Title: Three Rivers Levee Improvement Authority Cash Flow Projection for Existing and Future RightofWay and
1Three Rivers Levee Improvement AuthorityCash
Flow Projection for Existing and Future
Right-of-Way and Project ExpendituresMarch 22,
2007
2Outline
- Project Overview
- Project Timeline/Schedule
- Real Estate/Right of Way
- Overview
- Existing actions still pending
- Feather River Segment 1 3
- Feather River Segment 2 (setback)
- Project Revenues (existing planned future) and
Total Expenditures - Key Expenditures and Anticipated cash flow
3TRLIA Work by Phase
- Phase 1 (red) Yuba
- Phase 2 (green) Yuba, Western Pacific
Interceptor Canal, and Bear - Phase 3 (purple) Bear Setback
- Phase 4 (blue) Yuba, and Feather River
4Phase 4 - Feather River includingSetback Levee
Segment 3
- Achieves 200 Year Protection
- Approx. 13 miles
- Segments 1 3 strengthen-in-place
- Segment 2 setback with new levee
construction
Segment 2(Setback Levee)
Segment 1
5Design, Permitting, and ConstructionSchedule
6Right of Way Steps
- Engineering
- Plats and Legal Description
- Rights of Entry for Construction
- Appraisal
- Acquisition
- Relocation
7Right of Way (ROW) Steps
- Condemnation Phase
- Resolution of Necessity
- File Complaint in eminent domain court
- Deposit funds in State Treasury
- Property owner is served complaint
- Property owner may oppose motion (30 days)
- Project Responds to opposition (15 days)
- Hearing on Motion (45 days)
- Effective Order of Possession (30 days)
8Types of Acquisitions
- Permanent Easement
- Fee Title
- Temporary Construction Easement
- Flowage Easement
9Generic ROW Timeline
10Existing TRLIA ROW Acquisition
- Phase 1, 2, 3, 4-Yuba, and Olivehurst Det.
- 60 parcels affected
- 9 acquisitions still pending
- 6 are in litigation
- 3 are in negotiations
- TRLIA has already deposited Approx. 8.8 Million
for pending litigation - Additional 2 to 6.0 Million required to close 9
acquisitions between April and November. - Included in cash flows
11New TRLIA ROW Acquisition
- Phase 4 Feather Segments 1 3
- 25 parcels affected
- Mainly Temporary Rights
- Permanent Rights for stability berm
- Acquisitions complete in May 2007
- 1 million loaded in cash flow
12New TRLIA ROW Acquisition
- Phase 4 Segment 2
- 48 parcels, including multiple SSJDD
- 30 property owners
- Acquisition Stages
- Stage 1 North of Ella
- Stage 2 Ella to Anderson
- Stage 3 South of Anderson
- Stage 4 Setback Area
- Stage 5 Borrow Pit Areas
13(No Transcript)
14Project Revenues (existing future)and Total
Expenditures (in millions)
15Key Expendituresand Anticipated Cash Flow (in
millions)
16Three Rivers Levee Improvement AuthorityMarch
22, 2007
17(No Transcript)
18(No Transcript)
19Additional Right of Way Gantt charts
20Segment 2 ROWSchedule
Stage 1 North of Ella 4 Private Owners
21Segment 2 ROWSchedule
Stage 2 Ella to Anderson 6 Private Owners
22Segment 2 ROWSchedule
Stage 3 South of Anderson 8 Private Owners
23Segment 2 ROWSchedule
Stage 4 5 Setback Area Borrow Pits 13
Owners