Using%20Earned%20Value%20(EV)%20for%20better%20management%20of%20software%20projects - PowerPoint PPT Presentation

About This Presentation
Title:

Using%20Earned%20Value%20(EV)%20for%20better%20management%20of%20software%20projects

Description:

The Schedule Tracking give information on the amount of schedule that has been ... The very usage of Earned Value in projects improves the quality of planning, ... – PowerPoint PPT presentation

Number of Views:112
Avg rating:3.0/5.0
Slides: 15
Provided by: Tath
Category:

less

Transcript and Presenter's Notes

Title: Using%20Earned%20Value%20(EV)%20for%20better%20management%20of%20software%20projects


1
Using Earned Value (EV) for better management of
software projects
  • Tathagat Varma
  • Engineering Manager,
  • Huawei Technologies India Pvt. Ltd.
  • Bangalore, India

2
Disclaimer
  • The views represented in this presentation are
    authors own personal views and do not
    necessarily represent the views of his employers
  • All facts, data, research material referenced
    from the Internet web sites is gratefully
    acknowledged to the site addresses to highlight
    its ownership

3
Metrics for Project Management
  • By and large, everyone agrees that we need to
    measure !
  • There is a plethora of software metrics
  • The general tendency for a organization starting
    to use metrics is to collect as much as
    possible
  • This leads to confusion and loss of mission /
    purpose no one knows for whom the metrics are
    meant to be
  • The key is to use as few metrics as possible, but
    put them in closed-loop management

4
Major Parameters to track
  • Schedule
  • Productivity
  • Effort / Cost
  • Review Effort
  • Review Efficiency
  • Rework Effort
  • Test Effort
  • Pre-release Defect Density
  • Post-release Defect Density
  • ...

5
Problems
  • Schedule Tracking
  • In conventional methods, we track the schedule in
    WBS / Gantt chart
  • The Schedule Tracking give information on the
    amount of schedule that has been spent, but can
    never correctly predict the remaining amount of
    schedule really needed to complete the project
  • The task granularity is often very large
    resulting in ineffective scheduling and tracking
  • Effort / Cost Tracking
  • Often, this is tracked separately - there is no
    real correlation with the traditional schedule
    tracking
  • Often, the effort already spent can not be
    well-utilised to predict the effort remaining for
    remaining tasks

6
Proposal Solution
  • Use Earned Value as the metrics for tracking
    schedule and cost
  • Earned Value is a derived metrics that needs
    basic project measurements that are normally
    collected planned and actual schedule, planned
    and actual effort / cost, etc.
  • However, it is the predictive capability of
    Earned Value metric that really helps us improve
    the visibility and control of a software project

7
Earned Value
  • From www.earnedvalue.com
  • Earned Value is a program management technique
    that uses "work in progress" to indicate what
    will happen to work in the future. Research shows
    that projects that are over budget when only 15
    percent finished usually post overruns at
    completion. Similarly, research shows that actual
    completion costs will not improve by more that 10
    of the current percentage overrun. This
    statistic highlights the need for early and
    disciplined review of current project status
    throughout the life of a project.

8
Earned Value Graph
  • http//www.projectmagazine.com/nov00/evm1.html

9
Benefits of Earned Value
  • More granular estimation, planning, scheduling
    and tracking gt Improved project performance
  • Get the difference between effort and
    progress very clear
  • Focus on big picture gt Management by exception
  • Prediction of Cost and Schedule variance at the
    completion

10
Disadvantages / Cost of Earned Value
  • Difficult concept takes a higher order of
    project management capabilities to effectively
    deploy an EVM system
  • May not be very suited for very small projects

11
Conclusions
  • Earned Value system does not suffer from the
    problems that traditional schedule tracking has
  • The very usage of Earned Value in projects
    improves the quality of planning, scheduling,
    tracking and reporting
  • Earned Value is a standard concept in
    multi-site / global projects, it is uniquely
    understood irrespective of the geographic
    location of the site
  • Earned Value chart is very simple and effective
    way to inform the Senior Management on the
    project progress

12
Web References
  • NASA Website on Earned Value Management
    (http//evm.nasa.gov/)
  • Earned Value Calculations in Microsoft Project 98
    (support.microsoft.com/default.aspx?scid/support/
    project/content/prj98/EValCalcs.asp)
  • Earned Value for RD-Type Projects
    (evm.larc.nasa.gov/EV_Overview.ppt)
  • Using Earned Value to Manage Successful Software
    Projects, Paul J. Solomon (http//www.qaiindia.com
    /SEPG_minisite/Past_papers/pdf_files/Northrop_USIN
    G_EARNED_VALUE.pdf)
  • Earned Value Management Maturity Model
    (http//www.mgmt-technologies.com/evmtech.html)

13
Questions ?
14
Thank you !!!
Write a Comment
User Comments (0)
About PowerShow.com