Title: AMS02 Thermal Vacuum and Thermal Balance Tests in the Large Space Simulator at ESTEC J' Burger AMS02
1AMS-02 Thermal Vacuum and Thermal Balance Tests
in the Large Space Simulator at ESTECJ.
BurgerAMS-02 TIMCERN, July 23, 2004
2AMS data sheet
- Size 3.2 m x 5.1 m x 4.1 m in test stand
- Mass 6700 Kg8944 Kg test article
- 10817 Kg crane wt.
- Power 2kW
3Two Meetings at ESA/ESTECNoordwijk,
Netherlandsto request overall AMS-02 TVTin
Large Space Simulator (LSS)
- June 11 2003 - Presentation of AMS request to
ESA - S.C.C. Ting Martin Zell Head of Human
Spaceflight ESA - Martin Pohl Wolfgang Supper Head of
Thermal ESTEC - Joseph Burger Jean Jamar Head of
Testing ESTEC - Robert Becker
- July 3, 2003 Follow-up Meeting
- Joseph Burger Jean Jamar Head of
Testing ESTEC - Marco Molina Wolfgang Supper Head of
Thermal ESTEC - Alexander Grechko Gaetan Piret Test
Manager ESTEC - Peter Berges R. Effenberger Managing
Director ETS - Y. Hoyet ESTEC
- Matin Zell Head of Human Spaceflight ESA
4LMSO Visit to LSS
- Trent Martin, Phil Mott, Ross Harold, and Craig
Clark were at ESTEC last year for planning
acoustic test. - Also visited the Large Space Simulator
5(No Transcript)
6Large Space Simulator DimensionsUseable Volume
diameter 9.5m, height 10m
7 8Our Original Request from ESA/ESTEC
- Test equipment
- 300 temperature sensors with DAS and cables
(provided in advance) - Test heaters or IR lamps (TBC)
- Cabling Power (120VDC) and data, including
fiber optics (provided by ESTEC cables inside
the chamber, feedthrough, cables outside chamber
to control room) - Corrugated stainless steel tubes from AMS02
venting ports to external vacuum pumps for He and
TRD gas venting - Space
- Clean room area 150 m2, with 8m crane
height - 40 m2 control room for 13 people with
pc/control terminals - 30 m2 storage room for shipping equipment
- Personnel - people to operate facility, plus 2
people full time during integration/deintegration
(plus crane drivers, ) - Office space for 10-15 people including phones,
fax, xerox, network plugs - Other list of elecrical and vent feedthroughs
needed - Time original request 42 days in chamber plus 3
weeks installation and checkout, 2 weeks
deinstallation and shipping - Mechanical and electrical interface data
- Thermal model of LSS in SINDA/TRASYS and support
in using it
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
1390 ton seismic block can support 60 tonsexternal
dimensions 3.2m x 3.2 mmechanically decoupled
from LSS and building
14Example of mounting HST Solar Wing on block
15Vacuum system typical pumping times
16Vent lines needed for He and TRD gas
- The turbomolecular pumps cannot handle the
nominal He venting rate of 2 mg/s, nor a TRD gas
venting, and a cryopump wont work on He - Vent lines are needed for normal He and TRD gas
venting and venting from the cryosystem burst
disk outputs
17Shrouds and Nitrogen Supply
- C1 covering the main chamber
- LN2 mode (lt100K)(max. heat load 170kW)
- or GN2 mode (150-350K) (max. heat load 10kW)
- C2 covering the auxiliary chamber LN2 mode only
18Solar Simulator
- Horizontal beam 6m diameter, 5m deep
- Maximum intensity at nominal lamp power
2000W/square meter - Intensity distribution in reference plane within
/-4
19Thermal Data Handling
- Thermocouple recording
- - 864 t/c internal
- - 216 t/c direct
- Platinum sensors
- - 98 Pt100
- - 8 Pt500
- Power supplies (P-U-I)
- 40 PSU 24 W - 40V 0.6A
- 94 PSU 240 W 80V 6A
- Possibility to record other signals using
external scanners - Possibility to send some information using RS232
link to EGSE - A total of 2000 channels with a minimum scan time
of 30 seconds - User interface using Dynaworks real time display
20WP1 Standard Facility preparation (seismic
block configuration)
- Chamber configuration
- Meetings
- Procedure reviews
- Data handling configuration
21WP2 AMS specific preparation prior to pre-test
- Provision of t/c harness (300 t/c) (no special
calibration) - Provision of internal harness including loan of
vacuum connectors - Provision of Helium venting line
- Provision of test heater/IR lamp setup (to be
clarified) - Support during installation of the compact
superfluid cooling system around the chamber - Support during installation of the specimen
support stand - Installation of test heater/IR lamp
22WP3 4 days of pre-test
- 4 days of pre-test in VTC modes
- Standard post test activity for facility and data
handling - Pre-test facility data report
- Note Pre-test is to check the facility
configuration including new flanges for line
feedthrough, - submit to vacuum all the test aids (test
support stands, piping, test harness,)
23WP4 Satellite preparation support
- Support to customer during installation of the
specimen (2 persons/3weeks) - Verification of specimen instrumentation
- Chamber close-out
- Normally, we have to do our own handling (crane
operations) of the AMS-02 payload
24WP5 42 days of TB/TV test
- 42 days of TB/TV test including 28 days of TV
test and 14 days of sun illumination
25WP6 Post-Test Activities
- Support for satellite removal (2 persons/1 week)
- Standard data handling post test activities
(including 1 set of all data in electronic
format) - Standard facility post test activities
- Preparation of facility data report
- Support during specimen support stand
26WP7 General Support
- Preparation of office, check-out area and clean
room - 150 sq.m. clean room class 100,000 during 12
weeks - (assembly area)
- 30 sq.m. clean room class 100,000 during 12 weeks
- (shipping equipment storage)
- 40 sq.m. clean room class 100,000 during 12 weeks
- (this is requested control room)
- Provision of offices for 15 persons incl. Phones,
FAX, access to copying machines during 12 weeks - Cleaning of equipment entering the clean room
27ESTEC meeting outcome
- A new stand for the TV/TB tests will be designed
and manufactured by AMS Collaboration - (Shandong University will send a mechanical
engineer to stay at CERN, who will work on
designing the stand with Robert Becker)
28ESTEC feedbackAction Items
- 1. AMS Collaboration should try reducing time
spent inside LSS to 30 days. - 2. ESTEC will investigate the sensitivity of the
facility vacuum gauges to the magnetic field - 3. Thermal model of LSS delivery in the requested
format (SINDA/TRASYS) will be confirmed end of
August, 2003 - 4. AMS Collaboration to check how long AMS can be
disconnected from the vacuum pump
29Status of Action Items fromJuly 3, 2003 Meeting
(1)
- We confirm 30 day thermal vacuum/balance test
schedule, while recommending reserving 12 days
contingency, because of the complexity of the
cryogenic system
30 - Simulations have been run in order to estimate
the time needed for the - Thermal Cycles
- Thermal Balance
- in HOT and COLD phases
31Preliminary TV-Test schedule 30 days
32Response for Action Item 1
- Geneva, September 18, 2003
- Dear Dr. Zell,
- After discussion of the studies of the times
needed to obtain stable conditions during thermal
vacuum - cycling and thermal balance, we can confirm that
we request thirty days in the Large Space
Simulator - for the thermal vacuum test of the AMS-02
experiment. This time includes allowance for pump
down of - the chamber, cycling to the highest and lowest
permissible non-operating temperatures, four
thermal - cycles to the hottest and coldest operating
temperatures, hot and cold thermal balance tests,
followed - By return to ambient conditions, as shown in the
accompanying preliminary schedule. - Following the suggestion of Dr. Eric Ettlinger we
wish to report to you that you may want to set a - contingency of the order of twelve days in the
test time to allow for the possibility of
unexpected - difficulties during the test, especially because
of the complexity of the superconducting magnet - cryogenic system with 2500 liters of superfluid
helium. - With best regards,
- Joseph Burger
- cc Jean Jamar
33Status of Action Items fromJuly 3, 2003 Meeting
(2)
- G. Piret says he has not yet gotten a response
from manufacturer on ability of LSS vacuum gauges
to withstand 5 gauss field at walls. - We offer to make a test in a weak field if ESTEC
supplies a probe and its electronics.
34Action Item 3
- LSS Geometrical Mathemetical Model and Thermal
Mathematical Model available only in
ESATAN/ESARAD (developed by ESA) - We asked model be translated into SINDA/TRASYS
(used by NASA and most others) - We were told this would probably be possible, but
no answer came - Now told they will help support the translation.
Two thermal engineers from SDU are now at CERN
and will work on this with ESTEC and CGS
35Status of Action Items fromJuly 3, 2003 Meeting
(4)
- S. Harrison confirms cryosystem can remain
disconnected from vacuum pump at least one day,
so there is no danger of losing superfluidity in
case of a crane failure while installing AMS-02
in the LSS
36Conclusion
- Martin Zell and Wolfgang Supper have stated they
do not expect any problem for ESA/ESTEC
supporting the AMS-02 thermal vacuum test - M. Zell has funds to start support for test
studies and preparation this year