Title: Surprises and Solutions When Driving Piles in Mountain Valleys of Vermont
1Surprises and Solutions When Driving Piles in
Mountain Valleys of Vermont
- Christopher C. Benda, P.E, VTrans
- John E. Lens, P.E., GeoDesign, Inc.
2Outline
- Introduction
- Design and Construction Approach
- 4 Short Pile Driving Overrun Stories
- Common Characteristics in Overruns
- Why These Matter
- Solutions
3Introduction
- Problem
- Environment/geology
- Exploration Difficulties
4Design and Construction Approach
- Explorations Advanced using rotary wash boring
techniques - Minimum of 1 boring per foundation element
- SPT testing
- Continuous sampling on first boring to 30 feet
- 5 foot intervals thereafter
- Typically to bedrock
- Unless SPT N gt100 for a depth of 20 feet
- 10 foot rock cores
- Lab testing conducted on soil and rock samples
- Field logs combined with lab classification and
geologists assessment - gINT logs generated and incorporated into project
plans
5Design and Construction Approach
- Soil profile developed
- Pile lengths estimated using Driven 1.2
- Nordlund-side friction
- Thurman-end bearing
- Meyerhof-limiting end bearing
- Soil properties estimated from correlations with
N values and profile - Box perimeter for side friction
- Cross sectional area for end bearing
- Cast shoes not considered in analysis
- Driveability analysis using GRLWeap
6Design and Construction Approach
- PDA testing specified
- Dense soils or boulders
- Side Friction
- Pile Driving Analyzer (PDA)
- Approved consultants
- Hired by contractor
- Submittals
- Pile Driving Equipment Data Form
- Wave equation analysis for preliminary driving
criteria - Capacity on plans
- Subsurface information
- Pile
- Equipment
- Estimated length
7Design and Construction Approach
- System inspection
- PDA testing conducted at first pile on each
foundation unit - Saximeter provided by contractor
- Stroke on OED
- Hammer blows
- Restrike at 48 hours
- CAPWAP analysis
- Criteria for remaining piles established
8Vermont Sites
9Cofferdam Pile Driving
10Lyndon Project
11Lyndon Project
- 80 integral abutment bridge
- 5 HP14x102 per abutment
- 20 loose to dense granular fill
- Medium to very dense gravely sand (Ngt50) with
scattered cobbles and boulders - 10 to 20 silt content
- Bedrock between 138 and 155 feet
12Lyndon Total Skin Friction
13Huntington
14Huntington
15Huntington
- 188 2-span curved girder bridge
- Conventional pile foundations
- 40 feet of dense to very dense sands, sandy silts
and silts - Boulders and cobbles with very dense sandy gravel
horizons to 82 feet - Abutment 2 similar w/o boulders
- Borings terminated 60-100 feet below footing
elevation
16Bristol
17Bristol
- 144 integral abutment bridge
- 5-HP 14X102 piles per abutment
- 20 of cobbles and boulders
- Medium dense to dense sandy silt
- More boulders at 65
- Borings terminated 90 -100 feet in boulders
18Bolton
19Bolton
- Rehabilitation of a pair of 5-span bridges
- Replacement of pier 2-NB and pier 3-SB
- Existing piers 2 on HP10X42 and timber piles
- Continuous structure fixed at new piers
- Design called for 12 ¾ pipe piles
- Changed to HP12X53
20Bolton
- 30 of medium dense silt, 20 feet of medium dense
sandy silt with gravel - Very dense sands and gravels to 170 feet
- 20 foot boulder layer encountered at piers at
135
21Bolton Baffle Plate
22Bolton Pier 2 Dynamic Testing Results
23Predicted and Actual Pile Lengths on Case History
Projects
24Common Characteristics Piles/Driving
- H-Piles (HP12x53, HP12x74, HP14x102)
- Piles from 50-151 feet long
- Single Acting Diesel Hammers (40-55,000
foot-pound rated energy) - 5 to 20 piles per pier/abutment
25Common Characteristics - Soils
- SPT N-values 40 to 100
- Sometimes Frequent Cobbles/Boulders but not
always - Silt trace to 25
- Gravelly Sands
- Glacial Tills
26Implications
- Cannot rely on boring refusals for piles
- Need to drill to bedrock to find end bearing
- ??s for Integral Abutment Bridges
- Time Added Project Costs
27Solutions
- Two Tiered Design Approach
- Expand the pile performance database
- Improve prediction skills
28Expand Pile Performance Database
- Standardize driving monitoring/records
- Increase PDA monitoring emphasis
- Share findings (especially DOTs)
29Improve Prediction Skills
- Existing analytical methods
- Myerhof
- Nordlund
- Tomlinson
30Back-calculated Skin Friction
31Consider Displacement Piles
- Concrete filled pipe piles
- Tapered piles
32Summary
- H-piles overruns
- Problematic geologic conditions
- Design implications integral abutments
- Design and construction based response
- Opportunity for a collaboration forum
33Acknowledgements
- Vermont Agency of Transportation
- GeoDesign, Inc.
- Michael Deery GZA GeoEnvironmental
34Thank You!
- VT Agency of Transportation vt.gov
- GeoDesign, Inc. geodesign.net