COSTING THE PRSP - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

COSTING THE PRSP

Description:

Cote d'Ivoire, Senegal. Objectives of the Studies. To assess the experience of a sub-set Africa PRSP countries with respect to ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 12
Provided by: europe8
Category:

less

Transcript and Presenter's Notes

Title: COSTING THE PRSP


1
COSTING THE PRSP
  • Lessons from Country Case-Studies
  • Kasirim Nwuke, ECA

2
Background
  • ECA commissioned ten country studies
  • Ethiopia, Kenya,
  • Zambia, Malawi,
  • Rwanda, Ghana,
  • Sierra-Leone, Burkina Faso,
  • Cote dIvoire, Senegal

3
Objectives of the Studies
  • To assess the experience of a sub-set Africa PRSP
    countries with respect to preparing or
    implementing the PRSP
  • On Content of the PRSP- To examine whether the
    growth strategies are pro-poor and the degree to
    which the social sector, especially health
    (HIV/AIDS), education are reflected in the PRSP
  • On Financing of the PRSP To examine whether the
    PRSP is costed, its link with the MTEF, sources
    of financing it
  • To assess whether capacity requirements for a
    successful implementation were duely considered
  • To assess the degree to which donors were
    beginning to harmonize their policies and
    programs with the countrys PRSP.

4
Ghana
  • Costing of the PRSP is an issue
  • The GoG appears not to have a coherent strategy
    on how it will pay for its programs
  • Financing sources are public sector driven and
    will require greater domestic revenue
    mobilization effort.
  • An effective and efficient public sector is
    required to meet these objectives. But Ghana is
    far from having this.
  • Costing of policy options remains a difficult
    task and where it has been done, quality varies
    from sector to sector
  • Implementation of the PRSP is therefore likely to
    be hampered as a consequence.

5
Zambia
  • Estimates of financing resources based on
    projected domestic resources
  • The underlying assumption of the estimates is a
    4.1 annual growth rate during the period
  • The 17 sectors of activities identified are
    costed The total cost is 1.2 bln (down from
    the initial 4 bln)
  • Only core priority activities are included in the
    current PRSP others postponed to later PRSPs.
  • Financing Sources
  • Tax revenues 18.5 0f GDP
  • Non-tax revenues 0.4 of GDP
  • External Assistance (project/programme grants)
    5.3 of GDP
  • Deficit financing 3 of GDP
  • Financing Gap 2.3 (95 mln in 2003), 1.6 (72
    mln in 2004) expected to be financed by donors.
  • Lessons Projects were ranked and final cost
    arrived at through an iterative process.

6
Kenya
  • There is no evidence that the PRSP was adequately
    costed
  • The financing gap is so wide (Kshs 70 bln) that
    it is considered a wish-list
  • Bids are not appraised against available
    resources (weak priority-setting)
  • There is no mechanism for balancing priorities
    with affordability
  • Donors have reacted by asking the GoK to prepare
    an Action, GAP, outlining how it intends to
    implement the PRSP.

7
Sierra Leone
  • Sierra Leone does not yet have a F-PRSP
  • There is no evidence that the I-PRSP was costed
  • Most of the financing for the I-PRSP came from
    external sources
  • Projected financing requirements of the F-PRSP
    now being finalized 391 million (2002) and 337
    million (2003)
  • Financing gap 89 million (2002) 76 million
    (2003)
  • The gap is expected to be financed by external
    partners.

8
Malawi
  • The PRSP was costed according to three
    categories Statutory (interest payments,
    pensions, gratuities), Statehood (defence, govt
    services), Poverty reduction
  • Basis of costing targets and unit costs
    priority-ranking (limited to the GoM sector)
  • The scope for costing was limited by
  • Capacity constraints
  • Poor assimilation and internalization of costing
    guidelines and methodologies
  • Lack of will to make hard decisions
  • Inadequate consultations
  • Overall, an attempt was made to establish
    realistic estimates of cost.

9
Ethiopia
  • Initial estimated total cost of the program is
    52.5 billion ETB for the period 02/03 04/05
  • This has been revised downward in view of the
    magnitude of the resource gap that emerged to 37
    bln ETB.
  • Revision based on re-proritization of programs
    and activities
  • Financing sources reduction in defense
    expenditures increased domestic mobilization
    cuts in administrative and government services
    moderate external support.
  • Domestic financing likely to be a problem because
    of low tax base, fragile growth foundations, etc.

10
Some Lessons
  • Countries are struggling with the problem of
    costing their PRSP. Some (e.g. Kenya) have not
    done so the PRSP
  • Those (Zambia, Ethiopia) that have attempted to
    cost the program have done so iteratively
  • It appears that this was not done systematically
    the emergence of a large resource gap appears to
    be the impetus for downward revisions in
    estimated financing needs
  • The domestic resource mobilization assumptions
    are weak and the goals of increased domestic
    revenue mobilization unlikely to be met

11
Some (Tentative) Conclusions
  • The weak domestic resource base implies enhanced
    scope for donor support and perhaps for donor
    conditionalities
  • Progress towards poverty reduction is unlikely as
    a consequence to be fairly rapid
  • If PRSs are to be indeed country-driven and
    country-owned, they must be realistically costed,
    projects must be duely ranked and the ranking
    then should influence the content of the PRSP
    itself
  • The costing problems arise either as an incentive
    problem (the amount of debt relief) or a capacity
    problem (countries lack costing capacity) or
    both.
Write a Comment
User Comments (0)
About PowerShow.com