Seismic Rehabilitation of Extreme SoftStory School Building with Friction Dampers Using the ASCE 41 - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Seismic Rehabilitation of Extreme SoftStory School Building with Friction Dampers Using the ASCE 41

Description:

Presented by: Paul E. Oyen. Overview. Description of Building. Project Background ... Following the 1994 Northridge Earthquake, the soft-story condition is identified ... – PowerPoint PPT presentation

Number of Views:466
Avg rating:3.0/5.0
Slides: 15
Provided by: PEO1
Category:

less

Transcript and Presenter's Notes

Title: Seismic Rehabilitation of Extreme SoftStory School Building with Friction Dampers Using the ASCE 41


1
Seismic Rehabilitation of Extreme Soft-Story
School Building with Friction Dampers Using the
ASCE 41 Standard
  • Presented by Paul E. Oyen

2
Overview
  • Description of Building
  • Project Background
  • Two Solution Procedures
  • Code-Based
  • Performance-Based (ASCE 41)
  • Friction Dampers
  • Comparison of Solutions
  • Conclusions

3
Description of Building
  • Glendale HS - Glendale, CA
  • Built in 1968
  • Administrative Offices Library
  • Structural System
  • Roof
  • Concrete Slab
  • Steel Girders
  • 2nd Story
  • Perimeter Bearing Walls
  • Reinforced Masonry Concrete
  • 2nd Floor
  • Reinforced Concrete Pan-Joist
  • 1st Story
  • Reinforced Concrete Columns
  • Foundation
  • Drilled-piers
  • 18f x 30 deep
  • Groups of 2-4 _at_ each column

4
Project Background
  • Following the 1994 Northridge Earthquake, the
    soft-story condition is identified
  • In 2006, Glendale USD funds rehabilitation as
    part of overall campus modernization.
  • Architectural requirements dictate perimeter
    braces for any strengthening stiffening.
  • Project falls under DSA jurisdiction as a
    voluntary seismic upgrade.

5
Deficiencies
  • Global
  • Soft-Story
  • Weak-Story
  • Local (Non-Ductile Detailing)
  • Little confinement in columns
  • Shear critical beams and columns
  • No top bars in pile caps
  • Partial height reinforcement in drilled-piers

6
Code-Based Solution
  • Design Steps
  • Size steel braces to eliminate code-defined
    soft-story
  • Check braces for elastic design forces
  • Check existing foundations for elastic design
    forces
  • Design foundation strengthening as necessary
  • Detail braces per code
  • Design brace frame connections to building with W
    forces
  • Analysis
  • Linear Dynamic
  • ETABS

7
Code-Based Solution
  • Results
  • Added (10) concentric steel braces frames
  • W14x233 W14x311 braces
  • Add (20) drilled piers to existing pier groups
  • Add new pier groups at each of (4) corners
  • Required frame to existing foundation connection
    strength could not be attained.

8
Performance-Based Solution (ASCE 41)
  • Design criterion
  • Basic Safety Objective for structural components
  • Life Safety in 10/50-yr event
  • Collapse Prevention in 2/50-yr event
  • Design Steps
  • Define desired yield mechanism
  • Add ductility to yielding components
  • Add stiffness to building
  • Analyze check deformation limits
  • Iterate to solution
  • Analysis
  • Nonlinear Static (pushover)
  • PERFORM-3D

9
Friction Dampers
  • Two steel plates sandwiched together by
    pretensioned bolts in long slotted holes
  • Calibrated to slip at specified axial load
  • Provide elastic-perfectly- plastic behavior
  • Two functions in this design
  • Allow large displacements without buckling brace
  • Limit force on foundation and connection to
    structure
  • ASCE 41 does not allow added damping in pushover
    analysis for friction dampers.

10
Performance-Based Solution (ASCE 41)
  • Results
  • Add ¼ steel jackets to (20) columns
  • Add braces at each corner with friction dampers
  • Friction dampers have 200-kip slip load /- 4½
    displacement capacity
  • Selectively cut longitudinal column bars to
    protect against shear failure

11
Comparison of Solutions
  • Code-Based
  • Conventional technology
  • Elastic analysis
  • 64,000 lbs of steel
  • (32) new drilled piers
  • Frames could not be adequately connected
  • Performance-Based
  • Additional testing approval required
  • Nonlinear analysis required
  • 30,000 lbs of steel
  • (12) new drilled piers
  • Predictable behavior ensured

12
Conclusions
  • Prescriptive code requirements led to a costly
    and infeasible solution.
  • Performance-based design concepts allowed for
    reduced construction costs and improved seismic
    performance.

13
Acknowledgements
  • Skip Freet
  • Craig Goings
  • Ron Hamburger
  • James Parker
  • Jaime Rosenbach

14
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com