Title: Emergency Management Strategies: Lessons Learned in Developing Specifications, Procuring, Housing and Maintaining a 100-Bed Mobile Hospital
1Emergency Management Strategies Lessons Learned
in Developing Specifications, Procuring, Housing
and Maintaining a 100-Bed Mobile Hospital
- Jenny Atas MD
- Associate Professor
- Wayne State University
- Medical Director
- Region 2 South Medical
- Bio-Defense Network
Mark Sparks Logistics/Planning Officer Region 2
South Medical Bio-Defense Network
2Presentation Overview
- Project Background
- Acquisition Process and Specifications
- Durable and Non-Durable Equipment Acquisition
Process - Storage Deployment Considerations
3PROJECTBACKGROUND Organization
4Project Background Organization Pre 9-11
District Organization
- 8 Emergency Management Districts covering 83
Counties - 45 Public Health Departments
- 65 Medical Control Authorities (oversight of
pre-hospital system) with no seat at the table
5Project Background OrganizationPost 9-11 New
Paradigm of Planning
Emergency Management
Health Care
Public Health
6Project Background OrganizationPost 9-11 HHS
Grant Programs
HRSA (now HHS ASPR)
CDC
Medical Control Authorities Hospital/Pre-hospital
Local Health Departments Other Local/Regional
Partners
Coordinated State/Local/Regional Planning
7Project Background - Organization Post 9-11
Regional Organization
- 8 Medical Bio-Defense Regions
- Mirror of 8 E.M. Districts
- Incorporates 65 MCAs
- Bioterrorism Coordinator
- Medical Director
- Emergency Preparedness Coordinator (Local Health
Department) - Epidemiologist
- SNS Technical Advisor
- Seat at the table
8Project Background OrganizationRegion 2 South
(R2S) Overview
- 3 Counties 97 local political jurisdictions 2.6
million people - 14 P.A. 390 Emergency Management/Homeland
Security Programs (4 with Public Health
authority) - 6 Public safety mutual
aid
organizations - 4 Public Health Authorities
- 4 Medical Control Authorities
- 37 Hospitals
- 69 Fire/EMS agencies
- 11 Private/EMS agencies
9Project Background OrganizationLessons Learned
- Regional Partnership with Emergency Management is
Critical - Development of surge plans, procedures and
resources must involve all disciplines - Take full advantage in the ability to leverage
other federal funding streams (restrictions /
allowances) - Allows you to mitigate duplication of effort on
all fronts
10PROJECTBACKGROUND Foundation DHHS NBHPP
Program Guidance for Fiscal 2006 dictates that
states have the ability to surge outside
hospitals and healthcare systems
11Project Background FoundationSituation
- Hospitals in Michigan have incorporated the
ability to surge 20 above the average daily
census. - Even with these additional 7,000 beds there still
exists insufficient surge response capability to
address the needs that a medium level pandemic - MEMS remains the primary method of addressing
- Medical Surge Capacity and Capability (MSCC)
- Hurricane Katrina demonstrated the utility of
surge facilities
12Project Background FoundationSituation
- Pandemic Flu
- Outbreak of a moderately severe pandemic flu
would exhaust surge capacity within the first two
weeks - Natural and Man-Made Disasters
- Trauma victims immediately exhaust surge capacity
- Non-urgent health problems are exacerbated and
further increase healthcare demands - Local Healthcare Emergencies
- International air-traveler quarantine
- 2003 SARS 3,017,496 international passengers
thru DTW - All hazards response capability
13Project Background FoundationSituation
- In light of these factors a decision was made to
utilize HRSA/ASPR funding to develop two
self-contained all-weather mobile field hospitals
or surge facilities - Initially develop and equip a 100-bed unit
- Lay the groundwork
- Based on available funding, develop a 50-bed unit
- Extension of 100-bed unit
- Rapid acquisition rely on established
specifications
14Project Background Foundation Patient and
Staff Planning Assumptions
- The Mobile Field Hospital would be designed
- For patients suffering from COPD, asthma,
congestive heart failure (no C-PAP or vent),
chronic pain syndrome, and behavioral conditions,
and needing IV hydration and IV antibiotic
therapy - With a 41 ratio of adult to pediatric patients
- With a planned admission/discharge rate of 23
hours - To be operated by a core team of medical
professionals augmented by volunteers (Michigan
Volunteer Registry)
15Project Background FoundationLessons Learned
- Dont recreate the wheel
- Patient profile from the Katrina disaster
experience - Patient demographics from Michigan Census
- Staff profile from existing Michigan plans for
Alternate Care Facilities/MEMS Model
16Transportable Emergency Surge Assistance Medical
Unit( TESA) Facility Acquisition Process
17TESA Project Facility Acquisition ProcessGrant
Application
- Region 2 South was selected to develop the
100-Bed TESA Unit - The project was outlined in Region 2 Souths FY
06-07 HRSA Grant Application - Statewide resource housed in S.E. Michigan and
operated by strike teams from across the state - Complete project within the grant year
- Establish a Task Force to
- Research the different platforms and associated
planning, operational, administrative and
logistical considerations - Recommend how to best configure and develop the
facility within budgetary constraints
18TESA Project Facility Acquisition Process
Grant Approval / Initial Steps
- Project was approved 1,000,000 budget
- Task Force formed in October 2006.
- Agencies represented
- Region 2 South Medical Bio-Defense Network
- Michigan Department of Community Health, Office
of Public Health Preparedness - Michigan Department of State Police, Emergency
Management/Homeland Security Division - Michigan-1 Disaster Medical Assistance Team
19TESA Project - Facility Acquisition Process Task
Force Determinations
- The recommended basic platform for the facility
would be a soft-walled shelter structure. - To account for cost uncertainties, the platform
(and invitation to submit proposals) would be
designed around - A core 50-bed facility (to include areas for
triage, supply, admin, and staff support) - 25-bed add-on patient wards.
20TESA Project - Facility Acquisition Process Task
Force Requirements
- Basic Requirements for the 50-Bed Core
- Separate staff and patient entrances
- Separate areas for facility administration,
facility supplies, staff lounge and staff
hygiene, and patient care wards - a. Staff hygiene must have a changing area, sink,
shower and toilet, cold and hot water, an
on-board potable water supply with a water
distribution system and a gray water containment
system - Each patient ward must be equipped with a private
field toilet (the Brief ReliefTM system, or
equivalent)
21TESA Project Facility Acquisition ProcessTask
Force Requirements
- Basic Requirements for the Entire Shelter System
- Completely self-contained
- Trailer-mounted generators
- Maximum component size (98w, 50d, 50h)
- Man-portable components (maximum 75lb per worker)
- Rapidly erected without the use of tools or
equipment - Must provide all-weather climate controlled
environment - Materials must meet NFPA Standards
- Must be interoperable with existing FEMA-NDMS
assets
22TESA Project - Facility Acquisition Process Task
Force Determinations
- Proposal/Bid Quotation Requirements
- Must provide a comprehensive description of
- Proposed system components
- Warranties, manuals, parts availability
guarantees - Where requirements are met or exceeded
- Where requirements are not met and why a variance
should be considered - How it will be packaged w/container dimensions
- Must include diagrams (50-bed core, 75-bed and
100-bed configurations) - Must identify single POC for notices and inquires
- Must be submitted by e-mail (formatted in MS Word
and Adobe PDF.
23TESA Project - Facility Acquisition Process Task
Force Determinations
- Parameters established to select potential
shelter sources - Identify potential sources known by the Task
Force to manufacture shelters that - Generally met platform requirements
- Were in common use as mobile medical facilities
- To maximize practical competition, limit the
minimum number of potential sources to 3 - To minimize the procurement process, limit the
maximum number of potential sources to 6
24TESA Project - Facility Acquisition Process Task
Force Determinations
- Six potential platform sources were identified
- 4 that generally met shelter requirements and had
been used by members of the Task Force - 1 that generally met shelter requirements but was
unknown to members of the Task Force - 1 that manufactured hard-walled shelters, was
unknown to members of the Task Force but was a
Michigan-based company - These 6 potential vendors were e-mailed the
Invitation to Submit a Combined Proposal/Bid
Quotation
25TESA Project - Facility Acquisition Process The
RFP/RFQ Package
- Task Force determinations were reduced to a
3-page invitation to submit a combined
Proposal/Bid Quotation
- that would be e-mailed to pre-selected vendors.
26TESA Project - Facility Acquisition Process The
RFP/RFQ Package
- Task Force determinations were reduced to a
3-page invitation to submit a combined
Proposal/Bid Quotation
- that would be e-mailed to pre-selected vendors.
27TESA Project - Facility Acquisition Process
Evaluating Proposals/Quotes
- All invitees responded
- Hundreds of pages
- Each with unique format
- Some highly detailed and well organized
- Some lacked detail and organization
- All were printed, bound and distributed to each
member of the Task Force
28TESA Project - Facility Acquisition Process
Evaluating Proposals/Quotes
- COMPARABLES
- Quote Duration
- Cost
- Max Size Container
- Assembly
- Basic Units
- Access Doors
- Area (sq. ft.)
- Furniture
- Power
- Lighting
- Outlets
- HVAC
- NDMS Interop?
- Trailer Boot
- Warranty
- Framing
- Fabric
- Insulation
THE EVALUATION MATRIX
29TESA Project - Facility Acquisition Process
Awarding the Contract
- 2 vendors RFP/RFQ met specs, the other 4 were
eliminated from competition - Task Force members to NDMS conference to inspect
both shelter systems - Gained experience - revised specifications
- Requested final quote on revised specifications
- Reviewed final quotes
- Unanimous agreement to award contract
30TESA Project - Facility Acquisition Process
Lessons Learned
- Need experienced and knowledgeable team to avoid
pitfalls when expediting a complex project - Need comparison matrix to efficiently deal with
variable specifications - No substitute for getting your hands dirty
(in-person inspection and assembly) - No substitute for face-to-face discussion with
vendor representatives
31TESAPROJECT Facility Specifications
32TESA Project Facility SpecificationsQuick Specs
- 10,000 Sq. Ft. Enclosed Area
- 20,000 Sq. Ft. Footprint (125 x 158)
- 5 Generators (4 _at_ 36kW and 1 _at_ 56 kW)
- 16 HVAC
- 15 _at_ 42K BTU heat/3.5 ton cool/29K heat strip
- 1 _at_ 60K BTU heat/cool/HEPA positive or negative
pressure) - 4 Hygiene Centers
- Each with sink, shower, toilet, hot H2O,
500-gallon fresh and gray water holding tanks
- 16 Interconnected Shelters
- 1 each for Administration, Staff, Supply (w/boot)
and Intake/Triage/Treat - 1 ten-bed Patient Ward (isolation)
- 7 ten-bed Patient Wards
- 4 five-bed Patient Wards
- Design
- 41 ratio of adult to pediatric patients
- Admit/Discharge Rate 23 hours ( 100 patients
per day) - Over 1,000 Separate Pieces
33TESA Project Facility SpecificationsThe Design
34TESA Project Facility SpecificationsTactical
Labeling
- The components of each individual shelter are
- Color-coded labeled
- Packaged together
35TESA Project - Facility SpecificationsTactical
Storage
36TESA Project Facility SpecificationsAs Built
(40-Bed Unit)
37TESA Project Facility Specifications Lessons
Learned
- Color-code and label individual shelter
components - Facilitates handling
- Has limitations
- Only so many distinct colors
- Correlates only to complete 100-bed layout
- Because it is a white vinyl tent labor intensive
for cleaning before repackaging - Setup and tear down takes expertise
- Requires the development of specialized teams
38TESAPROJECT Equipment Supply Acquisition
39TESA Project Equipment/Supply Acquisition
ProcessPatient Staff Profile
- The Mobile Field Hospital would be designed
- For patients suffering from COPD, asthma,
congestive heart failure (no C-PAP or vent),
chronic pain syndrome, and behavioral conditions,
and needing IV hydration and IV antibiotic
therapy - With a 41 ratio of adult to pediatric patients
- With a planned admission/discharge rate of 23
hours - To be operated by a core team of medical
professionals augmented by volunteers (Michigan
Volunteer Registry)
40TESA Project Equipment/Supply Acquisition
ProcessTask Force Determinations
- The stakeholder Task Force determined to utilize
sole-source provider of medical supplies and
equipment to outfit the facility - Previously qualified source
- Current source of ACC and NEHC facilities for
MEMS components. - Demonstrated ability
- Medical expertise to identify and meet needs
(based on expected patients and healthcare staff) - Professional packaging
- Competitive pricing
41TESA Project Equipment/Supply Acquisition
ProcessPatient Profile Questionnaire
- Comprehensive questionnaire was used to refine
the patient profile and then determine what level
of service would be provided over a given period
of time
42TESA Project Equipment/Supply Acquisition
ProcessCapability Worksheet
Function (sample) Adult PEDS Infant
Airway X X X
Wound Treatment X X X
IV Therapy X X X
Ortho Care X X X
EENT X X X
Genitourinary X X X
Gastrointestinal X X X
Medication Admin X X X
Emergency Care X X X
43TESA Project Equipment/Supply Acquisition
Process Master Template
- Master Template was used to generate the type of
treatment which could be offered and the type and
quantity of equipment and supplies needed.
44TESA Project Equipment/Supply Acquisition
Process The Design
45TESA Project Equipment/Supply Acquisition
Process The Design
46TESA Project Equipment/Supply Acquisition
Process The Design
47TESA Project Equipment/Supply Acquisition
Process The Design
48TESA Project Equipment/Supply Acquisition
Process The Design
49TESA Project Equipment/Supply Acquisition
Process The Design
50TESA Project Equipment/Supply Acquisition
Process The Design
51TESA Project Equipment/Supply Acquisition
Process The Design
52TESA Project Equipment/Supply Acquisition
Process Lessons Learned
- Patient Profiles will define the treatment
modalities necessary - Establish a cache which is broadly used so that
replenishment is easier and can be integrated
into a local healthcare system - Establish Augmentation Sets to supplement
specialty areas - OB-GYN
- PEDS
- Isolation
- O2 Therapy
- Nursery
- Establish and procure basic equipment lists which
do not require long training sessions
53TESAPROJECT Storage Deployment
Considerations MAXIMIZEDEPLOYMENT AND
RECOVERY SPEED
54TESA Project Storage/Deployment Considerations
Tactical Containerization Labeling
- Color-coded labels
- Color-coded packages
- Color-coded containers and augmentation sets
- Modules which are color-coded and containerized
55TESA Project Storage/Deployment Considerations
Containers
- Storage
- Pallet size
- Weight
- Deployment
- On or off pallets?
- Storage of shipping materials
- Re-packing
- Sustainment
56TESA Project Storage/Deployment Considerations
Transporting Handling
- Transport Vehicle
- Semi-trailers
- Flat bed
- Dry box
- Box truck
- Material Handling Equipment
- Fork Lifts
- Pallet Jacks
57TESA Project Storage/Deployment Considerations
Trailer-Mounted Generators
- Shipping
- Flat Bed - loading unloading
- Need loading dock
- Need material handling equipment
- Individual
- Multi tow-vehicles and drivers
58TESA Project Storage/Deployment Considerations
Storage Space
59TESA Project Storage/Deployment Considerations
Storage Scheme
60TESA Project Storage/Deployment Considerations
Lessons Learned
- Color-coding simplifies storage, picking,
shipping and sustainment planning and execution - Consider the storage of shipping materials
(pallets, containers, etc.) in deployment plans - Know your material handling equipment needs
- Field (e.g. parking lot) vs. fixed facility (e.g.
conference/exhibition center)
61Emergency Management Strategies Lessons Learned
in Developing Specifications, Procuring, Housing
and Maintaining a 100-Bed Mobile Hospital
Jenny Atas MD R2S Medical Director e-mail
jatas_at_2south.org Mark Sparks R2S Planning
Logistics Officer e-mail msparks_at_2south.org