Overview of the ARCS Project Plan: The View at One Year - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Overview of the ARCS Project Plan: The View at One Year

Description:

High temperature superconductivity. Crystal field spectroscopy ... SEQUOIA a proposal for high-resolution. Principal Investigator : Steve Nagler ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 12
Provided by: dougabe
Category:
Tags: arcs | one | overview | plan | project | view | year

less

Transcript and Presenter's Notes

Title: Overview of the ARCS Project Plan: The View at One Year


1
Overview of the ARCS Project PlanThe View at
One Year
ARCS IDT Meeting Lujan Center, LANL
September 30, 2002
  • Doug Abernathy
  • ARCS Instrument Scientist

SNS Instrument Systems
Argonne/Oak Ridge
2
ARCS -- The Project -- Key People and Places
Brent Fultz -- Caltech (project leader,
coordinator, aligner of personnel) Doug
Abernathy -- Caltech and Argonne (hardware
project manager) Michael Aivazis -- Caltech
(software project manager) Hardware Engineering
Argonne (Robb Williams) Hardware Construction
-- Oak Ridge Software -- Caltech
3
ARCS -- The Project -- Management
4
Bifurcation of ARCS
  • Full instrument had no contingency funds
  • Canadian CFI program prompted interest in a
  • second high-energy chopper instrument
  • International class facility should have a
    general
  • purpose and a magnetism instrument

Presently
CNCS (Eilt50 meV) 2 resolution 140o at 3 m
SEQUOIA 1 resolution 60o at 5.5 m
ARCS 2 resolution 140o at 3 m
5
a wide Angular-Range Chopper
Spectrometer
Intended for study of atomic-scale dynamics in
the thermal and epithermal range with single
crystal capability.
Moderator decoupled poisoned water Beam
line 18 Source-sample 13.6 m Sample-detector 3.0m
IDT headed by Brent Fultz Scientist Doug
Abernathy
  • Lattice dynamics
  • Entropy and the effects of vibrational modes on
    stability and phase transitions of solids
  • Excitations in disordered materials effects of
    nanoscale features on vibrational entropy and
    thermodynamic stability
  • Equations of state from measurements of the
    phonon density of states as a function of
    temperature and pressure
  • Phonons in correlated-electron materials
    coupling of lattice and electronic degrees of
    freedom in high Tc, heavy-fermion and mixed
    valence materials
  • Magnetic dynamics
  • High temperature superconductivity
  • Crystal field spectroscopy
  • Low dimensional systems 1D quantum magnets and
    low-dimensional conductors
  • Magnetism in actinide materials
  • Heavy fermion magnetism and superconductivity
  • Metal-insulator transitions in oxides
  • Chemical Physics
  • Deep inelastic neutron scattering studies of
    hydrogen
  • Characterization of novel materials

6
ARCS Instrument Overview
Moderator
Shutter
Guides
Choppers
Sample
Detector Array
7
DOE Review March 2002
  • The ARCS Baseline Review Committee included
    experts in instruments and in project management
    because no previous reviews had been held.
  • Important recommendations
  • Develop a Project Execution Plan and Memorandum
    of Agreement with SNS to solidify the project
    management structure
  • Major instrumental uncertainties need to be
    address
  • Operation of detectors in vacuum
  • Shielding needed for personnel dose rates and
    backgrounds

8
Key dates in schedules as presented 3/02
  • Early Late
  • Project start 9/01 9/01
  • Detector in vacuum decision 9/02 9/02
  • Guide procurement 9/02 9/02
  • First detector module procurement 8/03 9/05
  • Vessel procurement 9/03 10/03
  • Target inserts needed 6/04 6/04
  • Target Building occupancy date 6/04 6/04
  • Start installation 6/04 6/04
  • End detector module assembly and
    testing 5/05 7/06
  • SNS project early completion 12/05 12/05
  • End installation 1/06 8/06
  • Project end 9/06 9/06

9
SEQUOIA a proposal for high-resolution
Principal Investigator Steve Nagler Instrument
Scientist Garrett Granroth Early identification
should allow much better optimization of design
for ARCS
10
(No Transcript)
11
Costs
  • Methods for cost reporting and tracking of the
    baseline schedule are being developed at Argonne
    with SNS personnel
  • Preliminary costs through August 2002 for the
    instrument effort
  • Caltech Hardware for prototype testing
  • Costs 89,600
  • Commitments 23,900
  • Oak Ridge Personnel (instrument scientist
    shielding calculations)
  • Costs 176,300
  • Argonne Personnel (engineer designer
    technician)
  • Costs 307,200
  • Current budget through August
  • Materials 90,700 Actual - 113,500
  • Work 444,900 Actual - 483,500
Write a Comment
User Comments (0)
About PowerShow.com