Nadcap and Export Control (rev 2)
  • DonB
  • Export Control Roundtable
  • Pittsburgh, PA
  • July 24, 2008 Allegheny Room
  • 100 PM 430 PM

2
Attendees
  • The following people attended in person on via
    phone

3
Purpose of the Roundtable
  • Encourage greater understanding of the challenges
    and approaches we (PRI) are taking on behalf of
    the Nadcap process to ensure 100 compliance with
    the regulations (ITAR/EAR)
  • To encourage dialogue among primes suppliers, and
    PRI Staff on the subject of EC

4
Topics
  • New definition EC-LR/Restricted
  • New form to report EC-LR/Restricted materials to
    PRI
  • Explanation of the PRI TAA licensing process via
    a flow chart
  • Other licensing alternatives
  • Auditor input of data in eAuditNet on
    EC-LR/Restricted parts
  • New WEB pages
  • Open discussion other issues

5
EC-LR/Restricted definition
  • All Defense Articles and Technical Data
    controlled by the ITAR

6
EC-LR/Restricted definition
  • All Defense Articles and Technical Data
    controlled by the ITAR any foreign origin
    Defense Articles and Technical Data that would be
    controlled by the ITAR if of U.S. origin

7
EC-LR/Restricted definition
  • All Defense Articles and Technical Data
    controlled by the ITAR any foreign origin
    Defense Articles and Technical Data that would be
    controlled by the ITAR if of U.S. origin any
    dual-use or civil items or Technology controlled
    by the EAR under any ECCN except EAR99

8
EC-LR/Restricted definition
  • All Defense Articles and Technical Data
    controlled by the ITAR any foreign origin
    Defense Articles and Technical Data that would be
    controlled by the ITAR if of U.S. origin any
    dual-use or civil items or Technology controlled
    by the EAR under any ECCN except EAR99 and
    includes any foreign origin dual-use or civil
    items or Technology that would be controlled by
    the EAR under any ECCN except EAR99 if of U.S.
    origin.

9
New form to report EC-LR/restricted materials
  • Once the supplier has signed the supplier
    agreement in eAuditNet, the following question
    must be answered

When you click here
This is scheduled to be in place in the 4th qtr
2008
10
EC-LR form
  • Suppliers are to complete the data on this form
    to start the licensing process

11
PRI TAA Licensing process
12
Other licensing Processes Volvo approach
  • Volvo approach - supplier approaches primes to
    modify their initial MLAs TAAS to include the
    Nadcap audit
  • PRI to determine what auditors Staff Engineers
    would be involved in the Nadcap audits at the
    supplier
  • PRI to send personnel data to supplier (personal
    data sheet NDA copy passport)
  • Supplier coordinates with primes to amend MLAs
    TAAs

13
Other licensing Processes Volvo approach
  • Prime submits amended license request to
    appropriate government agency
  • Once authorized - PRI would coordinate any PRI
    personnel sign offs needed back to prime
  • Once License secured copy to PRI for posting in
    eAuditNet coordination with all applicable PRI
    personnel
  • Next audit licensed items and materials can be
    subject to the Nadcap audit

Thanks to Chet Date Honeywell who is piloting
this approach with their company
14
Other licensing Processes New Licenses
  • Prime coordinates with PRI on upcoming licenses
    which will be submitted for approval by
    government agency
  • PRI provides personnel data and verbiage to prime
    to include the Nadcap audit in the license
  • Prime submits PRI personnel and the Nadcap audit
    to the Governmental agency as part of the initial
    authorization to export the materials

15
Other licensing Processes New Licenses
  • Once authorized - PRI would coordinate any PRI
    personnel sign offs needed back to prime
  • Once License secured copy to PRI for posting in
    eAuditNet coordination with all applicable PRI
    personnel
  • Next audit licensed items and materials can be
    subject to the Nadcap audit

16
3 Licensing Options listed in order of
desirability
  • Include PRI (auditors Staff) on initial
    licenses to export EC-LR/Restricted items
  • Get it done up front cleanest no impact on
    audit schedules. PRI provide data on personnel.
  • Amend existing Licenses
  • Use when there are 2 or less primes with EC-LR
    items at a supplier. Primes will have to agree -
    much coordination between Export Control Depts
    prime Quality personnel PRI. PRI provide data
    on personnel.
  • Get PRI TAA -
  • Used when we have more than 2 primes involved.
    Covers all EC-LR/Restricted items at a supplier
    good for 10 years NOTE Possible downside -
    supplier may still have to secure re transfer
    authorization

17
Response/discussion
  • How do you (primes and suppliers) react to the 2
    additional ways to get the Nadcap audit licensed?
  • Are you willing to help resolve the EC issues we
    have in the Nadcap process by one of these means?
  • What does PRI need to know about this process
    (from primes standpoint)? What data would you
    need from PRI to get your licenses amended?

18
Auditor input
  • Checklists have been/are being identified with an
    (EC) for those questions where detailed data
    cannot be input into eAuditNet (see example next
    page)

19
(No Transcript)
20
Auditor Input
  • Auditors to not display technical details in
    writing up ncrs on EC-LR/Restricted materials

21
Audit Status
  • PRI has generated a report which identifies
    audits which must have action (Licensing) before
    the next audit due date
  • In response to additional requests from primes,
    PRI is working on a new report

22
Audit Status
  • New report will outline suppliers whose next
    audit will involve the work around

23
New WEB page
  • Export Control page on PRI/Nadcap web
  • http//www.pri-network.org/PRI/
  • Nadcap
  • About Nadcap
  • Export Control (http//www.pri-network.org/Nadc
    ap/Export-Control.id.879.htm)

24
(No Transcript)
25
(No Transcript)
26
Questions?
  • Don Buehler
  • donb_at_sae.org
  • 513-662-5190 (phone)
  • 513-305-7493 (cell)

27
Notes from the meeting
  • We reviewed the definition of EC-LR/Restricted
    quite extensively in the mtg.
  • NOTE a basic question which came up during the
    meeting has now been resolved see embedded word
    file for the situation
  • Page 22 work around list - we reviewed this
    committed to getting it to primes by August 8th.
    Note there was no discussion nor commitment on
    the part of PRI to this being a regular report.
  • During the licensing discussions it was noted
    that many primes do not license individual part
    numbers that they license sub systems and
    generally described components.
  • NOTE even though this was not directly
    discussed as part of the Roundtable it became
    apparent to DonB that 1- the approach to
    licensing by part number is not the best way to
    proceed and 2 due to the terrible time we have
    getting the needed data from the suppliers
    (unless they physically have the licenses from
    the primes), the best way for PRI to proceed get
    the data needed for the PRI TAAS is to go
    directly to the primes.
  • This new approach will be outlined in a letter to
    the primes NMC reps recounting the proposed
    approaches discussed during the Roundtable and
    proposing this addition al approach.