Title: LHCb Vertex Detector System: Status Report J.F.J. van den Brand Subatomic Physics Group, VUA - NIKHEF
1LHCb Vertex Detector SystemStatus Report
J.F.J. van den BrandSubatomic Physics Group,
VUA - NIKHEF
- Milan design
- Optimized design
- mechanics
- vacuum system
- cooling system
- Summary
2Mechanics TP design
top half bottom half
See LHCb 99-042/VELO
3Milan design
- VELO Design
- Single flange
- XY table
- CO2 cooling
- WF suppressors
- Second. vacuum
- Studied
- assembly
- alignment
- To do
- further design
- FEA
4Detector and support frame
- both halves on same side
- VD easier to mount and
- position in the tank
- install complete VD at once
- the two halves are no
- longer interchangeable
5Vacuum vessel
- Employ top flange
- Easier installation
- Shorter cables
- Length 2000 mm
- Width 1200 mm
6Top flange
- Length 1500 mm
- Distance from ceiling 1900 mm
- Install using wires
- Baking to 60o C?
- Regenerate NEGs after every access to Si detectors
1900
770
Lift 600
7Optimized System
- Two detector boxes
- Baking up to 150o C
- Decouple access to Si detectors
8 Support system
- Microswitches at out position
- LVDTs
- Steel frame
- Alignment
- 2 planes
- 3 points each
- define IP
9Support system
- Alignment pins for reproducible coupling
- reproducible positioning
10Vessel Installation
- Move bellows to in-position
- Install vessel from top
- Align vessel
- Mount vessel to frame
- Mount bellows
- Pump-outs visible
11Install 2nd-Vacuum Vessel
- Remove upstream flange
- Need 2 m access
- Rectangular bellows
- 60 mm stroke
- normal 35 mm
- lateral 6 mm
- Fabrication
- Palatine, Bird
- Calorstat, MB
- cost
12Vacuum vessel / Positioning system
Secundary vacuum
- Moving parts not in vacuum
- Thin vacuum container
- Special bellows construction
Primary vacuum
13After installation
- Detector system separated from vacuum system
functionality - Mount positioning system to detector housing
- Install
- pump-out, valves
- turbos, damping
14Connect inner system to motion drives
- Mount M8 through side flanges
15Detector Installation
- Install detector halfs from sides
- Decouple detectors from box
- Tooling needed
16VELO Assembly
17Wakefield suppressors
- Mount screens after mounting 2nd vacuum container
- Mount through top flanges
- seal with view ports?
- Upstream mount with large flange off
18Wakefield suppressor downstream
- Up/downstream suppressors are identical
- Material CuBe
- Length 179 mm
- Thickness 100 ?m
- 16 segments
- Mounting to box non-trivial
19Wakefield suppressors
- Segments deform differently during movement
- Coating needed on suppressors
- Press-fit to beam pipe structure
- Anneal CuBe, deform, harden at 400o C
20Detector Mounting
Install Modules 3D alignment Mount References
21Thin Vacuum foil
- Beryllium expensive k 500 per container
- Aluminum
- welding 250 ?m Al is possible
- press-shaping being developed
- FEA ongoing
22Thin Vacuum foil
- Labour intensive press, anneal, etc.
- welding 250 ?m Al is possible
- Extensive prototyping program
CP?!
Chiel Bron
23Thin Vacuum foil
- Increase radius 10 ? 20 mm to avoid folding
- Crystal structure is affected
- Employ Al with magnesium alloy
- Deform at higher temperature 150 - 200o C
24Foil design ongoing (continued)
25Foil design ongoing
26Control of Vacuum System
- Group active with experience at former NIKHEF
accelerator - Propose meeting in Q1 2001
27Vacuum Tests
- Self-regulating valve behaves as advertized
- Various gas flows have been characterized
28Vacuum constraints
(rough!)
See LHCb 99-045/VELO
- LHC
- beam life time
- static density of 10-7 mbar ? 2 m (H2 300K) ?
- 0.01 of LHC limit for integrated
density - ( 2.7 106 cm ? 1.6 109 molecules/cm3
) - beam stability dynamic effects must be taken
into account - LHCb
- 10-7 mbar ? 1.2 m (H2 300K) ? 1.5 of LHCb
nominal luminosity - Difficult to achieve with silicon detectors,
electronics and signal wires - directly in LHC vacuum ! ? differential pumping.
29Static pressure in VD
Consider outgassing by assuming outgassing
rates of (mbar l s-1 cm-2) ? 11 m2
Kapton (signal wires, pumped 40 hours) 10-7
H2O ? 2.3 m2 Al housing (per half) 10-10
H2 ? 1.5 m2 bellows (per half) 10-9 H2 ? 8
m2 SS vessel 10-10 H2 Pumps in detector
volume ? 140 l/s (per half) H2O Pumps in
tank ? 4000 l/s H2 Bypass tube 200 mm ? 4
mm pumped in the middle. Calculate using a
static flow model. Result 110-4 mbar in
detector volume 110-8 mbar in VD
tank 210-8 mbar l s-1 from det. vol. to VD
tank
30Outgassing measurements
Summary table (Data are approximate. QLHCb_total
estimate for the full vertex detector, i.e.
both halves.) Item Outgassing rate of
item QLHCb_total mbar l s -1 Kapton
foil, after 40 hrs pumping 1 E-7 mbar l s -1
cm-2 n/a sample Kapton flat cable QPI
3 E-5 mbar l s -1 130 E-4 male/female pair
of PEEK D-type 25-pin connectors 6 E-6 mbar l s
-1 / pair 50 E-4 male/female pair of
stand. D-type 25-pin connectors 1 E-5 mbar l s -1
/ pair 100 E-4 Liverpool carbon-fiber Si
support 1 E-8 mbar l s -1 cm-2 1 E-4
Continue measure all unknown outgassing rates of
components in a detector station
31Dynamic Vacuum
See Adriana Rossis presentation
Beam-induced particle bombardment ? desorption,
emission
Ions, photons, electrons energies up to keV
- Local pressure runaway (ion/electron-induced
desorption) - Local static charge increase (electron
multipacting)
LHC beam instability
32Dynamic Vacuum (continued)
- Perhaps a solution
-
- use coating of surfaces by Ti
- advantages low ?SEY , low ?, local pumping
- Design issues
- better surfaces ? (NEG ?)
- in-situ coating required or not ?
- thickness of layer needed ?
- what re-coating rate ?
- affordable cathode temperature in-situ ?
- wake field / RF properties ?
- side effects ? (peeling, ...)
- We need ?, ? for
- different materials
- surface conditions (un)baked,
- saturated, activated, etc.
- different impact energy
- spectra
- Data available only in a
- few months ! (Mahner et al.)
33Cooling system with mixed-phase CO2
34CO2 Cooling Tests
Cooling system -30o C 40 W/module
35Mixed-phase CO2 Cooling system
See LHCb 99-046/VELO
CO2 gas-liquid storage tank 57.3 bar at 20 C
cool to 20 C
gas only
compresssor
heat to 20 C
pressure (temperature) regulating valve
CO2 supply line
flow restrictions
P W
cooling lines
P W
P W
supply line expansion valve
36CO2 Cooling Tubes
Cooling tubes 1.1 (0.9) mm S.St. Welding and
brazing
37FEA ongoing
38Tests ongoing
39RF tests at NIKHEF
- First 3 measured eigenmodes
- 220 MHz
- 270 MHz
- 380 MHz
Picture 1 of tank removed
Picture 2 of tank removed
Simulation with MAFIA
- Outlook
- Eigenmodes
- Short range effects Z/n
- Electric field inside secondary vacuum
40Wake field Suppressor
Central cooling line Temperature sensors (2 per
station, 4 wires per measurement
41Detector Modules
Liverpool delivers modules
44 pins, 440 / module
Discuss
Number of planes 25
40 W, 1 m cable, 50 isolation thickness, 10 -
15 K ?T, radiative cooling
42Summary
- Design is based on secondary vacuum system
- Beryllium option costly and uncertain
- needs approval for TDR
- Current design
- allows baking up to 150o C
- decouples Si detectors from primary vacuum system
- employs venting with Argon
- cooling based on CO2 in gas-liquid phase
- Self-regulating valves behave as advertised
- Wakefield excitation under study
- Need information on dynamic vacuum effects
- Propose meeting on control issues (e.g. NIKHEF)