File Complaint in eminent domain court. Deposit funds in State Treasury. Property owner is served complaint. Property owner may oppose motion ( 30 days) ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 24
Provided by: tomen
Category:

less

Transcript and Presenter's Notes

Title: Three Rivers Levee Improvement Authority Cash Flow Projection for Existing and Future RightofWay and


1
Three Rivers Levee Improvement AuthorityCash
Flow Projection for Existing and Future
Right-of-Way and Project ExpendituresMarch 22,
2007
2
Outline
  • Project Overview
  • Project Timeline/Schedule
  • Real Estate/Right of Way
  • Overview
  • Existing actions still pending
  • Feather River Segment 1 3
  • Feather River Segment 2 (setback)
  • Project Revenues (existing planned future) and
    Total Expenditures
  • Key Expenditures and Anticipated cash flow

3
TRLIA Work by Phase
  • Phase 1 (red) Yuba
  • Phase 2 (green) Yuba, Western Pacific
    Interceptor Canal, and Bear
  • Phase 3 (purple) Bear Setback
  • Phase 4 (blue) Yuba, and Feather River

4
Phase 4 - Feather River includingSetback Levee
Segment 3
  • Achieves 200 Year Protection
  • Approx. 13 miles
  • Segments 1 3 strengthen-in-place
  • Segment 2 setback with new levee
    construction

Segment 2(Setback Levee)
Segment 1
5
Design, Permitting, and ConstructionSchedule



6
Right of Way Steps
  • Engineering
  • Plats and Legal Description
  • Rights of Entry for Construction
  • Appraisal
  • Acquisition
  • Relocation

7
Right of Way (ROW) Steps
  • Condemnation Phase
  • Resolution of Necessity
  • File Complaint in eminent domain court
  • Deposit funds in State Treasury
  • Property owner is served complaint
  • Property owner may oppose motion (30 days)
  • Project Responds to opposition (15 days)
  • Hearing on Motion (45 days)
  • Effective Order of Possession (30 days)

8
Types of Acquisitions
  • Permanent Easement
  • Fee Title
  • Temporary Construction Easement
  • Flowage Easement

9
Generic ROW Timeline
10
Existing TRLIA ROW Acquisition
  • Phase 1, 2, 3, 4-Yuba, and Olivehurst Det.
  • 60 parcels affected
  • 9 acquisitions still pending
  • 6 are in litigation
  • 3 are in negotiations
  • TRLIA has already deposited Approx. 8.8 Million
    for pending litigation
  • Additional 2 to 6.0 Million required to close 9
    acquisitions between April and November.
  • Included in cash flows

11
New TRLIA ROW Acquisition
  • Phase 4 Feather Segments 1 3
  • 25 parcels affected
  • Mainly Temporary Rights
  • Permanent Rights for stability berm
  • Acquisitions complete in May 2007
  • 1 million loaded in cash flow

12
New TRLIA ROW Acquisition
  • Phase 4 Segment 2
  • 48 parcels, including multiple SSJDD
  • 30 property owners
  • Acquisition Stages
  • Stage 1 North of Ella
  • Stage 2 Ella to Anderson
  • Stage 3 South of Anderson
  • Stage 4 Setback Area
  • Stage 5 Borrow Pit Areas

13
(No Transcript)
14
Project Revenues (existing future)and Total
Expenditures (in millions)

15
Key Expendituresand Anticipated Cash Flow (in
millions)
16
Three Rivers Levee Improvement AuthorityMarch
22, 2007
17
(No Transcript)
18
(No Transcript)
19
Additional Right of Way Gantt charts
20
Segment 2 ROWSchedule
Stage 1 North of Ella 4 Private Owners


21
Segment 2 ROWSchedule
Stage 2 Ella to Anderson 6 Private Owners


22
Segment 2 ROWSchedule
Stage 3 South of Anderson 8 Private Owners


23
Segment 2 ROWSchedule
Stage 4 5 Setback Area Borrow Pits 13