Title: Nancy Cameron Project Manager / PMO Lead 3M / Medical Division IT PMO User Group Teleconference Date: January 8, 2003
1Nancy CameronProject Manager / PMO Lead3M /
Medical Division ITPMO User Group
TeleconferenceDate January 8, 2003
2PMO User Group Teleconference--Agenda--
- Company Name and Description
- PMO / Project Offices / PM Professional
Associations across 3M - PMO structure within 3M/Medical Division IT
Functions / Responsibility - Background Why EPM in 3M/Medical Division IT?
- EPM Toolset
- Project Management Methodology Status and Use
- Future Opportunities
- Top PMO Challenges
3 The 3M Organization
3M's business units comprise six major markets
4PMO User Group Teleconference--Background--
- PMO, Project Offices, Professional Associations
within 3M - PMO structure within 3M/Medical Division IT
53M/MD-IT Project Office--Vision Statement--
- Develop and implement Project Management process,
tools and methodologies to give us - visibility into the work being done and the
process for doing that work. - visibility into the effort expended for that work
- visibility of resource commitment across projects
and their availability for new work - information to help us to prioritize efforts and
new work requests at an organizational level.
6Enterprise Project Management
Methodology
Resource Management
Tools
Templates
Alignment with Business Strategy and Objectives
Portfolio Management
Collaboration
Asset Management
Project Management
Knowledge Management
Phase III
Process
Phase I
Phase II
7Enterprise Project Management--Framework--
Business Alignment Process Improvement Project / Portfolio Mgmt Resource Mgmt Asset Mgmt Knowledge Mgmt
3 2 - 3 2 2 2 3
8PMO structure in 3M / Medical Division IT--Roles
/ Responsibilities--
- Project Manager, Business/IT projects
- Process Improvement utilize Six Sigma
methodology to define,improve and measure project
management/PMO processes as well as all MD-IT
operational processes - Coach project managers and resource managers
- project scheduling
- resource utilization
- project prioritization
- PM Training project scheduling/control
- Documentation
- Future . . . Sharing / learning best practices
9Processes Improvement Opportunities --High Level
Activity Map--
10EPM ToolSet
- System Users / Components Used
- 100 licensed users (MD-IT, Corp IT, Business)
- Time, Workbench, MSProject (import), Resourcer
(ltd) and Planner - Reports built in Business Objects
- Maturity of System Use
11EPM Implementation / Decisions
- Both project non-project time tracked
- Time-Tracking required for all MD-IT resources
- Single source project initiation
- Efforts larger than 24 hours are projects
- Required PM documentation w/ suggested templates
- Weekly project status
- Monthly usage/status reporting
- Criteria / weighting to prioritize projects
12Project Management Methodology-- Done/Yet to do
--
- Utilize
- RUP SDLC methodology
- Process Information Guide (PIG)
- Lotus Notes Team Room project communications
- To Do
- Right-size project templates, documentation for
the types of projects/support we provide - Incorporate aspects of Six Sigma process
methodology into projects common terminology - Profile projects author PMLC methodology into
Planner - Develop common templates, roadmap
13PMO Future Opportunities
- Niku 6 upgrade (web-based)
- Metrics identification / measurement
- Align project/portfolio management processes with
Six Sigma methodology - Embed SDLC, PMLC Six Sigma methodologies within
EPM tools - Charge-back system interface with Niku
Peoplesoft
14PMO Top Challenges
- Selling value of PMO organization to MD-IT
management new sponsorship - Functional responsibility with accountability
- Position Six Sigma process improvement, controls,
measurements within PMO - Expanding Project Management maturity establish
improvement measures - Niku 6 upgrade implementation