Title: MRP and Related Concepts
1MRP and Related Concepts
- TLA (Three Letter Acronym) Definitions
- ATP Available to Promise
- BOM Bill of Materials
- DRP Distribution Requirements Planning
- MPS Master Production Schedule
- MRP Materials Requirements Planning
- PAC Production Activity Control
- SOP Sales and Operations Planning
2Where Does MRP Fit?
3Master Scheduling I
- Controls the timing and quantity of production
for products or product families - Primary interface point for actual customer
orders - Coordinates forecasted demand and actual orders
with production activity - Serves as tool for agreement between marketing
and operations (but at a different level than SOP)
4Master Scheduling II
- Feeds more detailed material planning
- Indicates the quantity and timing (i.e., delivery
times) for a product or group of products - More detailed than SOP
- weekly versus monthly
- specific products versus average
- must satisfy the needs of marketing
- must be feasible for operations
5Link between SOP and MPS
Month January February March Output 200 300 4
00
SOP
January (weeks)
1 2 3 4
Push Mowers 25 25 25 25 Self-propelled 35 40 R
iding 12 13
MPS
6MPS Formulas Definitions
- ATPt Available to promise in period t
- EIt Ending Inventory for period t (same as
projected on-hand inventory for next period) - Ft Forecasted demand for period t
- MPSt MPS quantity available in period t
- OBt orders booked for period t
7MPS Formulas
8Detailed MPS for Widgets
On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October 100
Month November November November November December December December December
Week 45 46 47 48 49 50 51 52
Forecast Demand 150 150 150 150 125 125 125 125
Orders Booked 170 165 140 120 85 45 20 0
Master Schedule 300 0 300 0 250 0 250 0
- Notes
- Planning time fence ? cumulative lead time for
product - What seems to be the lot-sizing rule here?
9Projected On-Hand Inventory
On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October 100
Month November November November November December December December December
Week 45 46 47 48 49 50 51 52
Forecast Demand 150 150 150 150 125 125 125 125
Orders Booked 170 165 140 120 85 45 20 0
Projected On-Hand Inventory 230 65 215 65 190 65 190 65
Master Schedule 300 0 300 0 250 0 250 0
i.e. Projected on-hand inventory for week 47
65 300 150 215
10Available-to-Promise
On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October 100
Month November November November November December December December December
Week 45 46 47 48 49 50 51 52
Forecast Demand 150 150 150 150 125 125 125 125
Orders Booked 170 165 140 120 85 45 20 0
Projected On-Hand Inventory 230 65 215 65 190 65 190 65
Master schedule 300 0 300 0 250 0 250 0
Available-to-Promise 65 40 70 230
120
ATP(45) 100 300 (170 165)
65 ATP(47) 300 (140120) 40 ATP(49)
250 (85 45) 120
11Change in Forecast Demand
On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October 100
Month November November November November December December December December
Week 45 46 47 48 49 50 51 52
Forecast Demand 150 150 150 150 150 150 150 150
Orders Booked 170 165 140 120 85 45 20 0
Projected On-Hand Inventory 230 65 215 65 165 15 115 (35)
Master schedule 300 0 300 0 250 0 250 0
Available-to-Promise 65 40 120 230
Are we in trouble yet?
12Change in Orders Booked
On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October On-hand inventory at end of October 100
Month November November November November December December December December
Week 45 46 47 48 49 50 51 52
Forecast Demand 150 150 150 150 125 125 125 125
Orders Booked 170 230 140 120 85 45 20 0
Projected On-Hand Inventory 230 0 150 0 125 0 125 0
Master schedule 300 0 300 0 250 0 250 0
Available-to-Promise 0 40 120 230
Note impact of ATP(45) and on-hand inventory
projections
13Key Points about MPS
- Provides more detail than SOP
- Tracks the following information
- Actual versus forecasted demand
- Available-to-Promise
- This gives sales information for accepting or not
accepting new orders for delivery in a given week
14A Final View of Master Scheduling
SOP
Marketing
Operations
MPS
Rough-Cut Capacity Plan
15Material Requirements Planning
- MRP in the planning cycle
- The logic of MRP
- an extended example
- Considerations of MRP
16Assume that weve scheduled 500 chairs to be
ready five weeks from now.
. . . Now what?
17Material Needed for a Chair
18Chair Structure Tree(aka Bill of Materials)
19Graphic Lead-Time
Week 5
Week 4
Week 3
Week 2
Week 1
Back Support (2 weeks)
Back Assembly
Side Rails (2 weeks)
Cross Bar (2 weeks)
(1 week)
Chair Assembly
Seats (2 weeks)
(1 week)
Leg Assembly
Legs (2 weeks)
(1 week)
Cross Bar (2 weeks)
20Lead-Time Key Points
- To have finished chairs at the beginning of Week
5, we must begin production and order materials
in Week 1. - Exploding the bill of materials tells us when
to order things. - Not much we can do to adjust output of chairs for
the next 4 weeks. Why?
21Material Requirements Planning (MRP)
- We need the following inputs
- Bill-of-Materials (BOM)
- Inventory records
- Master production schedule
- Well get the following outputs
- What items should be ordered
- When each item should be ordered
- How much of each should be ordered
22The MRP Process Starts with the MPS
End items are also known as Level 0 items
23The Parent / Child Relationship
Where do the gross requirements come from? Do you
understand the MRP logic?
24Going Deeper
25
25
25
25Moving from Level 1 itemsto Level 2 items .
. .
25
25
25
Where do the gross requirements for LEGS come
from?
26Combining Requirements Cross Bars
25
25
25
Note effect of differences in lead times and
order sizes on the gross requirements for each
component
27Impact of Longer Lead Times
We cannot do this since the planned order would
be in the past. Thus the 250 crossbars will be
delivered late one week to back assembly. What
does this do to our chair schedule?
25
25
25
28Do You Understand ...
- Why it is important to have an accurate BOM and
accurate inventory information? - Why do we need to freeze production schedules?
- Where do gross requirements come from?
- The is the difference between planned and
scheduled receipts?
29Other Considerations I
MRP
Feedback
Feedback
Planned Orders
Suppliers
Production
30Other Considerations II
- When do we update the system?
- Capacity requirements planning using MRP output
- Pegging
- Lot sizing issues
31Recall ...
25
25
25
Look at the lumpiness of demand for legs
32If we order lot-for-lot
25
25
25
Much smoother demand for legs, lower average
inventory
33Distribution Requirements Planning (DRP)
- Anticipates downstream demand
- Uses this information, not predetermined reorder
points or periodic reviews, to determine when to
order - Computer-based software systems needed to deal
with the added complexity
34DRP Example I
Suppose we forecast demand for Wholesaler A for
the next 8 days (the best time horizon to use
will depend on many factors) Based on this, we
anticipate that Wholesaler A will order on Day 3
35DRP Example II
We extend the analysis to include Wholesaler B
Combined, we expect to see orders on Days 3 and 4
36DRP Example III
The distributor then uses this information to
plan its own orders. In this case, suppose it
takes two days for the supplier to replenish
based on the information, the distributor would
order on Day 1
37DRP Benefits
- Helps improve customer service
- Provides a better and faster understanding of the
impact of shortages and/or promotions - Helps reduce costs
- Inventory
- Freight
- Production
- Provides integration between the stages in the
supply chain
38DRP Constraints
- Accurate forecasts and inventory levels
- Necessary to anticipate correctly when orders
will be placed - Consistent and reliable lead times
- To ensure that orders can be placed and arrive by
the time they are needed - Nervousness
- Even slight changes in demand for downstream
partners can have a significant impact on order
volumes, especially when order sizes are
relatively high