Title: Kein Folientitel


1
Max-Planck Institut für Plasmaphysik
Status of WENDELSTEIN 7-X Construction F.
Schauer on behalf of the W7-X team Max-Planck-Inst
itut für Plasmaphysik, Euratom Association,
D-17491 Greifswald
  • Overview
  • In-vessel components
  • Plasma vessel
  • Magnet system
  • Outer vessel
  • Ports
  • Assembly of the basic device
  • Periphery
  • Project issues

24th Symposium on Fusion Technology (SOFT24),
Warsaw September 12, 2006
2
WENDELSTEIN 7-X Overview - technical data
Major radius 5.5 m Minor radius 0.53
m Plasma volume 30 m3 Non-planar coils
50 Planar coils 20 Number of ports 299 Rot.
transform 5/6 - 5/4 Induction on axis max.
3T Stored energy 620 MJ (nom.) 660 MJ
(max.) Heating power 15 - 30 MW Pulse length
30 min Machine height 4.5 m Maximal diameter
16 m Machine mass 725 t Cold mass 392
t W7-X symmetry 5 identical modules Module
symmetry 2 flip-symmetrical halfs
3
WENDELSTEIN 7-X In-vessel components
  • target elements (10 MW/m2)
  • baffles (1.0 MW/m2)
  • wall protection (0.2 MW/m2)
  • control coils
  • cryo pumps
  • instrumentation and diagnostics
  • about 1 Million parts

4
WENDELSTEIN 7-X In-vessel components - divertor
10 separate divertor units consisting of targets
and baffles, 2 in each of the 5 modules
5
WENDELSTEIN 7-X In-vessel components - divertor
target module
Target
Baffle Max. P/A 10 MW/m2
1 MW/m2 Total area 19 m2
5.6 m2 Modules No. 100
20 Elements No. 890 240
Material CFC-tiles, Cu (AMC)
graphite Heat sink CuCrZr CuCrZr
Fixation HIP, EBW clamped
CFC Snecma, France Target elements Plansee,
Austria
See also poster J. Boscary
6
WENDELSTEIN 7-X In-vessel components status of
manufacture
  • Targets
  • First target element prototypes tested to 12
    MW/m² in GLADIS test facility (at IPP)
    Flaws detected at interface between CFC
    tiles and heat sink Improved elements
    expected in October (Plansee, Austria)
  • Baffles Being fabricated in the
    workshops of IPP Garching ?15 finished
  • Wall protection Graphite shield
    fabricated at IPP Garching, ?20
    finished
  • Double-walled steel panels fabricated by
    MAN DWE, ?25 finished
  • Control coils Production started at
    Babcock Noell comp. (BNG) First coil
    delivered in October
  • Cryopumps
  • Fabricated at IPP Garching, ?25 finished
  • Piping, feedthrough, supports, flanges
  • Fabrication starting at IPP Garching,
    prototypes built, procedures qualified

See also poster Füllenbach
7
WENDELSTEIN 7-X Plasma vessel
Close tolerances
  • volume 110 m3
  • surface 200 m2
  • mass 33 t 15 t
  • vacuum lt 10-8 mbar
  • baking up to 150 C
  • tolerances ? 2 mm (narrow areas)

See also presentation Cardella/Reich, and poster
Koppe
8
WENDELSTEIN 7-X Plasma vessel plasma vessel
Plasma vessel sectors (MAN DWE)
  • Plasma vessel (PV) is built up from rings
  • Each half-module delivered in two sectors
  • Both sectors connected after threading on
    coil 3 (middle coil of half-module)

9
WENDELSTEIN 7-X Plasma vessel thermal insulation
  • Al-coated glass fibre panel with MLI
  • Cu-braids for connection to
  • He-cooling pipe
  • MLI 20 layers of crinkled, Al-coated
    Kapton foil

(MAN DWE)
Thermal insulation on a vacuum vessel sector
10
WENDELSTEIN 7-X Plasma vessel status of
manufacture
  • Plasma vessel Manufacture of all half-module
    sectors completed
  • One half-module finished after assembly of coil
    no. 3
  • First half-module thermally insulated (thermal
    insulation is performed step by step in
    accordance with coil assembly)
  • Magnetic diagnostics (Rogowski and saddle coils)
    is mounted on one module

11
WENDELSTEIN 7-X Magnet system
  • magn. field on plasma axis 2.5 T (max. 3T)
  • magn. field at conductor max. 6.8 T
  • magnetic energy 620 MJ (standard)
  • 660 MJ (high iota)
  • 50 non-planar coils 5 types
  • 20 planar coils 2 types
  • CIC sc cable 243 strands
    Cu/NbTi-ratio ? 2.5
  • void fraction ? 37
  • operated at gt3.4 K

See also presentation Wanner, and posters
Schröder, Köppen, Birus, Bykov, Egorov, Feist
12
WENDELSTEIN 7-X Magnet system - coils
13
WENDELSTEIN 7-X Magnet system non-planar coil
production
Overview of Production hall (BNM, Zeitz)
Winding pack and casing (Winding ABB, Ansaldo
casing Österby, Sweden)
  • Winding pack built up of 6 double-layers
  • 18 turns per double-layer (one cable length)

14
WENDELSTEIN 7-X Magnet system non-planar coil
production
Coil AAB18
copper stripes
casing
  • Cooling by 2 He-loops in parallel,
  • with 2 turns each in series
  • Thermal contact via copper stripes

embedding
cooling channel
winding pack
15
WENDELSTEIN 7-X Magnet system non-planar coil
production
Required coil accuracy ?B/B00 lt 2?10-4,
corresponding to 2 mm for manufacturing and
assembly
16
WENDELSTEIN 7-X Magnet system planar coil
production
Planar Coil (Tesla, UK)
  • Same superconductor as with NPC
  • Winding pack built up from 3 double-layers
  • 12 turns per double-layer (one cable length)
  • Bolted casings, reinforced with 300 - 400
    shear pins per coil
  • Casing cooling by 1 cooling loop contacted
    via Cu-plates to housing

17
WENDELSTEIN 7-X Magnet system Cryogenic tests
on coils
  • Test facility at CEA Saclay, France
  • 2 cryostats for 2 coils each
  • Full current tests at 5 K
  • Quench test to check Ic-margin (min. 1st coil
    of each type)
  • Capacity about 2 coils per month

See also poster Ehmler
18
WENDELSTEIN 7-X Magnet system Paschen tests on
coils
  • It cannot be excluded that during W7-X
    operation Paschen minimum
  • conditions (breakdown voltage ?160 V at 0.3
    3 mbarmm) exist locally
  • Powerful tool to detect hidden insulation
    defects
  • Therefore all coils are tested under Paschen
    minimum conditions in air (between 0.001
    and 100 mbar) at 9.1 kV

Joint insulation failure detected by Paschen test
See also poster Petersen-Zarling
19
WENDELSTEIN 7-X Magnet system status of coil
production
  • Non-planar coils
  • Superconductor fabrication finished
  • All 50 winding packs finished
  • All 50 casings cast and complete
  • 38 coils embedded
  • 12 coils complete
  • 6 coils formally accepted
  • Short circuit detected in one coil termination
  • Suspicion of similar weakness in seven other
    coils,
  • necessity of repair being investigated
  • Systematic insulation defects in type 1 and 5
    coils being repaired
  • 1 coil assembled
  • Planar coils
  • all winding packs finished
  • 13 coils embedded
  • 8 coils complete
  • 3 coils formally accepted

20
WENDELSTEIN 7-X Magnet system bus bars
  • Superconducting bus-bar system connects
  • coils
  • coils and power supplies
  • bifilar winding of bus bar for coil type 1 to
    avoid error fields

Development and manufacture of bus-bar system by
Research Centre Jülich (FZJ)
21
WENDELSTEIN 7-X Magnet system bus bars
Bus bar connection at coil terminal
Status Bus bar fabrication started
Bus bar manufacture Weight support during
bending process using He-balloons
See also poster Rummel
22
WENDELSTEIN 7-X Magnet system central support
structure
  • Welded structure, 10 half-modules, supports
    the whole magnets system
  • Cooled by one cooling loop per half-module
  • Final machining before assembly guarantees
    exact interfaces
  • Total mass 72 t
  • Produced by ENSA, Spain

See also presentation Cardella/Reich
23
WENDELSTEIN 7-X Magnet system central support
structure
Inboard side
Outboard side
Trial assembly of 2 half-modules after precise
machining of flange interfaces (accuracy 0.1 mm)
at Rovera comp. (Italy)
See also poster Pilopp
24
WENDELSTEIN 7-X Magnet system coil support
elements
Central Support Elements (CSE) Narrow Support
Elements (NSE) Lateral Support Elements (LSE)
  • Central support elements
  • Coils are fixed by heavy inconel bolts to
    the central supporet structure (CSS)
  • Wedges against shoulders at the CSS-side
    flanges support shear forces and torque
  • Support for 5 Non-planar coil types
  • 6 CSE with 9 bolts M30 each
  • 2 CSE with 6 bolts M30 each
  • 1 CSE with 1 bolt M90
  • 1 CSE with 1 bolt M76
  • 2Support for 2 planar coil types
  • 4 CSE with 4 bolts M24 each

See also poster Damiani
25
WENDELSTEIN 7-X Magnet system coil support
elements
  • Cross section of a central support element with
    9 bolts M30
  • Bolts arranged in a 3x3 matrix
  • Inconel sleeves for increased elasticity
  • Superbolt nuts for controlled high pre-loading

See also poster Dudek
26
WENDELSTEIN 7-X Magnet system coil support
elements
  • Narrow Supports on inboard side
  • forces up to 1.5 MN
  • sliding contact (lt5 mm)
  • and tilting (lt1o).
  • Al-bronce pad with MoS2 layer
  • Counter-side sprayed with MoS2-spray
  • Lateral Supports on outboard side
  • Rigid (bolted/welded) connection
  • Planar Supports
  • (to fix planar coils on non-planar ones)
  • Two options available, to be decided
  • - sliding contact analogously to NSE- elastic
    joint

27
WENDELSTEIN 7-X Magnet system status of support
structure
  • Central support structure
  • First CSS module interface flanges machined
  • Cooling tubes being installed
  • Delivery of first module beginning of 2007
  • Central support elements
  • First prototype tested, second prototype test
    being prepared
  • Wedge welding being qualified
  • Inconel bolts ordered
  • Narrow support elements
  • Extensive development program close to
    completion
  • Production for first coil interfaces started
    (IPP workshops and sub-contractors)
  • Lateral support elements
  • Welded LSE design finished
  • Welding procedure qualified
  • Bolted HM-connection development close to
    completion

28
WENDELSTEIN 7-X Outer vessel
  • Outer vessel
  • Volume 525 m3
  • Surface 480 m2
  • Mass 170 t
  • Vacuum 10-6 mbar
  • Port dome openings 549

See also presentation Cardella/Reich
29
WENDELSTEIN 7-X Outer vessel
Outer vessel during pre-assembly (MAN DWE)
Thermal shield prototype (MAN DWE)
  • Status
  • 10 module half-shells welded
  • 10 half-shells have been milled
  • 4 half-shells equipped with about 70 of the
    domes/flanges
  • first module to be delivered until April 2007

30
WENDELSTEIN 7-X Ports
Port insulation prototype (MAN DWE)
OV MLI
Ports (Romabau-Gerinox AG, CH)
  • Status
  • 299 ports, 190 for diagnostics, 19 for heating,
  • 20 for pumping and 70 for divertor supply
  • 278 delivered
  • Final delivery in November 2006

port tube shield
port bellows shield
OV shield
See also posters Reich, Kunkel
31
WENDELSTEIN 7-X Assembly magnet modules
Mounting stand Ia magnet PV half-module
Mounting stand Ib flip-symmetric magnet
PV half-module
Mounting stand II magnet PV module
Experimental hall (final assembly)
Half-module mounting stands Ia and Ib
Metrology centre
See also poster Bräuer
32
WENDELSTEIN 7-X Assembly torus completion
5 magnet modules including bus system, plasma
vessel, and central support structure
Machine base, in-vessel components,
instrumentation, current feed-through, joints,
heating systems and diagnostics
Periphery (cooling, electrics, auxiliaries,
supplies)
33
WENDELSTEIN 7-X Assembly status
Assembly of coil AAB18 (type 3) on insulated
plasma vessel
NPC and PLC pre-assembly
34
WENDELSTEIN 7-X Periphery Power supply,
protection, current leads
  • Power supply
  • All seven units of coil power supplies
    delivered (ABB Switzerland) and accepted
  • Power supplies for control coils delivered
  • Protection
  • Nickel dump resistors delivered
  • Quench detection system being developed in
    cooperation with FZK
  • Prototype electronics successfully tested in
    stray field
  • Current leads
  • 7 pairs required
  • Maximal design current 18.2 kA
  • Upside-down operation
  • High temperature superconductor at ?50 K
  • Development, manufacture, and test contract with
    FZK

See also posters Hartmann, Schacht, Laqua, Spring
35
WENDELSTEIN 7-X Periphery Refrigeration system
  • Status
  • Production on time
  • (Linde Kryotechnik, CH)
  • Comissioning end of 2008

Layout refrigerator hall
Split cold-box
36
WENDELSTEIN 7-X Periphery ECRH
10MW, 140GHz cw system
View into the transmission duct
TED
CPI
TED
W7-X Gyrotrons 1 MW, cw each (Forschungszentrum
Karlsruhe, FZK)
Full performance demonstrated TED Gyr. 920 kW
for 30 min CPI Gyr. 900 kW for 30 min
  • Status
  • 5 out of 10 gyrotrons delivered
  • Optical transmission lines up to torus hall
    completed, most loaded section tested

See also poster Braune
37
WENDELSTEIN 7-X Projcet issues - Site
38
WENDELSTEIN 7-X Projcet issues - Personnel
History und Plan
Status September 2006
Additional 17 contracted from companies
20 IPP Garching 10 inspectors/advisors
20 FZJ 25 FZK and IPF Stuttgart Plan
2007 Assembly personnel will be contracted
from industry
39
WENDELSTEIN 7-X Projcet issues Schedule
  • Schedule endangered due to coil quality
    problems (mainly defective HV insulation and
    interturn faults)
  • Acceleration measures considered
  • Second coil test facility
  • Second assembly line up to mounting stand II