcript)
4(No Transcript)
5Downtown
Creek
Sand Spit
0
Upper Aquifer (Zone C)
Lower Aquifer (Zone D)
Lower Aquifer (Zone E)
Bedrock
-700
6Los Osos Drinking Water
- Three water suppliers LOCSD, GSWC, and ST
Mutual - Much of the upper aquifer is high in nitrates,
blending or treatment is required - The lower aquifer currently supplies 77 of the
water delivered by these suppliers
- Urban pumpers are exceeding the yield of the
lower aquifer by over 40
77 Lower
7Lower Aquifer Ground Water Elevations - 2001
Creek Valley
Morro Bay Estuary
At Sea Level
10 below
5 below
8Extent of Seawater Intrusion into the deepest
zone (Zone E) is not shown.
Area of Sea Water Intrusion into Lower Aquifer
(Zone D)
LOCSD Palisades Well
9Creek
Downtown
Sand Spit
Ocean
Upper Aquifer (C)
Lower Aquifer (D)
Lower Aquifer (E)
10(No Transcript)
11Sea water is the unwanted source in the lower
aquifer (values derived from 2002 Seawater
Intrusion study)
Los Osos Creek
Upper aquifer leakage
Sea Water Intrusion
12Current actions to combat seawater intrusion
- Purveyors reduction of water use (pumping) by
approximately 15 - Purveyors shift in lower aquifer pumping from
west to east - SLO County retrofit-upon-sale ordinance
- Purveyors attempting to shift to upper aquifer
through blending and future nitrate treatment
13Results of purveyor actions
- Sea water intrusion estimated in 2002 study
- 560 acre feet per year
- Current estimated sea water intrusion
- 420 acre feet per year
- Total purveyor pumping is approximately 2,050 AFY
(5 year average)
14ISJ Agreement
- February 2004 - Basin adjudication initiated by
LOCSD - September 2007 - Water Purveyors and the County
of SLO entered into an Interlocutory Stipulated
Judgment (ISJ) - August 2008 ISJ approved by court
- Current Conducting technical studies
negotiating Basin Management Plan (BMP)
15BMP Components
- Hydrologic assessment of the basin
- Strategy for maximizing reasonable and beneficial
use of the basin - Balancing basin under current development and
build-out - Protect environment influenced by the basin
- Quantification of water rights
- Water conservation goals
- Well abandonment and construction program
- Equitable sharing of costs
- Coordination with LOWWP
16ISJ Work Program
- Task 1 Completed
- Update steady state hydraulic model
- Assess the potential of the upper aquifer before
and after the wastewater project - Update safe yield estimates
- Update demand estimates
- Task 2 - Completed
- Evaluate and determine creek compartment safe
yield - Assess water quality of creek compartment
17ISJ Work Program
- Task 3 Pending
- Determine location of future wells for each
purveyor - Run additional groundwater model scenarios
- Confirm the amount of water required at
build-out, with aggressive conservation - Update water conservation plan
- Define water supply infrastructure and cost to
achieve a balanced basin at build out - Tasks 4 and 5 - Future
- Further development of the groundwater model
- Monitoring and assessment of actual basin
performance
18Relationship with the Los Osos Wastewater Project
- Balancing the Los Osos basin will be difficult
- The long term sustainability of the groundwater
basin must be a priority for treated effluent
produced by the LOWWP - Quantity Enact cooperative management agreement
to return treated effluent to the groundwater
basin - Quality Enact cooperative management agreement
to address long term management of salt,
nutrients and other contaminants - If the wastewater project is delayed, the ISJ
process will continue to move forward
19Relationship with the Los Osos Wastewater Project
ISJ Process
Tasks 1 2
Task 3 and BMP
Final BMP
2009
2010
Planning Comm.
BOS?
Coastal Comm?
Design/Construction
Wastewater Project Process
20Private Well Water Use Estimates
- Purpose to more accurately estimate the private
domestic pumping in the basin - Methodology
- - Irrigation / aerial surveys
- - Review of demand data
- - Development of demand factors
- Conclusion use estimates raised from 150 AFY to
200 AFY
21Agricultural Water Use Estimates
- Purpose to estimate ag pumping in the basin in
the Los Osos Creek valley - Methodology
- - Detailed crop data submitted by farmers to SLO
County - - Estimates of water use by crop
- - Consideration of average-year climate
- Conclusion previous use estimates confirmed
800 AFY
22Agricultural Water Use Estimates
23Agricultural Water Use Estimates
24Urban Area Basin Yield Update
- Purpose to estimate the yield of the urban area
under current and future conditions - Provides a tool for basin management and
infrastructure planning - Considers role of wastewater project in planning
efforts
25Updated groundwater model
- Simulates seawater intrusion over time (dual
density transient model) - Calibrated to match current conditions with a
50-year test run - Future production wells can be added and
optimized to determine safe yield.
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31Key Conclusions
- Seawater intrusion can be mitigated through
effective basin management including
conservation, pumping shifts, and monitoring - With effective basin management, adequate basin
yield exists for current demand - For build out demand, additional basin management
strategies will be necessary (Task 3)
32Key Conclusions
- Even with promising modeling results, significant
purveyor challenges and decisions lay ahead - If pumping can be reduced below the maximum
yield, water quality and infrastructure benefits
would result - Conservation, recycling, and other strategies can
further enhance water quality and allow for
unforeseen conditions (Task 3)
33Key Conclusions
- A sea level rise will result in a slightly lower
sea water density (thermal expansion) - A 2 sea level rise would reduce the safe yield
by approximately 50 AFY
34Creek Valley Yield Analysis
- Purpose to estimate the yield of the creek
valley portion of the aquifer - Previous studies assumed that yield matched
current pumping - Stream data pointed to the potential for
additional yield
35(No Transcript)
36Creek Valley Yield Scenarios
- Purveyor wells west of Los Osos Creek
- - Adjacent to existing purveyor infrastructure
- - May be more straightforward to permit
- Purveyor wells west and east of Los Osos Creek
- - Requires more extensive infrastructure
- - May integrate with recycled water agricultural
exchange programs
37(No Transcript)
38(No Transcript)
39Key Conclusions
- Yield increases by 250 AFY with purveyor wells on
the west side of Los Osos Creek - Yield increases by 500 AFY or more with purveyor
wells on both sides of Los Osos Creek - Significant decisions and challenges on well
locations, pumping, and infrastructure still
exist
40Key Conclusions
- Water quality information was not as extensive as
desired, but potable quality expected based on
test results - Significant decisions and challenges on well
locations, pumping, and infrastructure still
exist - Additional wet weather studies are recommended to
review actual creek flows
41Next Steps
- Complete Task 3, with a focus on conservation and
build-out supply infrastructure - Implement a Basin Management Plan
- Move forward on a funding mechanism to finance
water projects
42Next Steps
- Expedite conservation measures where possible.
- Continue to reduce demand on the lower aquifer
through pumping shifts and blending - Remain engaged in wastewater project discussions
43Questions?