Title: Introduction to Linac4 Structure, schedule and goals of the Technical Design Report Maurizio Vretenar AB/RF
1Introduction to Linac4Structure, schedule and
goals of the Technical Design ReportMaurizio
Vretenar AB/RF
2Linac4
- Linac4 (160 MeV, H-) is intended to replace
Linac2 as injector to the PS Booster. - It will double the brightness and intensity out
of PSB (higher energy H- injection). - Is the basis for all LHC upgrade scenarios.
- In a second stage (gt2010), could become the
front-end of the SPL, a high-energy, high
intensity linac replacing the PSB. - Medium-size project (50-60 MCHF), reusing part
of the RF equipment from LEP, to be built in the
period 2007-10. - Support by the DG for a decision on construction
at end 2006.
3From SPL to Linac4
- The SPL (Superconducting Proton Linac) study of a
large (3.5 GeV) SC linac replacing Linac2 and PSB
is going on since 1997. - Large project (gt550 MCHF), decision is expected
from 2010. Conceptual Design Report just
finished, limited work foreseen for the period
2006-2010. - The normal-conducting front-end of the SPL was
first proposed as an injector for the PSB in 2001
and called Linac4. - In the period 2001-06
- General and beam dynamics design
- RD and prototyping of Linac4 structures
- Design and construction of the Linac4 3 MeV
injector - RD work integrated in a EU Activity (HIPPI),
with support from Russia (3 ISTC projects)
and India.
4Linac4 basic design
Linac4, a new 160 MeV H- injector for the PS
Booster
Cell Coupled Drift Tube Linac prototype (40 MeV,
external quads) built at CERN, tuned, to be
tested with RF power
The 3 MeV test stand in preparation in the PS
South Hall (source RFQ chopper line)
Drift Tube Linac tank 1 prototype (3-10 MeV,
permanent quad focusing) design finished, in
construction at VNIIEF (Ru)
5Linac4 design features
- Linac4 is designed for the high duty cycle
required by the SPL (10) but in the first stage
will operate for the PSB only at 0.1 duty cycle
(2 Hz, 500 ms). - Natural location for Linac4 is the PS South
Hall (about 100m space available, possible
connection to PSB next talk) but in the case
of SPL construction it will have to be moved to
another location the linac will be built for
high duty cycle operation, but all the
infrastructure (including most power supplies ?)
will be dimensioned only for low duty. - Result is that Linac4 will be overdimensioned
for beam loss, beam dynamics, thermal and RF
problems, but needs to have a reliability as
high as the present Linac2 (98 availability)
6Linac4 layout in South Hall
7Linac4/SPL beam parameters
8Linac4 Schedule
- Tentative schedule
- 2006 Continuation of RD preparation of test
stand. - 2006 (end) Linac4 Design Report (design frozen).
- 2007 Detailed design (execution drawings!),
definition of construction strategy,
attribution of contracts - 2008-09 Construction
- 2010 End of installation and commissioning
- From the point of view of use of CERN resources,
it goes in the wake of LHC.
Estimate of financial needs (kCHF) for the period
2007-10
9Responsibilities
- General coordination of all proton linac
activities R. Garoby - Linac4 coordination M. Vretenar
- (includes editing of Linac4 TDR and
coordination of EU collaboration) - Coordination for 3 MeV test stand C. Rossi
- SPL/Linac4 coordination committee (core team)
R. Garoby, F. Gerigk, K. Hanke, A. Lombardi,
C. Rossi, M. Vretenar. - Linkpersons are being nominated by the different
groups.
10Technical design committee meetings
- The idea is to have general coordination
meetings aiming at the TDR, about 1/month from
now until the end of the year (duration should
not exceed 1 hour!). - Goal coordinate the overall design and the
writing with the different groups - The meeting should consist in short technical
presentations a tour de table on general
problems. - Is the date-time convenient to all ? (Tuesday
morning conflict with ABOC at 1000,
alternatives Tue 1400, Thu 1100 or Thu 1400). - In parallel, SPL meetings (every 1 or 2 months)
for more general subjects and 3 MeV Technical
Committee meetings (1/month) for detailed
technical subjects concerning the test stand. - A separate working group will analyse in detail
the problems of PSB injection (coordination K.
Hanke).
11The Technical Design Report (TDR)
- Based on the design work done, integrated with
technical descriptions of all components. - Will rely on what has been already written for
the SPL Conceptual Design Report authors who
have already provided their contribution to SPL
CDR2 will be asked only to revise and complete
their contribution. - Every section has a coordinator, who is free to
ask support from other colleagues. - The TDR will be the basis for a cost estimate,
which will be published afterwards, as a
separate document. - Goal of the TDR show to the management that we
have a sound design, and give them a good
estimation of schedule and resources.