Title: Tamalpais Union High School District Measure A Bond Modernization Program


1
Tamalpais UnionHigh School DistrictMeasure A
Bond Modernization Program
  • Almost-Home-Stretch Review
  • Board of Trustees
  • June 22, 2004

2
Agenda
  • Back to basics
  • Increment refresher
  • Schedule overview
  • Financial review
  • Program review
  • Master Plan-to-Complete

3
Back to basics
  • Remembering District goals
  • April 2001
  • Presentation to Board

4
Back to basics April 2001
  • Team members
  • Legal counsel
  • Architects
  • Construction management
  • Financial temporary position
  • Administrator temporary position
  • Consultants energy, technology, green building,
    funding experts.

5
Back to basics April 2001
DONE!
  • Team members
  • Legal counsel
  • Architects
  • Construction management
  • Financial temporary position
  • Administrator temporary position
  • Consultants energy, technology, green building,
    funding experts.

6
Back to basics April 2001
  • Committees
  • District Citizens Fiscal Oversight Committee
  • District Modernization Oversight Committee
  • Site Modernization Committees
  • Ad Hoc Site Committees
  • Ad Hoc District Committees

7
Back to basics April 2001
DONE!
  • Committees
  • District Citizens Fiscal Oversight Committee
  • District Modernization Oversight Committee
  • Site Modernization Committees
  • Ad Hoc Site Committees
  • Ad Hoc District Committees

8
Back to basics April 2001
  • Tentative Big Picture
  • September 2005 All major work completed
  • Summer 2005 All portables removed
  • Summer 2004 Phase IV starts
  • Winter 2004 Phase III starts
  • Winter 2003 Phase II starts
  • Summer 2002 Phase I starts
  • Spring 2002 State Projected Funding approval

9
Back to basics April 2001
  • Tentative Big Picture
  • September 2005 All major work completed
  • Summer 2005 All portables removed
  • Summer 2004 Phase IV starts
  • Winter 2004 Phase III starts
  • Winter 2003 Phase II starts
  • Summer 2002 Phase I starts
  • Spring 2002 State Projected Funding approval

Re-phased new completion 2/06
10
Increment refresher
  • Red completed
  • Green in construction
  • Orange bid, ready to award
  • Blue design done
  • Black Master Plan-to-Complete

11
Increment refresher
  • Tam 1 Campus utilities
  • Tam 2 Gus Gym/locker rooms, Palmer Hall
  • Tam 3 Upper campus
  • Tam 4 Theater, perimeter campus, Keyser
  • Tam 5 Master Plan-to-Complete
  • Red completed
  • Green in construction
  • Blue design done
  • Black Master Plan-to-Complete

12
Increment refresher (contd)
  • Drake 1 Campus utilities
  • Drake 2 Building 500
  • Drake 3 Main campus
  • Drake 4 Gym building, student center
  • Drake 5 Master Plan-to-Complete
  • Red completed
  • Green in construction
  • Orange bid, ready to award

13
Increment refresher (contd)
  • Redwood 1 Campus utilities
  • Redwood 2 Main campus
  • Redwood 3 Master Plan-to-Complete
  • Red completed
  • Green in construction

14
Increment refresher (contd)
  • Tamiscal Entire campus
  • Corp Yard 1 Print shop, auto shop
  • Corp Yard 2 Conversion of MCAL office
  • San Andreas Entire campus
  • Red completed
  • Green in construction
  • Blue design done

15
Increment refresher (contd)
  • Tam Fields
  • Drake Fields
  • Redwood Fields (except softball)
  • Redwood Softball
  • Green in construction
  • Blue design done

16
Schedule overview
  • Master Plan complete by 12/05
  • Current Plan complete by 2/06
  • Master Plan-to-Complete TBD

17
Construction schedule
  • Redwood 2 Now January 2005
  • Drake 3 Now October 2005
  • Tam 3 January 2004 June 2005
  • Redwood F-1 February 2004 February 2005
  • Tam Fields April 2004 February 2005
  • Drake Fields April 2004 February 2005
  • Drake 4 April 2004 August 2005
  • San Andreas April 2005 October 2004
  • Tam 4 August 2004 February 2006
  • Redwood F-2 June 2005 November 2005
  • Redwood 3 TBD 2005 - 2006
  • Drake 5 TBD 2005 - 2006
  • Tam 5 TBD 2005 2006

18
Construction schedule
  • Redwood 2 Now January 2005
  • Drake 3 Now August 2005 (earlier date!)
  • Tam 3 January 2004 June 2005
  • Redwood F-1 February 2004 February 2005
  • Tam Fields April 2004 February 2005
  • Drake Fields April 2004 February 2005
  • Drake 4 April 2004 August 2005
  • San Andreas April 2005 October 2005 (deferred
    one yr)
  • Tam 4 August 2004 February 2006
  • Redwood F-2 June 2005 November 2005
  • Redwood 3 TBD 2005 - 2006
  • Drake 5 TBD 2005 - 2006
  • Tam 5 TBD 2005 2006
  • Red new dates

19
Financial review
  • As of May 2004
  • Dollars rounded to nearest 1,000

20
Program overview
  • Original Master Plan 122,670,000
  • Bond 121,000,000
  • Interest 1,670,000
  • State funds/modernization 13,929,000
  • State funds/ADA 196,000
  • Federal grant 149,000
  • Current budget 136,944,000

21
Program overview (contd)
  • Anticipated additional funds
  • State funds for San Andreas 458,000
  • Additional interest 1,000,000
  • These funds will be recommended for allocation
    back to reserves.

22
Donations
  • Redwood Dugout Club 75,000
  • Moody infield turf
  • Tam Foundation 15,000
  • Sliding marker boards, science classrooms
  • Redwood Parents 10,000
  • Alternative design, football bleachers
  • Redwood Benchwarmers 3,000
  • Extra work in training room

23
Approved reserve allocations
  • Fields 6,042,000
  • Drake (gym, student center) 2,700,000
  • Technology 1,855,000
  • Redwood (change orders) 1,000,000
  • District Office 1,000,000
  • Miscellaneous (38 items) 3,117,000
  • see Exhibit A

24
Anticipated reserves
  • 6,299,000 Current program reserves
  • - 3,900,000 Proposed allocations
  • 7,358,000 Possible budget savings
  • 458,000 State funding for San Andreas
  • 1,000,000 Additional earned interest
  • 11,215,000 Anticipated reserves
  • See Exhibit A, page 3

25
Program budgets by site
26
Budgets by category ()
  • Master Plan
  • Construction 70 70
  • Support costs 25 23
  • Reserves 5 7
  • (of current total budget)

27
Funds committed to date ()
  • Construction 62
  • Support costs 76
  • Total program 63
  • (of each budget)
  • Total commitments have increased almost 20 in
    six months.

28
Change orders
  • Major contracts (gt 100,000) 13
  • Total of base contracts 38,321,224
  • Change order contingencies 4,485,70810
    Redwood/Drake 15 Tam 20 fields
  • Change orders to date 3,940,918Percentage
    10.3
  • Contingency unspent to date 544,79013
    major contracts only

29
What were watching
  • Construction prices
  • Steel, wood, gasoline, concrete
  • Tamalpais age-related damage
  • Dry rot, beetles, water
  • Field construction
  • Scheduled turf installation, site conditions
  • Relocation
  • Moving logistics, portables, storage, parking
  • Support costs through FY 05-06
  • Staffing, operating costs, design fees

30
More about Tam Gus Gym
  • The problem
  • Beetles (floor and substructure)
  • Sinking substructure
  • Sports floor at 90 of useful life
  • Proposed solution
  • 25-30 year, 1 million fix
  • Fumigate
  • Improve drainage
  • Replace substructure w/ jacks
  • Replace floor
  • Preventive maintenance plan

31
More about Tam dry rot
  • Hoetger / Phoenix
  • Sub-floor
  • Drainage
  • Increment 3 remaining buildings
  • Increment 4 existing buildings
  • Destructive testing
  • Scope of repairs
  • Costs

32
Still ahead
  • Drake Increment 4 bid award tonight
  • Tam Increment 4 - Fall
  • San Andreas - Winter
  • Gus Gym - Winter
  • Redwood Softball 05-06
  • Master Plan-to-Complete 05-06

33
Master Plan-to-Complete
  • July Scope development
  • Early August Input from Principals
  • Mid-August Review by District Oversight
    Committee
  • September Board approval (plan)
  • October Fund review
  • November Board approval (funds)