Title: Tamalpais Union High School District Measure A Bond Modernization Program
1Tamalpais UnionHigh School DistrictMeasure A
Bond Modernization Program
- Almost-Home-Stretch Review
- Board of Trustees
- June 22, 2004
2Agenda
- Back to basics
- Increment refresher
- Schedule overview
- Financial review
- Program review
- Master Plan-to-Complete
3Back to basics
- Remembering District goals
- April 2001
- Presentation to Board
4Back to basics April 2001
- Team members
- Legal counsel
- Architects
- Construction management
- Financial temporary position
- Administrator temporary position
- Consultants energy, technology, green building,
funding experts.
5Back to basics April 2001
DONE!
- Team members
- Legal counsel
- Architects
- Construction management
- Financial temporary position
- Administrator temporary position
- Consultants energy, technology, green building,
funding experts.
6Back to basics April 2001
- Committees
- District Citizens Fiscal Oversight Committee
- District Modernization Oversight Committee
- Site Modernization Committees
- Ad Hoc Site Committees
- Ad Hoc District Committees
7Back to basics April 2001
DONE!
- Committees
- District Citizens Fiscal Oversight Committee
- District Modernization Oversight Committee
- Site Modernization Committees
- Ad Hoc Site Committees
- Ad Hoc District Committees
8Back to basics April 2001
- Tentative Big Picture
- September 2005 All major work completed
- Summer 2005 All portables removed
- Summer 2004 Phase IV starts
- Winter 2004 Phase III starts
- Winter 2003 Phase II starts
- Summer 2002 Phase I starts
- Spring 2002 State Projected Funding approval
9Back to basics April 2001
- Tentative Big Picture
- September 2005 All major work completed
- Summer 2005 All portables removed
- Summer 2004 Phase IV starts
- Winter 2004 Phase III starts
- Winter 2003 Phase II starts
- Summer 2002 Phase I starts
- Spring 2002 State Projected Funding approval
Re-phased new completion 2/06
10Increment refresher
- Red completed
- Green in construction
- Orange bid, ready to award
- Blue design done
- Black Master Plan-to-Complete
11Increment refresher
- Tam 1 Campus utilities
- Tam 2 Gus Gym/locker rooms, Palmer Hall
- Tam 3 Upper campus
- Tam 4 Theater, perimeter campus, Keyser
- Tam 5 Master Plan-to-Complete
- Red completed
- Green in construction
- Blue design done
- Black Master Plan-to-Complete
12Increment refresher (contd)
- Drake 1 Campus utilities
- Drake 2 Building 500
- Drake 3 Main campus
- Drake 4 Gym building, student center
- Drake 5 Master Plan-to-Complete
- Red completed
- Green in construction
- Orange bid, ready to award
13Increment refresher (contd)
- Redwood 1 Campus utilities
- Redwood 2 Main campus
- Redwood 3 Master Plan-to-Complete
- Red completed
- Green in construction
14Increment refresher (contd)
- Tamiscal Entire campus
- Corp Yard 1 Print shop, auto shop
- Corp Yard 2 Conversion of MCAL office
- San Andreas Entire campus
- Red completed
- Green in construction
- Blue design done
15Increment refresher (contd)
- Tam Fields
- Drake Fields
- Redwood Fields (except softball)
- Redwood Softball
- Green in construction
- Blue design done
16Schedule overview
- Master Plan complete by 12/05
- Current Plan complete by 2/06
- Master Plan-to-Complete TBD
17Construction schedule
- Redwood 2 Now January 2005
- Drake 3 Now October 2005
- Tam 3 January 2004 June 2005
- Redwood F-1 February 2004 February 2005
- Tam Fields April 2004 February 2005
- Drake Fields April 2004 February 2005
- Drake 4 April 2004 August 2005
- San Andreas April 2005 October 2004
- Tam 4 August 2004 February 2006
- Redwood F-2 June 2005 November 2005
- Redwood 3 TBD 2005 - 2006
- Drake 5 TBD 2005 - 2006
- Tam 5 TBD 2005 2006
-
18Construction schedule
- Redwood 2 Now January 2005
- Drake 3 Now August 2005 (earlier date!)
- Tam 3 January 2004 June 2005
- Redwood F-1 February 2004 February 2005
- Tam Fields April 2004 February 2005
- Drake Fields April 2004 February 2005
- Drake 4 April 2004 August 2005
- San Andreas April 2005 October 2005 (deferred
one yr) - Tam 4 August 2004 February 2006
- Redwood F-2 June 2005 November 2005
- Redwood 3 TBD 2005 - 2006
- Drake 5 TBD 2005 - 2006
- Tam 5 TBD 2005 2006
- Red new dates
19Financial review
- As of May 2004
- Dollars rounded to nearest 1,000
20Program overview
- Original Master Plan 122,670,000
- Bond 121,000,000
- Interest 1,670,000
- State funds/modernization 13,929,000
- State funds/ADA 196,000
- Federal grant 149,000
- Current budget 136,944,000
21Program overview (contd)
- Anticipated additional funds
- State funds for San Andreas 458,000
- Additional interest 1,000,000
- These funds will be recommended for allocation
back to reserves. -
22Donations
- Redwood Dugout Club 75,000
- Moody infield turf
- Tam Foundation 15,000
- Sliding marker boards, science classrooms
- Redwood Parents 10,000
- Alternative design, football bleachers
- Redwood Benchwarmers 3,000
- Extra work in training room
23Approved reserve allocations
- Fields 6,042,000
- Drake (gym, student center) 2,700,000
- Technology 1,855,000
- Redwood (change orders) 1,000,000
- District Office 1,000,000
- Miscellaneous (38 items) 3,117,000
- see Exhibit A
24Anticipated reserves
- 6,299,000 Current program reserves
- - 3,900,000 Proposed allocations
- 7,358,000 Possible budget savings
- 458,000 State funding for San Andreas
- 1,000,000 Additional earned interest
- 11,215,000 Anticipated reserves
- See Exhibit A, page 3
25Program budgets by site
26Budgets by category ()
- Master Plan
- Construction 70 70
- Support costs 25 23
- Reserves 5 7
- (of current total budget)
27Funds committed to date ()
- Construction 62
- Support costs 76
- Total program 63
- (of each budget)
- Total commitments have increased almost 20 in
six months.
28Change orders
- Major contracts (gt 100,000) 13
- Total of base contracts 38,321,224
- Change order contingencies 4,485,70810
Redwood/Drake 15 Tam 20 fields - Change orders to date 3,940,918Percentage
10.3 - Contingency unspent to date 544,79013
major contracts only
29What were watching
- Construction prices
- Steel, wood, gasoline, concrete
- Tamalpais age-related damage
- Dry rot, beetles, water
- Field construction
- Scheduled turf installation, site conditions
- Relocation
- Moving logistics, portables, storage, parking
- Support costs through FY 05-06
- Staffing, operating costs, design fees
30More about Tam Gus Gym
- The problem
- Beetles (floor and substructure)
- Sinking substructure
- Sports floor at 90 of useful life
- Proposed solution
- 25-30 year, 1 million fix
- Fumigate
- Improve drainage
- Replace substructure w/ jacks
- Replace floor
- Preventive maintenance plan
31More about Tam dry rot
- Hoetger / Phoenix
- Sub-floor
- Drainage
- Increment 3 remaining buildings
- Increment 4 existing buildings
- Destructive testing
- Scope of repairs
- Costs
32Still ahead
- Drake Increment 4 bid award tonight
- Tam Increment 4 - Fall
- San Andreas - Winter
- Gus Gym - Winter
- Redwood Softball 05-06
- Master Plan-to-Complete 05-06
33Master Plan-to-Complete
- July Scope development
- Early August Input from Principals
- Mid-August Review by District Oversight
Committee - September Board approval (plan)
- October Fund review
- November Board approval (funds)