Surprises and Solutions When Driving Piles in Mountain Valleys of Vermont - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Surprises and Solutions When Driving Piles in Mountain Valleys of Vermont

Description:

Surprises and Solutions When Driving Piles in Mountain Valleys of Vermont – PowerPoint PPT presentation

Number of Views:129
Avg rating:3.0/5.0
Slides: 35
Provided by: utah5
Category:

less

Transcript and Presenter's Notes

Title: Surprises and Solutions When Driving Piles in Mountain Valleys of Vermont


1
Surprises and Solutions When Driving Piles in
Mountain Valleys of Vermont
  • Christopher C. Benda, P.E, VTrans
  • John E. Lens, P.E., GeoDesign, Inc.

2
Outline
  • Introduction
  • Design and Construction Approach
  • 4 Short Pile Driving Overrun Stories
  • Common Characteristics in Overruns
  • Why These Matter
  • Solutions

3
Introduction
  • Problem
  • Environment/geology
  • Exploration Difficulties

4
Design and Construction Approach
  • Explorations Advanced using rotary wash boring
    techniques
  • Minimum of 1 boring per foundation element
  • SPT testing
  • Continuous sampling on first boring to 30 feet
  • 5 foot intervals thereafter
  • Typically to bedrock
  • Unless SPT N gt100 for a depth of 20 feet
  • 10 foot rock cores
  • Lab testing conducted on soil and rock samples
  • Field logs combined with lab classification and
    geologists assessment
  • gINT logs generated and incorporated into project
    plans

5
Design and Construction Approach
  • Soil profile developed
  • Pile lengths estimated using Driven 1.2
  • Nordlund-side friction
  • Thurman-end bearing
  • Meyerhof-limiting end bearing
  • Soil properties estimated from correlations with
    N values and profile
  • Box perimeter for side friction
  • Cross sectional area for end bearing
  • Cast shoes not considered in analysis
  • Driveability analysis using GRLWeap

6
Design and Construction Approach
  • PDA testing specified
  • Dense soils or boulders
  • Side Friction
  • Pile Driving Analyzer (PDA)
  • Approved consultants
  • Hired by contractor
  • Submittals
  • Pile Driving Equipment Data Form
  • Wave equation analysis for preliminary driving
    criteria
  • Capacity on plans
  • Subsurface information
  • Pile
  • Equipment
  • Estimated length

7
Design and Construction Approach
  • System inspection
  • PDA testing conducted at first pile on each
    foundation unit
  • Saximeter provided by contractor
  • Stroke on OED
  • Hammer blows
  • Restrike at 48 hours
  • CAPWAP analysis
  • Criteria for remaining piles established

8
Vermont Sites
9
Cofferdam Pile Driving
10
Lyndon Project
  • Bridge Photo

11
Lyndon Project
  • 80 integral abutment bridge
  • 5 HP14x102 per abutment
  • 20 loose to dense granular fill
  • Medium to very dense gravely sand (Ngt50) with
    scattered cobbles and boulders
  • 10 to 20 silt content
  • Bedrock between 138 and 155 feet

12
Lyndon Total Skin Friction
13
Huntington
14
Huntington
15
Huntington
  • 188 2-span curved girder bridge
  • Conventional pile foundations
  • 40 feet of dense to very dense sands, sandy silts
    and silts
  • Boulders and cobbles with very dense sandy gravel
    horizons to 82 feet
  • Abutment 2 similar w/o boulders
  • Borings terminated 60-100 feet below footing
    elevation

16
Bristol
17
Bristol
  • 144 integral abutment bridge
  • 5-HP 14X102 piles per abutment
  • 20 of cobbles and boulders
  • Medium dense to dense sandy silt
  • More boulders at 65
  • Borings terminated 90 -100 feet in boulders

18
Bolton
19
Bolton
  • Rehabilitation of a pair of 5-span bridges
  • Replacement of pier 2-NB and pier 3-SB
  • Existing piers 2 on HP10X42 and timber piles
  • Continuous structure fixed at new piers
  • Design called for 12 ¾ pipe piles
  • Changed to HP12X53

20
Bolton
  • 30 of medium dense silt, 20 feet of medium dense
    sandy silt with gravel
  • Very dense sands and gravels to 170 feet
  • 20 foot boulder layer encountered at piers at
    135

21
Bolton Baffle Plate
22
Bolton Pier 2 Dynamic Testing Results
23
Predicted and Actual Pile Lengths on Case History
Projects
24
Common Characteristics Piles/Driving
  • H-Piles (HP12x53, HP12x74, HP14x102)
  • Piles from 50-151 feet long
  • Single Acting Diesel Hammers (40-55,000
    foot-pound rated energy)
  • 5 to 20 piles per pier/abutment

25
Common Characteristics - Soils
  • SPT N-values 40 to 100
  • Sometimes Frequent Cobbles/Boulders but not
    always
  • Silt trace to 25
  • Gravelly Sands
  • Glacial Tills

26
Implications
  • Cannot rely on boring refusals for piles
  • Need to drill to bedrock to find end bearing
  • ??s for Integral Abutment Bridges
  • Time Added Project Costs

27
Solutions
  • Two Tiered Design Approach
  • Expand the pile performance database
  • Improve prediction skills

28
Expand Pile Performance Database
  • Standardize driving monitoring/records
  • Increase PDA monitoring emphasis
  • Share findings (especially DOTs)

29
Improve Prediction Skills
  • Existing analytical methods
  • Myerhof
  • Nordlund
  • Tomlinson

30
Back-calculated Skin Friction
31
Consider Displacement Piles
  • Concrete filled pipe piles
  • Tapered piles

32
Summary
  • H-piles overruns
  • Problematic geologic conditions
  • Design implications integral abutments
  • Design and construction based response
  • Opportunity for a collaboration forum

33
Acknowledgements
  • Vermont Agency of Transportation
  • GeoDesign, Inc.
  • Michael Deery GZA GeoEnvironmental

34
Thank You!
  • VT Agency of Transportation vt.gov
  • GeoDesign, Inc. geodesign.net
Write a Comment
User Comments (0)
About PowerShow.com