Title: Rim Joist Track Installation


1
Rim Joist Track Installation
  • The 5.5 inch metal rim joist track is installed
    around the upper interior wall perimeter.
  • This is the support attachment for the second
    story flooring and eliminates door window wall
    headers.

2
Double 2 x 6 Rim Joist is installed within the
metal Rim Joist track Time required 2 hours.
3
Interior Wall Framing
  • Bathroom, Kitchen and Bedroom pre-framed walls
    are secured to floor and wall framing members
    before placement of end wall.
  • Time required two men three hours.

4
Final Wall Panel Placement.
  • Panels meet in final corner to close the wall
    framing.
  • Outside view of the four foot window module.
  • Time required to frame exterior walls two men
    three hours.

5
Completed Interior Exterior Walls
  • Exterior and interior walls are placed and
    secured to bottom tracks.
  • Total time to this point Two men 16 hours.

6
Second Floor Framing
2x6 framing members placed 24 inches on center
for Second floor.
7
Second floor sheathing
  • Second floor framed and sheathed( ¾ inch plywood
    sub flooring)
  • Roof track placed around perimeter of second
    floor.